In this article: Section 42 — Electric welders. The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Rule 42-000 Scope — states that Section 42 is a supplementary or amendatory section of the code and applies to the installation of electric welders. The CEC Handbook provides additional notes and diagrams to better explain this section. There are two main types of welders: arc and resistance welders. Arc welders use a sacrificial rod to weld the metal target material together. Resistance welders fuse the metal target material together. Arc welders are divided further into transformer and motor-generator types.

Rule 42-002 Special terminology — contains definitions for special terms that apply to section 42 that are not defined in Section 0 such as: actual primary current, duty cycle, and rated primary current. These terms will be important when calculating the ampacity of the supply conductors for welders.

Rule 42-004 Receptacles and attachment plugs — outlines that, where receptacles are installed for the plug and cord-connection of a portable welder, the ampacity rating of the overcurrent protection for the circuit can be more than the rating of the receptacle, but the receptacle must have a rating equal to or greater than the ampacity of the supply conductors for the welder. This is important because the high instantaneous inrush start-up current of the welder will exceed the branch circuit conductor ampacity. This prevents nuisance tripping.

Transformer arc welders

Rule 42-006 Supply conductors — provides the factors in determining the ampacity of supply conductors for transformer type arc welders. The ampacity depends on the duty cycle of a single welder, as in sub-rule (1) and the demand factors where a group of welders are supplied by one circuit as in sub-rule (2). The CEC Handbook contains Tables 42-1 and 42-2, which show the correlation between duty cycle and demand factor and determination of the demand factor for multiple welder installations.

Rule 42-008 Overcurrent protection for transformer arc welders — specifies the factors to be used in calculating the rating of circuit overcurrent protection per the ampacity of supply conductors and welders as in sub-rule (1). Sub-rule (2) outlines the factors in calculating the rating of the overcurrent protection for the supply conductors using Tables 1,2,3, or 4. Sub-rule (3) provides the factors in calculating the rating of the overcurrent protection for a feeder supplying a group of transformer arc welders.

Rule 42-010 Disconnecting means — requires that where there is no integral disconnect on the welder, one must be provided to disconnect the supply conductors, and it must have sufficient current rating capacity to accommodate the overcurrent protection.

Motor-generator arc welders

Rule 42-012 Conductors, protection, and control of motor-generator arc welders — specifies that the rules of Section 4 and Section 28 generally apply to the determination of supply conductor ampacity, and selection of protection and control. The CEC handbook outlines methods of calculation of duty-related demand factors through Table 42-1, 42-2 and 42-3.

Resistance welders

Rule 42-014 Supply conductors for resistance welders — provides the factors in determining the ampacity of supply conductors depending on the primary current or duty cycle of either an individual seam resistance welder or an automatically fed resistance welder. Table 42-4 in the CEC Handbook shows the relationship between duty cycle and demand factors.

Rule 42-016 Overcurrent protection — specifies the factors in determining the rating of the overcurrent protection based on the rated primary current of the welder and the allowable ampacity of the supply conductors based on Tables 1,2,3 or 4. The CEC Handbook outlines methods of calculation of duty related demand factors through Tables 42-3 and 42-4. For determining the rating of overcurrent Protection for a group of resistance welders use the factors contained in rule 42-014.

Rule 42-018 Control of resistance welders — requires that a resistance welder have a disconnecting switch or circuit breaker rated for the capacity of the supply conductors to isolate the welder from the supply circuit.

Rule 42-020 Nameplate data for resistance welders — requires data specific to the resistance welder be provided on the nameplate, including rated KVA at 50% duty cycle, maximum and minimum open-circuit secondary voltage, short circuit current, and the throat and gap setting.

In the next installment, we will be discussing Section 44 — Theatre installations

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

** Note the CEC Handbook is also published by CSA.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.


The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA
William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

 

       Partnering For The Next Step                                                                     

Siemens CanadaWelcome to the Digital Enterprise Virtual Summit brought to you by Siemens

How quickly can you react to changing conditions and demands in your market? How can you ensure your production will run securely at any time in the future?

Industry’s digital and technological transformation is the answer for meeting today’s and tomorrow’s challenges and market needs.

With the right digitalization and automation solutions, expertise won from practical experience, and a partnership approach that benefits all involved parties.

To explore these possibilities, we’re bringing together top-level speakers, specialists and decision-makers from various industries and experts from Siemens to the Digital Enterprise Virtual Summit under the motto “Partnering for the next step.”   

This virtual summit will be an interactive digital event featuring first-hand experiences and success stories achieved with industrial digitalization and automation solutions, and cutting-edge technologies.

Join us on July 16 and learn from customers and experts how you can respond efficiently, flexibly and safely to the changing market environment.

To cover as many different time zones as possible, we offer two almost identical live sessions – you can also watch them on demand at your convenience:

Sessions runs from :  9:30 am to 2:15 pm ET (3:30 pm to 8:15 pm CEST)


READ MORE

Changing Scene

  • Prev
Stay Wired to Win is a monthly at-home challenge designed to keep your competitive spark going ...
Join the Electrical Contractors Association of Ontario (ECAO) for a live webinar on July 7 at 2:00 ...
Following the latest COVID-19 announcements from the Ontario Government, ESA has decided to ...
Introducing Stay Wired to Win – a series of monthly at-home challenges designed to keep your ...
ESA’s response team has been working diligently to address the emerging issues. We are moving into ...
This recall involves Legrand / Pass & Seymour commercial-grade tamper resistant duplex ...
In response to the current COVID-19 crisis, IDEAL Canada was looking for ways to contribute to the ...
Join Nexans for a free webinar as Isaac Müller, Applications Engineer for Nexans discusses this ...
IDEAL INDUSTRIES has made the difficult but necessary decision to cancel the original ...
The Regional Electrical Inspector performs physical inspections on all types of electrical ...

 

WestburneMany contractors prefer to deal with the people that they know, in their local branch. When doing a job out of town, it’s often inconvenient or simply impossible to return to your home branch to pick up material orders for the next day, within standard business hours.

Westburne’s new locker solution extends the branch’s pick up times to 24 hours, 7 days a week.

 

 

 


Read More

 

Latest Articles

  • Prev
Any contractor who has been on the jobsite during a difficult wire pull can attest to the ...
All electrical incidents are preventable! Keep employees safe with an up-to-date electrical ...
Vast quantities of renewables and bi-directional flows on the grid, along with rapid cost declines ...
Many organizations are at risk of continued interruption to operations due to coronavirus and ...
It is very scary to realize that our entire world has changed so drastically with the COVID-19 ...
The new electrical code includes several changes to support electrical workers in the safe ...

EmployeesBy Terry Becker

All electrical incidents are preventable! Keep employees safe with an up-to-date electrical safety program and complimentary training.

“Employees don’t do what you expect, they do what you inspect!” This is a great quote when it comes down to occupational health and safety. The need for ensuring that an audit is a key component of your overall occupational health and safety management system and your company’s electrical safety program is essential.

Read More

 

 

Michelle BraniganBy Michelle Branigan

Student workers may make up a relatively small portion of the sector workforce, but their impact is substantial. EHRC’s Empowering Futures wage subsidy program has placed 510 students, contributing $14.8 million to the Canadian economy (and counting). That’s no small figure, especially considering that many placements are only a few months long.

In challenging economic times, the tendency might be to pull back on initiatives not deemed essential to operating — why take a chance on an inexperienced employee for only a short time when resources are already stretched?

Read More

 

Product News

  • Prev
Engineered to provide customers with portable task-specific lighting in hazardous industrial ...
HPS is now offering three phase general purpose and k-rated transformers for solar applications ...
The EVduty from Elmec Inc. is a level 2 charging station for electric vehicles. It lets you ...
Smart, Accessible, and Easy-to-use, Noodoe EV Stands Out Against Other EV Chargers with its ...
Littelfuse have expanded its DCN Series of high voltage direct current (DC) contactors.   ...
The Pull-handle Butterfly Valve Lockout. Its simple, fold-over design effectively lockspull handles ...
LEDVANCE is launching, on July 2020, SYLVANIA SubstiTUBE PS Natural LED T8 Lamps and ...
Luminis has improved and expanded its Maya family of exterior luminaires. Improvements in design ...
A new 8” diameter size has been added to the 12” and 16” existing diameters. The translucent white ...
Universal’s EVERLINE® Vapor Tight is ideal for unforgiving lighting environments. These durable LED ...

 

Brady Pull-Handle Butterfly Valve LockoutThe Pull-handle Butterfly Valve Lockout. Its simple, fold-over design effectively lockspull handles in any desired position. And, it holds up to four padlocks for added safety. No matter what industry you’re in, this versatile, one-piece lockout device bolsters your safety lockout solution. And that’s a welcome addition to any lockout program. With this device you’ll also get:

  • A great fit – exclusive, anti-pivot lockout device that fits a variety of pull handle butterfly valve sizes

 

 

 

Read More


Shannon TymoskoBy Blake Marchand

Shannon Tymosko is a first-year apprentice with IBEW (International Brotherhood of Electrical Workers) Local 105, something she undertook after 10 years working her way up the ranks of a payday loan company.

“One of the things I love, working in the trades, is you can see your progress and you can see at the end of the day the work that you have done.

 

Read More

 

 

Copper $US Dollar price per pound

Kerrwil Publications Great Place to Work. Certified December 2019 - December 2020

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2020 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil