Bill BurrIn this article: Section 52 — Diagnostic imaging installations. The CE code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook**, but will hopefully provide some help in navigating the code.

Rule 52-000 Scope states that Section 52 is a supplementary or amendatory section of the code and applies to the installation of X-ray and other diagnostic imaging equipment operating at any frequency, but does not provide any specifications for safeguards against radiation. Information on radiation safeguards is contained in the series of Health Canada Safety Codes for radiation protection. The CSA CEC Handbook provides additional explanations and tables.

Rule 52-002 provides some special terminology for this section, and defines momentary and long-term ratings of 20 seconds and 5 minutes respectively for operation of applied x-ray and computerized tomography equipment.

Rule 52-004 provides guidelines for guarding of high-voltage parts, and requires that high-voltage parts be contained within bonded to ground metal enclosures, or within separate rooms or enclosures where a circuit control switch controlling the diagnostic imaging equipment is interlocked, to be open when the door is open and unlocked, and be insulated from the enclosure. In addition, high-voltage circuit conductors must be of the shockproof type. If a milliammeter is provided, it must be either connected in the bonded-to-ground circuit conductor, or guarded, if connected in the high-voltage conductor.

Rule 52-006 permits mobile diagnostic equipment, and permanently connected diagnostic equipment on a 30 amp or less branch circuit, to be supplied with a plug and hard-usage cable or cord.

Rule 52-008 specifies that a disconnect must be placed in the supply circuit in a location accessible from the radiation control of the diagnostic equipment. The rating of the disconnect for X-ray or computerized tomography equipment is based on 100% of the power input required for the long-time rating of the equipment, or 50% of the power input required for the momentary rating of the equipment, whichever is greater. For equipment on a 120volt, 30amp circuit, the required disconnect may be a receptacle and plug of the appropriate size.

Rule 52-010 exempts transformers and capacitors, forming part of diagnostic imaging equipment, from the requirements of Section 26. This equipment must comply with the CEC Part II product standard for the equipment. Capacitors must be provided with a means for automatically discharging and grounding the plates when the supply is disconnected. This is not required if the current-carrying parts of the capacitors and conductors are located 2.5 meters or more above the floor and accessible to only authorized persons, or, if located within 2.5 meters of the floor, within

• metal enclosures that are bonded to ground, or
• enclosures of insulating material

Rule 52-012 provides for protection where step-up transformers are used for diagnostic equipment. The low-voltage circuit of the step-up transformer is required to have an overcurrent device with no exposed live parts, installed as part of or adjacent to the equipment that protects the high-voltage radiographic circuit from all fault conditions. Where the above overcurrent device is too large to protect other fluoroscopic or therapeutic circuits on the equipment, additional overcurrent protection needs to be installed to protect these circuits. In the case of portable equipment, the above requirements also apply. However, an exemption can be applied if all high-voltage parts are enclosed in a single metal enclosure, bonded to ground. Where more than one apparatus is supplied by a common high-voltage source, other switches must be installed to independently disconnect each apparatus from the high-voltage source.
Rule 52-014 reiterates that all non-current-carrying parts of apparatus, including ancillary equipment, must be bonded to ground in accordance with the requirements of Section 10.

Rule 52-016 provides the requirements for determining ampacity of supply conductors and rating of overcurrent protection for diagnostic imaging equipment. For a single piece of equipment, use the larger of

• the long-time current rating of the equipment, or
• 50% of the momentary current-rating required on a radiographic setting

Note that this information is contained on the equipment faceplate.

Where more than one piece of diagnostic equipment is supplied, the rating of the supply conductors and overcurrent device is based on

• the sum of the long time current ratings of all the equipment supplied by the circuit, or
• Tthe sum of 50% of the maximum momentary current rating for the two largest units supplied, plus 20% of the maximum momentary current rating of the other units, when the equipment is on a radiographic setting

In the next installment, we will be discussing Section 54 — Community antenna distribution and radio and television installations.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA
** Note the CEC Handbook is also published by CSA.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

Changing Scene

  • Prev
Kiashke Zaaging Anishinaabek (KZA)/Gull Bay First Nation (GBFN) and Ontario Power Generation (OPG) ...
The BCEA's Woman's Network THRIVE Summit is taking place on October 4th at the Executive Inn ...
NSI Industries has announced the acquisition of electrical products manufacturer Bridgeport ...
The National Electrical Trade Council (NETCO)—jointly sponsored by International Brotherhood ...
IDEAL Electrical has launched its fourth annual national competition to find the best ...
IDEAL Industries Canada has announced the appointment of Sean Bernard as Regional Sales Manager to ...
In his new role as Stelpro's Vice-President, Sales and Business Development, ...
The Support Equity and Under-Represented Groups project will address the under-representation of ...
Show your support by sharing a photo or experience of how a lineworker has made an impact in your ...
Eleven highly accomplished Hamiltonians are being honoured by Mohawk College as Distinguished ...

Electrician Forum Brought to you by Schneider Electric

As industry experts you know the products you use everyday better than anyone and should have input on what information you receive about products and what could improve them.

Therefore, we want your insight on the biggest challenges or issues you face when installing loadcentres, breakers (CAFI, GFI's…) and other surge protection devices. We ask that you do not provide product specific details but rather your general issues and concerns or any questions that have come to mind while working with these product types. Provide us with your valued expert insight into the issues you have faced so manufacturers can better inform you about the installation and use of these products. Lets generate some discussion that will help guide the Industry.

Make your comments  HERE

 

ABB PortalThe ABB eFinder portal simplifies the process of locating inventory from ABB’s selection of products used for connection and transmission of electrical power. Customers may now search online for ABB Installation Products and can purchase them from the distributor who has the products in stock. Once the product is located, the customer may buy it from the distributor by connecting directly to the distributor’s e-commerce page and placing the products in an online shopping cart for the final purchase transaction.

 

 

 

Read More

 

 

 

Codes and Regulations Brought to You by the CSA Group

  • Prev
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
In this article: Tables — Part B. This section of the Code contains 99 tables of essential ...
In this article: Section 58 — Passenger Ropeways and Similar Equipment. Rule 58-000 ...
  Unauthorized CSA Group certification marks have been found on wiring by Triumph Cable ...
In this article: Section 52 — Diagnostic imaging installations. The CE code is a ...
In this article: Section 46 — Emergency Power Supply, Unit Equipment, Exit Signs, and ...
  In this article: Section 44 — Theatre Installations. The CE Code is a ...
CSA has published C22.2 No. 60947-7-3, the harmonized standard for low-voltage switchgear and ...
  Electric welders. The CE Code is a comprehensive document. Sometimes it can seem ...

 

PolycarbonateElectronic waste is a huge issue, with Statista estimating nearly 50 million metric tons were generated globally last year alone.* Some of the materials traditionally used in LED lamp and luminaire components contribute to e-waste, and the industry is seeking more sustainable material alternatives. Thermally conductive (TC) polycarbonates, like those from Covestro, can replace aluminum in heat sinks, providing just such a replacement option. (The back enclosure of the A.L.P. Lighting Recruit wall mount fixture, shown in photo, is injection moulded from Makrolon TC polycarbonate.)

 

Read More 

Latest Articles

  • Prev
Pick up a newspaper or scan your preferred electronic newsfeed and you’ll likely see a series ...
Britech Corp, one of Canada’s largest heating cable companies has signed a formal agreement ...
Electrical enclosures serve to protect electrical devices from adverse environmental influences, ...

 

White PaperBy Steven Carlini, Schneider Electric

Internet use is trending towards bandwidth-intensive content and an increasing number of attached “things.” At the same time, mobile telecom networks and data networks are converging into a cloud computing architecture. To support needs today and tomorrow, computing power and storage is being inserted out on the network edge in order to lower data transport time and increase availability. Edge computing places data acquisition and control functions, storage of high bandwidth content, and applications closer to the end user. This white paper explains the drivers of edge computing and explores the various types of edge computing available.

Read More

 

 

Tools for the Trade

  • Prev
  IDEAL Industries has introduced Combination Drill Taps to its tool lineup. Combining the ...
  Stripping and crimping device, 100 - 240 V input voltage, for insulated ferrules with a ...
Professional all-in-one cutter/stripper for coaxial and twisted pair cables     ...
  Klein Tools' Coax Explorrer 2 tests coaxial cable and maps up to 4 locations   ...
  Ideal Industries' T-14 wire stripper s are ideal for all professionals working within the ...
  The ATS850 conveyor eliminates all types of electro static discharge requirements. ...
  Lorik Tool & Automation has the experience and ability to manufacture a variety of ...
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...

Project DotWhether sitting in a second-floor meeting space, or entering the lobby, it’s impossible not to notice the playful lighting fixtures at Dot Foods, Inc. At night, even passers-by can enjoy the circular fixtures that are visible through the two-storey pane glass windows of its Mt. Sterling, Illinois location.

Dot Foods is the largest food industry redistributor in the U.S. and has been expanding and renovating throughout its headquarters over a couple of years. The main lobby area is the latest to get an upgrade, and as the first point of contact for many entering the facility it had to leave an instant impression.

 

 

Read More

 

Product News

  • Prev
Now even more choice in the Compar range from ERCO: the new linear surface-mounted luminaires ...
Designed by Piero Lissoni, Light Bell is a suspended general lighting luminaire for indoor ...
MaxLite's LED High Bay DirectFit Lamps are the plug-and-play, energy-saving replacements for HID ...
EarthTronics has introduced two new energy efficient, High Output High Bay Fixtures featuring an ...
AEMC’s Thermal Imaging IR Camera Model 1954 is equipped with infrared thermography detection ...
Identify equipment problems early before a failure can occur by monitoring the health of motors, ...
The new TRI line comprises a set of high isolation, regulated DC/DC converter series which come in ...
One of the core requirements of flexible production is the ability to quickly install machines and ...
EarthTronics introduces its new Slim LED Recessed Downlight Series designed for energy efficiency ...
Luminaire manufacturers’ efforts to deliver consistent, quality light across their luminaire ...

 

Strip LightsEcoGen's Flexible Neon Series is suitable for both exterior and interior applications on residential or commercial buildings. The use of LED supposed to lights is quickly rising in terms of building design on a global level. These simple lights are more efficient, greater and are easy to install. When it comes to LED Flexible Strip lighting, you have a number of different options available and when it  comes to the time to decide, which one is best for you, there are different things that should be considered.

 

 

 

Read More

 

 

Peers & Profiles

  • Prev
Ouellet Electric Heating began humbly in 1960 with Charles-Emile Ouellet, who started manufacturing ...
Justin Harris is a Programmer/Electrician for COREngineering, a New Brunswick based mechanical ...
Bill Maki is an Electrical Engineer from Thunder Bay, Ontario working as a Control Systems ...
Benedict Electrical Contracting Limited is a locally owned and operated family business in Owen ...
Spark Power Corp. is one of North America’s leading independent providers of integrated ...
Marcia Ranger is a master construction and maintenance electrician, as well as a college professor ...
Con’s Electric Company Limited was established in 1985. Based in Timmins Ontario, only 700 ...
Mark Unsworth is an electrical engineer with over 35 years of experience in project management, ...
Manygo Ho is an electrical designer with AECOM’s Buildings and Places group. Manygo designs ...
Don Neigel is Manager of the CSA-certified panel shop at Delta, BC’s Optimil Machinery. ...

Copper $US Dollar price per pound

Electrical Industry Newsweek

This special weekly newsletter has the broadest reach of those that are involved in all aspects of the electrical industry including electrical construction and maintenance professionals and electrical specifying engineers across Canada. EIN is designed to provide electrical professionals’ insight and intelligence on those developments in the industry that effect design, specification, installation of electrical equipment. From corporate news to new technologies and insightful opinions EIN will become your first read in the electrical industry in Canada. Published weekly – every Tuesday
Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2019 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil