Vent PCMKSome point source fans accommodate plug and play features.

Paul Laplante (LaplanteRicard&Associés), in collaboration with Milan Jovanovic

In last week’s article I discussed the topic of point source ventilation stemming from bath fans, the need for them to be certified for performance and sound levels, Canada’s national building codes pertaining to spot ventilation and finally in Quebec’s case the Novoclimat guidelines and requirements. 

Let’s continue with information that hopefully will round out what you need to properly size /select/supply the proper amount of supply wiring in a given situation.

Many reliable manufacturers such as S&P (Soler Palau), Broan and Nutone now also show performance curves or charts at a level of 0.25 PSI in order to reflect the reality of most installations. In fact, it has been demonstrated when adding a couple of transitions (elbows) and taking into account the type of ducting used, the lengths found on average installs in housing projects or residences that the pressure rises substantially above normal standard HVI test requirements at 0.1 PSI.

How does this affect what you need? First and foremost, determine by rule of thumb, 1 CFM per square foot as a minimum. Once you have arrived at the result, look at the 0.25PSI level on the manufacturers’ data sheets and select the unit that meets the total CFM you calculated at that static level rather than the 0.1PSI.

So in a case where you believe you need 90 CFMs at .25 PSI, chances are you will have to move to a unit that shows 110 CFM at 0.1PSI with either a 4” or 6’’ transition collar (duct adapter).

Toggle Switches

Toggle Switches

Multi level condominium towers and you

The Canadian National Building Code CNB-2005 (Modified) Section 6.2.2 and/or 9.32.3 states in the event of inability to install a central HRV in each unit due to space and design constraints the following as an acceptable and recognised substitute: the installation of a 2 speed bath fan, with a mandatory continuous speed at all times always with the possibility of switching the unit off in the event of prolonged absence. S&P PC110X-2 model for example meets the minimum 90 CFM at 0.1 PSI in high speed at a level of less than 0.3 sones, while performing at 30 to 40 CFM in low speed continuous mode. The use of such a fan then meets or exceeds the minimum air change requirements of 1 complete air change in the housing unit, every 3 hours.

The catch: to avoid depressurization the above installation must have a way to compensate for the air extracted with new air. Depressurisation has negative effects on buildings (it can permit radon gas infiltration) and/or on mechanical products such as water heaters, fireplaces or stoves not equipped with outside air supplies (direct vents). Avoiding depressurization can be accomplished by means of a small duct system and 120 V damper and contactor linked to the operation of the fan while it is in continuous mode. Some colder areas of the country include a duct heater within the configuration. 

How many supply wires do I need?

It is critical when using a 2-speed, positive off during prolonged absence to provide for a 3-wire feed in leading to a two commutator wall plug. In this fashion a PC110X-2 for example will be in the ‘’on’’ position of one of the commutators, switch the fan on continuous low. This must be first satisfied in order to then energise the second high speed thru the second wall switch. The key is that end user, should he select the off function cannot bypass the continuous low function when he arrives back from his prolonged absence and forgets to rearm it, and in it’s stead attempt to put the fan on high speed. 

Vent Plug and Play

How it’s done.

Are 3 wires enough?

If I may, I would say no, not with today’s multi-featured bath fans. If anything, I would suggest in renovation projects to provide for 5 to 6 wires to the units.

Why? That’s a lot of wire in case… Yes but many of today’s fans can accept after-install accessories that upgrade them from simple fans to smart fans. Some accept add-on motion detectors, humidity detector, and even a complete change of grills to transform the ordinary unit in a beautiful light/night light grill configuration like S&P PC50 to 150 CFM units. 

Finally, you are unsure that the fan you have selected and put in your truck to go on the job site is adequate for the job at hand. You get in the install area, make a quick recheck of the CFMs required with that rule of thumb I described and… the room is now larger than anticipated or the owners decided to add a separate shower or spa.

What are you going to do? Install the fan you have that you now know will not meet the needs of the area? Return it to your wholesaler? What a waste of time.

Consider the available alternates that the new DC motor technology has given the forward thinking ventilation manufacturers and your problems are solved.

Some manufacturers now offer a fan like Soler Palau’s PCD110 series that, through a series of selectable switches on the unit, will provide you from 80CFM- 90-110-120 right up to 140 CFMs.The performances will be certified providing you install it with the corresponding 4” or 6” inch duct collar that is provided. I suggest you use a 6’’ preferably for 110CFM and up.The technology even gives you the choice of selecting between one with a humidity sensor or another with a motion detector.

I do hope I have managed to give you more insight into the do’s and don’ts related to the spot ventilation market for bath fans. I am also hopefulthat with this information in mind that you will continue to distinguish yourself as the go-to company, contractor, builder,promoter,architect or engineer for your knowledge, your push for the best, and the best satisfaction experience for the one who will benefit most from that all this care — your end user and customer for a long time to come.


 

Paul Laplante is a manufacturing agent and co-owner of LaplanteRicard& Associates. He has worked in the electrical and ventilation fields for more than 35 years. Milan Jovanovic has worked in the field of mechanical ventilation for a number of years and is a former president of A.S.H.R.A.E.’s Quebec City chapter (2005-2006).

 

Changing Scene

  • Prev
  Electro-Federation Canada (EFC) and its members are proud to support Canadian university ...
  In the context of the energy transition currently unfolding where reducing greenhouse gas ...
  Nova Scotia Power plans to put the power in our customers’ hands by introducing ...
  Ontario's soaring electricity bills have driven numerous factories out of the province ...
CSA Group has announced that Shawn Paulsen, Manager of Conformity Assessment, CSA Group, has been ...
For the fifth consecutive year, Rittal Systems Ltd., is being certified as a Great Workplace ...
  A contract worker received an electrical shock after coming into direct contact with ...
  Rittal Systems has announced Franklin Empire has joined its distribution/partner network ...
  FortWhyte Alive is unveiling the largest solar installation in the City of Winnipeg. ...
  In partnership with TM4 Inc. and Cummins Inc., STL recently announced plans to test two ...

Irwin Beron RAB Design has announced the retirement of President, Irwin Beron.  After 50 years in the lighting industry, Irwin has decided to step down as President and hand over the reins to his eldest son, David Beron.  David will assume the position of President, effective immediately.  Irwin will remain on as Chairman, which will allow him to enjoy some well-deserved rest and relaxation with his lovely wife Lynette and seven grandchildren, yet still free to impart his many years of experience and expertise whenever possible as Chairman of RAB Design. Irwin has been serving as President of RAB Design Lighting since 2002.  He acquired the company during a difficult period and through grit, determination and hard work, turned it around to make it one of Canada’s most respected lighting companies.

 

Read More: Irwin Beron Retires as President of RAB Design... 

 

 

 

Electricians Provide Assistance in TD Centre's 50th Anniversary Illumination Project

Contractors Guild, Ainsworth, Symtech, Plan and ACML donated their services to temporarily reconfigure the buildings' automated lighting systems, while a crew of staff and volunteers worked to open and close blinds on over 6,000 windows across the TD Centre's five towers to create the message "Less is more or" in 100-foot-tall lights.

A media statement called it the largest public art project of its kind undertaken anywhere in the world.

Read more: Electricians Provide Assistance...

 

Codes and Regulations Brought to You by the CSA Group

  • Prev
In this article: Section 58 — Passenger Ropeways and Similar Equipment. Rule 58-000 ...
  Unauthorized CSA Group certification marks have been found on wiring by Triumph Cable ...
In this article: Section 52 — Diagnostic imaging installations. The CE code is a ...
In this article: Section 46 — Emergency Power Supply, Unit Equipment, Exit Signs, and ...
  In this article: Section 44 — Theatre Installations. The CE Code is a ...
CSA has published C22.2 No. 60947-7-3, the harmonized standard for low-voltage switchgear and ...
  Electric welders. The CE Code is a comprehensive document. Sometimes it can seem ...
  In this article: Section 40 — Electric cranes and hoists. The CE Code is a ...

