Research conducted on behalf of the BC Safety Authority (BCSA) could provide a technical solution to a key compliance barrier.

BCSA estimates that up to 50% of electrical work done by contractors in the province is performed without required installation permits. Unpermitted work is linked to higher risk to worker and public safety.

Graduate students from Simon Fraser University’s School of Public Policy recently conducted research, including interviews with BCSA stakeholders, to identify issues that may inhibit permitting. They prepared a report recommending several ideas that could help bring non-compliant electrical contractors into the safety system.

Why people don’t comply with regulations

According to the Organisation for Economic Co-operation and Development (OECD), people don’t comply with regulatory requirements for a number of reasons, including:

  • failure to understand the law
  • procedural injustice
  • costs of compliance (in terms of time, money or effort)
  • deterrence failure
  • incapacitation of those regulated
  • failure of persuasion

What the graduate students recommend

Recommendations include:

  • developing a mobile app to make the permit application process faster and more efficient
  • improving the navigation and usability of the BCSA website
  • providing multi-lingual website information and forms
  • enhancing homeowner education regarding when and where permits are required, and the risks of not obtaining them
  • exploring the potential of virtual inspections (via video-conference) for low-risk sites

The students’ report explores each of these recommendations. Here’s a summary of its recommendation for an app. The purpose would be to increase access to information and simplify the permit application process. The app could be for both contractors and their clients, and provide different information to each party.

How the app would work

Here’s a possible sequence of events and features.

For the contractor:

  1. User downloads the app
  2. User creates a contractor profile
  3. Information used to create a contractor profile is integrated into permit applications as basic auto-fill information. This increases ease of use by reducing the need to add personal information each time an application is created
  4. User is able to request a permit directly through the app, and relevant information about the job can be directly input
  5. User is able to request a virtual inspection.

For the customer:

  1. User downloads the app
  2. User is able to browse for information about what work requires a permit, and easily connect with a list of licensed contractors in their city
  3. Featured spaces/images run a campaign highlighting the risks of unpermitted work and the liability involved
  4. User can connect with the regulatory authority by telephone or email through the app

The budget for this project could reach $100,000, says the report, but it would be an effective tool, particularly for contractors looking to submit permit applications. The main benefits would be to

  • simplify the permit application process, which applicants find burdensome
  • create a direct line of communication between the regulatory authority and its stakeholders; for example, notifying electrical contractors of regulatory and process changes

While BCEA has published the report on its website, it has not yet publicly indicated any next steps. Find out more: www.safetyauthority.ca/news/electrical-newsletter/can-technology-help-bcsa-improve-electrical-compliance.

 

Related Articles


Latest Articles

  • Driivz: 2025 State of EV Charging Network Operators Report

    Driivz: 2025 State of EV Charging Network Operators Report

    May 19, 2025 As the EV charging industry is poised for profitability, network operators still face many challenges. But what are their biggest challenges, are they ready to scale up to support their business growth, and how will they provide drivers with a better charging experience in 2025. This report answers these questions and more,… Read More…

  • Electri International: Understanding, Identifying, and Measuring Rework

    Electri International: Understanding, Identifying, and Measuring Rework

    May 19, 2025 ELECTRI has sponsored a research project to create a playbook for electrical contractors that will help you: Unpaid rework refers to activities in the field (including prefabrication) that have to be done more than once, or activities that remove work previously installed as part of the project, where no change order has… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…

  • 6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    May 19, 2025 The rapid expansion of data centers has brought about significant challenges in maintaining data security standards. According to Statistics Canada, recovery costs from cyber security incidents in 2023 were $2.1 billion, up from $600 million in 2021. This critical situation requires a more robust cable management design to protect data from being… Read More…


Changing Scene

  • Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    May 19, 2025 Schneider Electric Canada has been recognized as one of Canada’s Greenest Employers for 2025 by Mediacorp Canada Inc. as part of the Canada’s Top 100 Employers project, a prestigious honour celebrating organizations that lead the country in creating a culture of environmental sustainability. This recognition highlights Schneider Electric’s long-standing commitment to advancing climate action, driving… Read More…

  • NEW ECAO Website is LIVE

    NEW ECAO Website is LIVE

    May 19, 2025 ECAO are excited to officially launch the new and improved ECAO website, redesigned with you in mind. Whether you are registering for training, accessing member resources, or staying up to date on key industry developments, ECAO’s new platform makes it faster, easier, and smarter. ECAO have rebuilt the site to deliver the ultimate… Read More…

  • Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    May 19, 2025 Catalyst Sales and Marketing is proud to announce a new line partnership with MGM Transformer Company, a recognized provider of dry-type and liquid-filled transformers for commercial, industrial, and infrastructure applications. With over 50 years of expertise, MGM delivers custom-engineered, reliable, and energy-efficient solutions designed to meet the demands of data centers, renewable… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…