Canada Energy Regulator Approval – Interconnection Project with Maine Gets the Final Green Light

EIN 27 hydro quebec 400

The Canada Energy Regulator (CER) issued the permit authorizing the construction and operation of the Appalaches–Maine Interconnection line. This infrastructure will link to the New England Clean Energy Connect (NECEC) line, whose construction began in Maine in February 2021. The project now has all the permits required for construction, from Saint-Adrien-d’Irlande in Québec to the City of Lewiston in Maine.

The CER’s authorization comes after a 21-month evaluation, which included a period for public comment.

“This green light recognizes the significant work carried out to date by our teams and our partners in the communities,” underscored Sophie Brochu, President and CEO of Hydro-Québec. “We are going ahead with a project that respects the highest environmental and engineering standards, and that has been favorably received by the various host communities.”  

Work will begin in the coming weeks, with commissioning slated for 2023. The Québec government authorized the project on April 7, 2021, whereas the Commission de protection du territoire agricole and the Régie de l’énergie gave their approvals in December and July 2020, respectively.  

The new Appalaches–Maine–NECEC line will carry 1,200 megawatts of Québec hydroelectricity to New England.  The interconnection will supply Massachusetts with 9.45 terawatthours of clean Québec hydropower. In addition, through an agreement signed with Maine last summer, Maine will receive 0.5 terawatthours annually for 20 years.

The route selected in Québec for the 320-kV direct current line extends 100 km between Appalaches substation in Saint-Adrien-d’Irlande (near Thetford Mines) and a connection point in the municipality of Frontenac in Estrie on the Québec–Maine border. The project also calls for the installation of a converter at Appalaches substation, which will convert alternating current to direct current to supply the new interconnection. The length of the line route in Maine is 233 km.

Source

 

Related Articles


Latest Articles

  • NSAA Apprenticeship Management System (AMS) is Now Available

    NSAA Apprenticeship Management System (AMS) is Now Available

    June 19, 2026 NSAA has now launched the Apprenticeship Management System (AMS) to provide a faster, easier, and more transparent way for apprentices and employers to manage apprenticeship activity. For Apprentices, Apprenticeship Management System will allow you to:  For Employers, with Apprenticeship Management System, you will be able to:  For Tradespersons Your launch of Apprenticeship… Read More…

  • IP Ratings in Lighting: What They Actually Mean in the Field

    IP Ratings in Lighting: What They Actually Mean in the Field

    By CSC LED IP ratings are among the most frequently referenced specifications in lighting, yet they are often misunderstood or oversimplified. While they may appear to be just another number on a specification sheet, IP ratings play an important role in determining where a fixture can be installed and how it will perform over time.… Read More…

  • The Role of Offshore Sourcing: An Editorial Perspective for Manufacturers, Distributors, Agents, Contractors, and Industry Stakeholders

    The Role of Offshore Sourcing: An Editorial Perspective for Manufacturers, Distributors, Agents, Contractors, and Industry Stakeholders

    The real divide is not domestic versus offshore. It is between committed, accountable partners and transactional, price‑only players. The CSA mark sits inside that story as one important signal but it is only a subset of what the market should be looking at. Read More…

  • Alberta OHS Code Review

    Alberta OHS Code Review

    June 15, 2026 Albertans are invited to provide feedback for Alberta’s ongoing review of Alberta’s OHS Code. Complete the surveys by July 8. Albertans are invited to participate in our ongoing review of the Occupational Health and Safety Code (OHS Code). This is an opportunity to improve health and safety outcomes for workers and streamline… Read More…


Changing Scene

  • AEMC® Instruments welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada

    AEMC® Instruments welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada

    June 19, 2026 AEMC® Instruments, part of the Chauvin Arnoux Group® welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada.  Mark will serve as your primary point of contact for product information, technical support, and order coordination in the Eastern Canada region. With over two decades of experience in technical sales, distribution and business development, Mark brings a… Read More…

  • BCCA Response to Investment Announcement

    BCCA Response to Investment Announcement

    June 19, 2026 Statement from BCCA: The British Columbia Construction Association (BCCA) welcomes today’s joint announcement by the federal and provincial governments to invest in housing, infrastructure, healthcare, and public transit across British Columbia, including funding to reduce Development Cost Charges (DCCs). These investments will help support the infrastructure needed to enable new housing and… Read More…

  • ECAO Recognition of Safety Achievement Award Recipients

    ECAO Recognition of Safety Achievement Award Recipients

    June 15, 2026 ECAO is proud to recognize the recipients of their Recognition of Safety Achievement Award. This award honours member companies that demonstrate exceptional commitment to workplace safety through outstanding safety performance and a strong culture of prevention. The Recognition of Safety Achievement Award celebrates organizations that maintain injury and illness statistics below the… Read More…

  • ECS Announces the Promotion of Jeff Bartlette to Branch Manager, Winnipeg

    ECS Announces the Promotion of Jeff Bartlette to Branch Manager, Winnipeg

    June 15, 2026 ECS is pleased to announce the promotion of Jeff Bartlette to Branch Manager, Winnipeg. Jeff joined ECS with a mandate to establish the company’s presence in Manitoba. Having successfully balanced both sales and leadership responsibilities, he will now focus fully on developing his team, strengthening branch capabilities, and positioning Winnipeg for continued… Read More…