Brame Electric’s Rory MacCuaig on their Stratford EV Charging Project

April 13, 2023

By Blake Marchand

In this article we talk with Rory MacCuaig of Brame Electric to gain some insight into the municipal EV Charger Installation project they are coordinating for the City of Stratford. MacCuaig is managing the project, he generally works as part of the industrial arm of Brame Electric, which is acting as the general contractor on the project as well as doing the electrical work.

The opportunity came about when the City manager reached out to them after not hearing back from their registered electrical contractor. Brame has done some water/wastewater work with the municipality, so they have a working relationship with the municipality.

Stratford wanted to move forward with an EV charger installation in several city parking lots, and they wanted to apply for some government grant funding. The funding applications required budgetary numbers, so they needed an electrical/general contractor to provide them with quotes for the project. The scope of the quote would need to include the entire project, not just the electrical work.

โ€œI was kind of the second call just because of general knowledge and how the city operates, and they know weโ€™re competent in taking care of the technical work,โ€ MacCuaig noted.

โ€œOne of the main things about this,โ€ he said, which was a bit of a concern for MacCuaig, โ€œthis isnโ€™t like a $5,000 install it is a pretty significant number for them. I was the one that figured out the layout and started talk with Festival Hydro, basically, I created a full scope of work for the city to use, and with it being a high-ticket number I thought it might go to tender and other people would have the opportunity to bid on this project. I never really like doing that because you never know if somebody is going to come in $50,000 under what you quoted but then turn around and bill the customer $50,000 worth of extras. Itโ€™s kind of a strange game that happens all the time.โ€

With that in mind he said, โ€œI was upfront with them,โ€ explaining that he was willing to consult on the project, create the scope of work, create the layout, give them the budgetary numbers for the City to move forward with, however if the project was going to go to tender, Brame would charge them a consultation fee for the process.

โ€œIf this is single sourced and I am allowed to carry on and complete this work,โ€ he told the city, โ€œI will waive that consultation cost because itโ€™s basically part of the project.โ€

Once the project went to council it was a close decision. Some of the council members were hesitant to bypass the tender process due to the project cost while having only one contractorโ€™s opinion on it.

โ€œI donโ€™t think they may have realized that this project had been in the works for almost two years and thereโ€™s been a lot of footwork involved, and for them to actually create a scope of work and send it out to tender, there was going to be a lot of lost time and they were going to end up not meeting deadlines for the grants.โ€

โ€œIt was a big decision they had to make.โ€

As a local contractor and taxpayer that grew up in Stratford it was a source of pride for MacCuaig to take on the project for the City.

Brame
Stratford, Ontario Town Hall Building

The Project

Brame Electric has done EV charger installations in the past but generally, MacCuaig said itโ€™s at a facility so the installation much more straightforward, โ€œWhere youโ€™re just running conduit form the distribution to an outer wall and install the EV charger and away you go.โ€

โ€œThis is a little bit more complicated but, like I mentioned before, we do a lot of work with control panels and wastewater/clean water, and remote areas,โ€ he said, so they have experience with more technical projects.

โ€œLetโ€™s say thereโ€™s parking lot one, there will be a centre median: we have to provide a new meter, so, itโ€™s metered power from the supply company, and then a distribution cabinet that houses a main disconnect and distribution panel, and then we feed out to our EV chargers.โ€

In providing the quote and scope of work, MacCuaig provided information on energy load for each site, trench location, coordination with Festival Hydro on location of the charging stations in relation to service, siting for electrical meters and distribution equipment, landscaping and concrete work for reconstruction following the work, as well as directional boring to avoid reconstruction for some sites.

There are 12 chargers being installed in total. Some of the locations have two chargers and others have up to six. The federal government is contributing $160,000 over three years, while the City has budgeted $317,000 for the project. The funding is being provided through Natural Resources Canadaโ€™s Zero Emission Vehicle Infrastructure program. There will be eleven dual output level two chargers and one level three charger. Level 2 chargers will charge a car battery from empty in approximately 4.5 hours. A level three charger will do the same in approximately 30 minutes.

Along with coordinating the non-electrical components of the project, MacCuaig said Brame will be bringing in another electrical contractor, Kellyโ€™s Electric, to help with a portion of the install, โ€œThey get into a lot more of the excavation and directional boring, sucker trucks, all that kind of stuff. We get along with them great, we work hand in hand if thereโ€™s anything with underground work โ€“ they are going to be assisting us with this project.โ€

โ€œOn some of the installations weโ€™re going to be using directional boring, just to eliminate having to cut up half of a parking lot. Some of them (EV charger sites) we have to suck down below vault entrances for pad mount transformers.โ€

They are still determining how the project will be carried out, whether itโ€™s one site at a time or all at once. The former would mean, MacCuaig said, โ€œWe excavate, bring our service feed over, get concrete to pour our bases, pull wire, fully terminate to have those fully operational โ€“ and then move on to parking lot two.โ€

The alternative would be to excavate all the sites at once and do each phase of the project at the same time.

โ€œWe could potentially turn around three of these parking lots within a month and have them fully operational,โ€ MacCuaig said, โ€œnow, thatโ€™s going to take a lot of organization and basically wipe the slate of any other projects in order to complete it that way โ€“ but like I mentioned before, we do have the manpower that I can have guys working on that job until its done.โ€

MacCuaig said that would be his preference, and that it would make coordinating the sub-trades easier.

Particularly for the concrete, it would make more sense logistically to pour the pads at each site rather than one at a time because the pads are 5โ€™x3โ€™ and 2โ€™x2โ€™.

At the time of the interview MacCuaig said they were still planning some of the layout logistics before they begin work on the project.

โ€œWe are planning on starting installations in the spring/early summer,โ€ he said, โ€œIโ€™m still currently working with the engineers on service layouts and some of the specifics on the site installations. Thatโ€™s getting very close to being completed.โ€

Once they are able to confirm the service layout with Festival Hydro, MacCuaig said the game plan is, โ€œnumber one, to order the distribution equipment, thatโ€™s one of the things thatโ€™s taken a little bit longer for us to get our hands on is big enclosures โ€“ it seems the bigger they get the longer the lead time.โ€

โ€œWeโ€™re just trying to sort out exactly what Festival Hydro requires for metering. Some of the sites are a little bit larger for distribution services so weโ€™ll need to have separate metering cabinets for distribution equipment.โ€

Ultimately, MacCuaig said, โ€œThe most important thing for me is that this project is flawless.โ€

โ€œI want to make sure we provide a perfect turn-key solution.โ€

He is confident that the functionality of the project will be there given the experience of the company and their track record, and so his focus is to deliver an overall finished product that is aesthetically pleasing to showcase Brameโ€™s work to the city, because itโ€™s such a public project and a major investment for the City of Stratford.

โ€œItโ€™s an interesting project for sure, weโ€™re looking forward to doing it,โ€ he said, โ€œStratford is a pretty busy city in the summer, itโ€™s good exposer for us, for sure.โ€

Supply Chain Challenges

Supply chain disruptions caused by the pandemic played a factor in the quoting process.

โ€œWeโ€™ve seen costs triple/quadruple in the last three or four years, so providing a quote last year [โ€ฆ] obviously there is a significant cost increase just based on material alone.โ€

โ€œIn the end I revised the price three, maybe four times, just to reflect differences in the material costs โ€“ and with the surging fuel costs six months ago, obviously for stuff to get here on trucks costs a lot more too. So, that was a bit of challenge with having to keep going through and 2-inch conduit was worth $2/ft now itโ€™s worth $2.56/ft, sort of thing, so you had to keep going through and doing that.โ€

โ€œThe last time I revised it, I said, look, Iโ€™ve been notified that in two weeks this price is going up, so Iโ€™ve accounted for that, if this project takes another six months to get going there may be another increase. Or they may be a decrease as well.โ€

โ€œOur suppliers are pretty good with us,โ€ he said, โ€œthey will give us a heads up, โ€˜thereโ€™s a copper increase coming in a couple weeks’ โ€“ stuff like that.โ€

MacCuaig said they have been stocking more general material since the start of the pandemic created significant supply shortages and price fluctuations.

โ€œWith the original COVID product delays letโ€™s call it, we kind of realized โ€“ there were times when you couldnโ€™t get ยพโ€ PVC conduit, thereโ€™d be thousands of feet on backorder from three of the wholesalers in town. So, we started playing it smart and stocking lots of our base material. Now, it comes with exorbitant costs for the amount of time before you can sell it, but you got to weigh that against the alternative of having employees standing around, theyโ€™re supposed to be doing the job but the materials not there for them to complete it.โ€

EV Infrastructure

As electric vehicles become more prominent and gas vehicles are pushed more to the side, MacCuaig sees more opportunity for EV infrastructure, particularly at gas stations and rest stops. For example, OnRoute has started putting EV chargers at some locations, but more will be required as uptake increases. Gas stations will also need to be retrofitted with EV chargers, which will have to include an upgraded service.

Brame
Ivy Charging Stations at the Tilbury, Ontario OnRoute

โ€œWhen youโ€™re looking at a normal gas station, it probably only has a 100amp or 200amp service, so that whole service is only going to run four Level 2 chargers,โ€ he explained.  โ€œYouโ€™ll have to upgrade the whole service to the gas station,โ€ MacCuaig noted. 

Brame Electric

MacCuaig has been with Brame Electric for five years. His previous company disbanded and a few of them moved over to Brame, which is when the company started expanding their industrial services.

Their shop is currently moving, which is another wrinkle for them in this project.

MacCuaig mentioned Brame has out grown their current space, โ€œWe do a lot of control panel builds as well โ€“ weโ€™re currently building a seven-foot tall four-foot-wide cabinet right now, it doesnโ€™t seem like that big of a cabinet but when you have everything laid out, strewn about it does take up a significant amount of space while youโ€™re doing the fabrication portion of it.โ€

Another interesting aspect MacCuaig touched on is the dynamic between electrical contractors in Stratford. There have been several challenges and uncertainties within the market in recent years, one that is becoming more prevalent is the availability of labour. Instead of competing to attract quality workers from other companies, the contractors in Stratford, MacCuaig said, tend to work together.

โ€œItโ€™s interesting here,โ€ he said of the landscape of contractors in Stratford, โ€œI remember a new manager coming into a supplier, many years ago, and he said, โ€˜I donโ€™t know how there are so many small contractors in Stratford that everybody really gets along, and nobody is trying to cut each otherโ€™s grass or anything like that.โ€™โ€

โ€œRight now, thereโ€™s kind of a worker shortage,โ€ he said, but itโ€™s not a scenario where he is trying to offer more money to electricians working for other contractors, โ€œwe donโ€™t try to poach off of each other.โ€

โ€œEverybody gets their piece of the pie,โ€ he said. โ€œWeโ€™ve kind of learned to all work together.โ€

www.brameelectric.ca

Related Articles


Latest Articles


Changing Scene

  • Skills Ontario Celebrates Team Ontario Winning 38 Medals atย Skills Canada National Competition 2026

    Skills Ontario Celebrates Team Ontario Winning 38 Medals atย Skills Canada National Competition 2026

    June 8, 2026 After two days of showcasing their skills, youth on Team Ontario are returning home from Skills Canada National Competition 2026 with 308 medals.  At a Closing Ceremony on May 30th following the Skills Canada National Competition in Toronto, which took place from May 28th to May 29th, Team Ontario took home 38 Read More…

  • Spartan Controls Opens New facility in Kitimat to Support Growing Industrial and Energy Sector Demand

    Spartan Controls Opens New facility in Kitimat to Support Growing Industrial and Energy Sector Demand

    June 8, 2026 Spartan Controls, a leading provider of industrial automation solutions, is proud to announce the opening of a new facility in Kitimat. The service centre expands Spartan’s presence in Northwestern British Columbia to support the region’s rapidly growing industrial and energy sector. The new facility strengthens Spartan’s ability to deliver local support to Read More…

  • Laurentide Controls Acquires C. Latendresse Inc., Reinforcing its Integrated Industrial Electrical Offering in Eastern Canada

    Laurentide Controls Acquires C. Latendresse Inc., Reinforcing its Integrated Industrial Electrical Offering in Eastern Canada

    June 8, 2026 Laurentide Controls is proud to announce the acquisition of C. Latendresse Inc., an industrial and commercial electrical contractor founded in 1976, based in Charlemagne, QC. The transaction closed on May 25, 2026. A Targeted Strategic Reinforcement This acquisition is the result of a strategic convergence: Laurentide brings to C. Latendresse Inc. the Read More…

  • ESA Highlights Proactive Maintenance as Part of Building Safety Month

    ESA Highlights Proactive Maintenance as Part of Building Safety Month

    June 8, 2026 Much of Ontarioโ€™s housing stock is aging, and the risks are becoming harder to ignore. More than ๐Ÿด๐Ÿฌ% ๐—ผ๐—ณ ๐—ฝ๐˜‚๐—ฟ๐—ฝ๐—ผ๐˜€๐—ฒ-๐—ฏ๐˜‚๐—ถ๐—น๐˜ ๐—ฟ๐—ฒ๐—ป๐˜๐—ฎ๐—น ๐—ต๐—ผ๐˜‚๐˜€๐—ถ๐—ป๐—ด ๐—ถ๐—ป ๐˜๐—ต๐—ฒ ๐—ฝ๐—ฟ๐—ผ๐˜ƒ๐—ถ๐—ป๐—ฐ๐—ฒ ๐—ถ๐˜€ ๐—ผ๐˜ƒ๐—ฒ๐—ฟ ๐Ÿฐ๐Ÿฑ ๐˜†๐—ฒ๐—ฎ๐—ฟ๐˜€ ๐—ผ๐—น๐—ฑ. Between 2019 and 2023, there was an ๐—ฎ๐˜ƒ๐—ฒ๐—ฟ๐—ฎ๐—ด๐—ฒ ๐—ผ๐—ณ ๐Ÿฏ๐Ÿฎ ๐—ฒ๐—น๐—ฒ๐—ฐ๐˜๐—ฟ๐—ถ๐—ฐ๐—ฎ๐—น ๐—ณ๐—ถ๐—ฟ๐—ฒ๐˜€ ๐—ฒ๐—ฎ๐—ฐ๐—ต ๐˜†๐—ฒ๐—ฎ๐—ฟ in aging multi-unit residential buildings, with the potential Read More…