Code Quiz: Answer for Section 20 – Flammable Liquid and Gasoline Dispensing, Service Stations, Garages, Bulk Storage Plants, Finishing Processes, and Aircraft Hangars

March 4, 2025

By William (Bill) Burr

A commercial vehicle repair garage is being constructed with one corner of the garage area containing a washroom, office and mechanical room which are separated from the vehicle repair area by an elevated floor area of about 50mm and a substantially constructed non-combustible wall with a self-closing fire door.

Would the electrical equipment in the office, washroom or mechanical room be required to be suitable for a hazardous location?

Answer:

  1. Given the 50mm elevated floor and the non-combustible construction and self-closing fire door, this area is not considered a hazardous location.
  2. As the office, washroom, and mechanical room are not considered to be classified as hazardous locations the electrical equipment contained in these areas may be suitable for an ordinary location.

Section 18 Hazardous Locations

Rule18-058 Equipment rooms

1) Where walls, partitions, floors, or ceilings are used to form hazard-free rooms or sections, they shall be

a) of substantial construction.
b) built of or lined with non-combustible material; and
c) such that the rooms or sections will remain free from hazards.

2) Where a non-hazardous location within a building communicates with a Zone 2 location or an explosive dust atmosphere, the locations shall be separated by close-fitting, self-closing fire doors.”

Section 20 – Commercial repair garages

Rule 20-102 Hazardous areas

1) For each floor at or above grade, the entire area up to a level 50 mm above the floor shall be a Zone 2 location except that adjacent areas shall not be classified as hazardous locations, provided that they are:

a) elevated from a service and repair area by at least 50 mm; or
b) separated from a service and repair area by tight-fitting barriers such as curbs, ramps, or partitions at least 50 mm high”

Go HERE for more information on Section 20

Go HERE for more information on Section 18

Related Articles


Latest Articles

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…

  • Goal Zero YETI 3000X Power Stations Recalled due to Fire and Burn Hazards

    Goal Zero YETI 3000X Power Stations Recalled due to Fire and Burn Hazards

    September 16, 2026 This recall involves Goal Zero YETI 3000X power stations. The silver and black portable power stations measure about 62 centimetres (24.4 inches) high, 47 centimetres (18.5 inches) wide, 57 centimetres (22.3 inches) deep and weigh approximately 42 kilograms (92 pounds). The power stations have yellow handles and a digital display at the… Read More…


Changing Scene

  • Innovair Solutions Acquires TRM Heating Cables

    Innovair Solutions Acquires TRM Heating Cables

    September 18, 2026 Innovair Solutions has announced the acquisition of TRM Heating Cables, a Toronto-based Canadian company specializing in heating cables for commercial and industrial applications. Founded in 2001, TRM has built strong technical expertise in the sale and installation of specialized products, including self-regulating cables, mineral-insulated cables and electric floor heating systems. The company… Read More…

  • Electrical Safety Authority Honours Leaders Helping Build a Safer, More Electrified Future

    Electrical Safety Authority Honours Leaders Helping Build a Safer, More Electrified Future

    September 17, 2026 From preparing the next generation of skilled workers to supporting one of the world’s largest sporting events, this year’s recipients demonstrate how electrical safety supports Ontario’s future As Ontario electrifies homes, transportation and industry, the Electrical Safety Authority (ESA) has recognized the organizations and individuals helping ensure safety keeps pace with that… Read More…

  • NERVA Energy to Support Deep Energy Retrofits Across Selected Morguard Properties

    NERVA Energy to Support Deep Energy Retrofits Across Selected Morguard Properties

    September 17, 2026 The Canada Infrastructure Bank (CIB) has reached financial close on a $100 million loan with Morguard Corporation to enable energy‑efficient retrofits across a portfolio of approximately 30 properties in Canada. Morguard is a fully integrated real estate firm with more than $24.2 billion in assets under management across North America. Morguard will collaborate… Read More…

  • Government of Canada Welcomes Major New Investment in Sovereign AI Infrastructure in Saskatchewan

    Government of Canada Welcomes Major New Investment in Sovereign AI Infrastructure in Saskatchewan

    September 16, 2026 New Canadian-led infrastructure project will help build secure and reliable computing capacity responsibly On September 14, 2026, the Government of Canada welcomed Bell Canada’s planned investment to expand its Bell AI Fabric capacity in Saskatchewan, an important step toward building the sovereign computing capacity Canada needs to compete and succeed in the… Read More…