CSA

 

By William (Bill) Burr

In this article: Section 56 — Optical fibre cables. Section 56 is a supplementary or amendatory section of the code and applies to the installation of optical fibre cables in conjunction with all other electrical systems. Rule 56-002 provides a special terminology definition for an Optical Fibre Cable — a cable consisting of one or more optical fibres that transmits modulated light for the purpose of control, signalling or communications.

Rule 56-102 outlines that there are three types of optical fibre cables.



Tools for the Trade

  • Prev
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...
  This new lock box is ideal for group lockout situations with multiple isolation points ...
  Greenlee has taken their standard storage boxes to the next level with the limited ...
  The SureTest circuit analyzers "look behind walls" to identify wiring problems that can ...
  The Ideal Dispenser is equipped with high-quality adhesive and 3 mil thickness that ...
  The Adjustable cable stripping tool has an intuitive blade design that allows users to ...
  The SIMpull CoilPAK completes the SIMpull Circuit Management System, taking heavy, ...
  The Javelin is a new product that makes drilling holes through stud walls easier. ...

Product News

  • Prev
  Liteline's LUNA is engineered for maximum heat dissipation and eliminates the need ...
Magic Lite 2013 Ltd. has announced a new selection of decorative lighting options for a multitude ...
  Arlington’s recessed In Box Cover Kits offer the best way to install a receptacle ...
  Arlington’s Countertop box kits with round plastic boxes and brass or nickel-plated ...
  Arlington’s new FLBC4502 4.5" non-metallic concrete floor box has six conduit ...
  Designed for time-savings and a neat, flush installation, Arlington’s DROP IN ...
  Arlington’s non-metallic Mutli Purpose Box is the labor-saving solution to ...
Standard's LSHOP series is an integrated solution for quick and easy installation; no wiring ...
  LUBO Lighting International Inc. has a new generation of outdoor lighting fixtures with a ...
  Arlington's Bare Wire Ground Clamp is made of solid brass with brass screws that is easy ...

 

Peers & Profiles

  • Prev
Andrew MacLeod is a territory sales manager with Leviton Manufacturing of Canada in British ...
  Floyd Lau founded Amptek Technologies in 2002 as an end to end engineering design ...
Mike Marsh, President and CEO of SaskPower, has been a leading figure in Saskatchewan’s ...
Gordon MacDonald is a cheerful, driven individual who loves to be challenged, a trait that suits ...
  Most of us have a difficult enough time managing one job and a home life. However, some ...
  Since 2012 Barnstormer has advanced the abilities of their brewery with the installation ...
  Electrical Industry Canada was recently given the unique opportunity to see ...
  Vickery Electric has been providing electrical services to the Whitby area since 1923, ...
Safety standards in the electrical industry are constantly evolving, which requires that ...
Newman Electric was founded in 1995 and has established itself as a leading electrical contractor ...

Copper $US Dollar price per pound

Gordon M

 Gordon MacDonald is a cheerful, driven individual who loves to be challenged, a trait that suits him well as a lighting specialist overseeing retrofit projects for Rexel in New Brunswick and P.E.I. He also has had a unique introduction to the field he now works in. 

Gordon was born and raised in Moncton, New Brunswick and has lived there for most of his life. He has an incredibly busy home life that extends to his children, stepchildren and grandchildren. Beyond family life he enjoys “playing guitar and piano, going target shooting, cooking BBQ, trying new foods and learning new things.”

How One Hospital Is Improving Patient Care with Advanced Analytics Demand for healthcare is outstripping capacity, but Toronto’s Humber River Hospital has a solution: a digital Command Centre powered by GE’s Wall of Analytics. As populations grow and age, many hospitals are being stretched past their limits. Rather than apply temporary or partial fixes to address the challenges that underlie this busy, acute care hospital, Toronto’s Humber River Hospital has chosen to implement a holistic, state-of-the-art hospital command centre that will enable it to achieve radical gains in quality and efficiency.

The hospital partnered with GE Healthcare Partners to conceive, design and build the new 4,500 square-foot command centre, a cornerstone of which will be GE’s Wall of Analytics that processes real-time data from multiple source systems across the hospital.

Read more: How One Hospital is ...

 

Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
2016 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil