In this article: Section 40 — Electric cranes and hoists. The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

40-000 Scope — this is a supplementary or amendatory section of the code and applies to the installation of electrical equipment and circuits for electric cranes, hoists, and monorails. The CEC Handbook provides additional notes and diagrams to better explain this section.

40-002 Supply conductor sizes — because of the short duty of crane and hoist motors, supply conductors are selected from Table 58, which specifically applies to crane and hoist installations.

40-004 Conductor protection — supply conductors for the main contactors of cranes and hoists must be in raceway, armoured cable, or mineral insulated, aluminum-sheathed or copper-sheathed cable. There is an exception to this where a conducting track of conducting rails is used as per 40-018. Where conductors supply the crane or hoist equipment directly and where a flexible connection is necessary, flexible type cord or festoon cable is permitted provided there is a take-up device provided to prevent damage and contact with the floor.

40-006 Overcurrent protection — for main contact supply conductors or directly supplied equipment, the overcurrent protection must be selected as per Rule 28-200 and Tables 29 and D16 for the motor load, plus any allowance as per Rule 14-104 where conductors have been selected with capacity for the other loads on the crane or hoist.

40-008 Disconnecting means — all ungrounded conductors of the main contact conductors must be capable of being simultaneously disconnected quickly for safety in an emergency and for maintenance. The disconnect must be within sight of the main contact conductors or the equipment. In addition, the disconnect must be accessible and be operable from the ground or floor over which the crane or hoist operates.

40-010 Main contact conductors — this rule requires that where there are bare main contact conductors, they must have an ampacity not less than the conductors supplying them and, if wire, shall be not smaller than No. 4 AWG copper, or No. 2AWG aluminum. If the conductors are more than 18 m long, then the minimum size must be No. 2 AWG copper or No. 1/0 AWG aluminum unless intermediate strain relief is provided by clamp type insulating supports. Bare conductors may be hard drawn copper, aluminum wire, or steel or other suitable metal in the form of angles, tees, T-rails, or other rigid shapes.

40-012 Spacing of main contact conductors —because bare main contact conductors depend on free air space to provide insulation between phases and to ground, this rule outlines the minimum support separation required of main contact conductor wires installed in a horizontal plane of 75mm for monorail hoists and 155 mm for other than monorail hoists. If installed in other than a horizontal plane, the separation of the main contact conductor wire supports must be 200mm. They should also be supported so that the extreme limit of displacement maintains a separation of 38mm from any surface. Where the bare main contact conductors are rigid, the supports must provide a minimum separation of 25mm between conductors, collectors, and any surface.

40-014 Supporting of main contact conductors — in addition to the spacing required in rule 40-012, the main contact conductor wires must be stretched between strain insulators at each end and supported throughout the length at 6m intervals. If building conditions preclude supporting at 6m intervals, it may be increased to a maximum of 12m intervals providing the separation between contact conductors is increased by the same proportion. In the case of rigid main contact conductors, insulated supports must be spaced at intervals of up to 80 times the vertical height of the conductor but not more than 4.5m. Refer to the CEC Handbook for diagrams illustrating support spacing and calculation notes.

40-016 Joints in rigid contact conductors — this rule outlines the importance of ensuring that any joints made in rigid main contact conductors must maintain the same ampacity of the conductors over the joint to eliminate any overheating.

40-018 Use of track as a conductor — this rule permits a single monorail, tramrail or crane runway track to be used as one of the main contact conductors or supply circuit conductors for one phase of a 3-phase circuit, providing it is derived from a single isolating transformer, does not exceed 300 v, is bonded to ground (see Rule 10-1100 to 10-1108), and any joints meet rule 40-016.

40-020 Guarding of contact conductors — requires that all contact conductors be guarded against inadvertent contact with bare current-carrying parts unless incorporated in an enclosed contact assembly. In addition, as long as a minimum clearance of 6 m between bare contact conductors and grade, floor, or any working surface (including a catwalk) is maintained, guarding of bare contact conductors may not be required.

40-022 Contact conductors not to supply other equipment — this rule prohibits the contact conductors supplying the crane, hoist or monorail feeding other equipment not essential to the operation of the crane, hoist or monorail.
40-024 Bonding — as per Rule 10-406 all exposed non-current carrying parts shall be bonded to ground. In addition, in the case of a track or rail used as a conductor, it shall be bonded in accordance with Rule 40-018. Note that metal wheels on metal rails may provide a low impedance grounding path. A flexible supply connection as per Rule 40-004(2) must contain a bonding conductor.

In the next instalment, we will be discussing Section 42 — Electric welders.

The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

 

Changing Scene

  • Prev
Eleven highly accomplished Hamiltonians are being honoured by Mohawk College as Distinguished ...
Canada’s Minister of Natural Resources recently announced the Governor in Council has ...
ABB recently won an order of eBus charging solutions to support TTC as it modernizes its service ...
A consortium of Canadian energy organizations has been shortlisted to develop the electricity ...
Skills Ontario Summer Camp is a week-long day program for kids entering Grades 7-9.   ...
  Glen Dimplex Americas is proud to announce that its Vancouver facility was recently ...
May 13 to 19 is Powerline Safety Week in Ontario, which is meant to inform people across the ...
Divisional Lighting Manager Salma Siddiqui, the initiative will focus on making Westburne the ...
As of April 30, Natural Resources Canada has new dry-type transformer energy efficiency ...
Ontario Power Generation (OPG), in partnership with the Six Nations of the Grand River Development ...

Electrician Forum Brought to you by Schneider Electric

As industry experts you know the products you use everyday better than anyone and should have input on what information you receive about products and what could improve them.

Therefore, we want your insight on the biggest challenges or issues you face when installing loadcentres, breakers (CAFI, GFI's…) and other surge protection devices. We ask that you do not provide product specific details but rather your general issues and concerns or any questions that have come to mind while working with these product types. Provide us with your valued expert insight into the issues you have faced so manufacturers can better inform you about the installation and use of these products. Lets generate some discussion that will help guide the Industry.

Make your comments  HERE

 

 

ABB CMD

ABB has appointed Maryrose Sylvester as Country Managing Director (CMD) and Head of Electrification for the United States, effective August 1, 2019.

In the CMD role, she will succeed Greg Scheu, who will support a smooth transition until his retirement at the end of October 31, 2019.

Sylvester was most recently President & CEO of “Current, powered by GE”, a GE startup business that was acquired in April by New York-based private equity firm American Industrial Partners.

 



Read More

 

 

 

 

CyberSecurityDuring a recent Industrial Control Systems Joint Working Group meeting, representatives from the National Electrical Manufacturers Association (NEMA), U.S. Department of Defense (DOD) and International Society of Automation (ISA) outlined a new program to address the growing risk of unprotected and under-protected building control systems in the U.S. and abroad.

Building owners, users, and manufacturers of control systems continuously work to find practical ways to create safe and more secure environments.

 

 

Read More

 

 

Codes and Regulations Brought to You by the CSA Group

  • Prev
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
In this article: Tables — Part B. This section of the Code contains 99 tables of essential ...
In this article: Section 58 — Passenger Ropeways and Similar Equipment. Rule 58-000 ...
  Unauthorized CSA Group certification marks have been found on wiring by Triumph Cable ...
In this article: Section 52 — Diagnostic imaging installations. The CE code is a ...
In this article: Section 46 — Emergency Power Supply, Unit Equipment, Exit Signs, and ...
  In this article: Section 44 — Theatre Installations. The CE Code is a ...
CSA has published C22.2 No. 60947-7-3, the harmonized standard for low-voltage switchgear and ...
  Electric welders. The CE Code is a comprehensive document. Sometimes it can seem ...

 

IoTElectrical contractors are approaching a tipping point in terms of pursuing roles and opportunities in the growing market of smart buildings, according to Smart Buildings And Internet of Things (IoT) Impact on Electrical Contracting, a new report from Electri International. Part 1 of this 3-part series provided an overview of the IoT challenges facing electrical contractors; Part 2: opportunities. Here in Part 3: two case studies.

Manitoba Hydro Place 

The first LEED Platinum Certified building in Canada, Manitoba Hydro Place (MHP) is considered the country’s greenest and most energy-efficient building. 

Read More 

Lighting LEEDThe Rivierè-des-Mille-Îles Park encompasses an array of natural forest, waterways, marshland and shoreline in the city of Laval, Quebec. With its exceptional biodiversity, it’s a unique natural attraction for the city, and welcomes over 150,000 visitors annually.

The Exploration Centre is the latest addition to the park and was built as the main visitor welcome area. The pavilion stands out with its modern and avant-garde architecture, and magnificent view of the nearby river.

 


Read more about Lighting Design...

 

 

Tools for the Trade

  • Prev
  IDEAL Industries has introduced Combination Drill Taps to its tool lineup. Combining the ...
  Stripping and crimping device, 100 - 240 V input voltage, for insulated ferrules with a ...
Professional all-in-one cutter/stripper for coaxial and twisted pair cables     ...
  Klein Tools' Coax Explorrer 2 tests coaxial cable and maps up to 4 locations   ...
  Ideal Industries' T-14 wire stripper s are ideal for all professionals working within the ...
  The ATS850 conveyor eliminates all types of electro static discharge requirements. ...
  Lorik Tool & Automation has the experience and ability to manufacture a variety of ...
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...

Product News

  • Prev
Proper illumination to exit a premises during a power failure is critical for safety. Lightheaded's ...
Emerson today introduced the new Appleton ATX FNLED non-metallic, hazardous area linear luminaire ...
Molex launches a Micro Power Distribution Box (µPDB) Sealed Module with two versions: ...
Eureka, a decorative lighting solutions company, recently announced the release of the Lily ...
Audacy Lighting Controls is the easy-to-program mobile app developed to operate your Audacy ...
AEMC's Ground Resistance Tester Model 6472 now includes two additional test voltages of 10 and 60 ...
Following their recent improvements to the IPL series architectural light, First Light Technologies ...
The BoxLED is available in both LED highbay and LED floodlight models. The BoxLED as been ...
Arlington's new cord grips are ideal for solar jobs - and more - requiring the connection of ...
Littelfuse, a global manufacturer of technologies in circuit protection, power control and sensing, ...

 

Fluke Insulated Hand ToolElectricians and facility maintenance technicians should ideally work on de-energized electrical equipment, but that isn’t always possible, so their hand tools should provide as much protection as possible. The new Fluke1000 V Insulated Hand Tools are designed to keep workers safe in hazardous areas and are rugged enough to use in the toughest environments without breaking.

Fluke Insulated Hand Tools are manufactured using state-of-the-art German steel to Fluke’s exacting standards for quality, ruggedness, and reliability. 

 


Read More

 

 

Maxlite TrimaxMaxLite has earned a U.S. patent for the innovative linking design features of its TriMax Vapor Tight fixture. This patent, issued as U.S. Patent No. 10,168,012, brings the number of MaxLite’s issued and pending patents worldwide to 106, a testament to MaxLite’s focus on developing cutting-edge innovation.

The TriMax is engineered with connections at the top of the fixture that maintain a hermetic seal when two or more 4’ fixtures are linked together. By simply snapping a toolless connection bracket into place, installers can uniquely create an IP66 rated lighting solution that is 8’ or longer. 

Read More...

 

Peers & Profiles

  • Prev
Con’s Electric Company Limited was established in 1985. Based in Timmins Ontario, only 700 ...
Mark Unsworth is an electrical engineer with over 35 years of experience in project management, ...
Manygo Ho is an electrical designer with AECOM’s Buildings and Places group. Manygo designs ...
Don Neigel is Manager of the CSA-certified panel shop at Delta, BC’s Optimil Machinery. ...
New Brunswick Power recently struck a deal with Joi Scientific to develop an innovative technology ...
The Shock Doctors is an electrical contracting company operating out of Orillia, Barrie and ...
Michael Gindalang works for Dupar Controls as a panel builder for the elevator and keypad industry. ...
Energy Efficient Lighting is a LED lighting manufacturer with nearly 30 years of industry ...
Matt Stanson is a master electrician with over 30 years of experience. He now leads a team of ...
After eight months, 263 events, 17 broken clocks, and thousands of competitors, Ideal ...

Copper $US Dollar price per pound

Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2019 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil