GE-Led Consortium Wins Manitoba Hydro Contract to Replace Substation in Winnipeg

Winnipeg Substation

Aconsortium led by GE’s Digital Energy business has won a milestone engineering, procurement and construction contract from Manitoba Hydro to build a new, 66 kilovolt gas-insulated substation that will help meet Winnipeg’s growing energy needs. The contract, valued at $31.4 million, is the first substation order for GE’s Digital Energy business in Canada.

The new Adelaide Street substation will be built in downtown Winnipeg, replacing the utility’s aging substation on King Street in the Exchange District. The project is part of Manitoba Hydro’s plan to upgrade or replace Winnipeg’s aging substations and other equipment with newer, more efficient power delivery systems.

GE submitted the winning EPC bid under an open consortium approach, with GE as the consortium leader and Edmonton, Alberta-based HB Construction Company, Ltd. as the consortium’s engineering and construction partner.Teshmont, a Winnipeg-based provider of high-voltage DC power transmission services, also plays a key role as GE’s key sub-contractor responsible for protection and control engineering and associated testing.

“Electrical substations are a critical part of our distribution system, delivering electricity to homes and businesses throughout the city and driving more sustainable economic growth for our province,” says Manitoba Hydro President and CEO Scott Thomson. “Even as we expand our networks, they are continuously being repaired and upgraded to meet the growing energy needs of our customers.”

Brent Reed, vice president, customer service & distribution for Manitoba Hydro noted that of the 97 stations in the city of Winnipeg, 37 are operating beyond their technical limitations and eight of them are more than 60 years old.
Winnipeg is not alone.A report by the Canadian Electricity Association quotes an International Energy Agency estimate that Canada will need to invest an estimated $350 billion in its electricity sector by 2030, representing a national investment of approximately $17.5 billion per year for 20 years.

The GE-led consortium’s scope of work on the new Adelaide substation includes the design, supply, installation, testing and commissioning support of three 30-megavolt ampere transformers; 66-kilovolt gas-insulated switchgear; and 12-kilovolt metal-clad switchgear. The equipment will be housed in a new building with a perimeter wall surrounding the station.

 

Related Articles


Latest Articles

  • Industrial Wiring Devices: A Brief Intro and How to Choose Them

    Industrial Wiring Devices: A Brief Intro and How to Choose Them

    June 9, 2025 Introduction: With the multitude of options on the market, it can be difficult to decide whether you need a pin and sleeve wiring device or a plug and connector in your industrial plant or facility. You might find your head swirling with thoughts about which option is best. Or you may not… Read More…

  • Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    June 9, 2025 By Electro-Federation Canada On June 3 and 4, a high-level delegation from Canada’s electrical and automation sector travelled to Montreal and Quebec City for a series of strategic meetings with Quebec government officials and key stakeholders. Organized by Electro-Federation Canada (EFC), this mission underscores the critical role the industry plays in advancing… Read More…

  • Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    June 9, 2025 By Electro-Federation Canada This year’s Annual Industry Conference, held against the breathtaking backdrop of Niagara Falls, Ontario, was a landmark event with more than 710 Electro-Federation Canada community members. More than just a celebration of our shared history, it was a launchpad for new ideas, future-based dialogue, and deeper connections.   The energy and… Read More…

  • Code Quiz: Canadian Electrical Code, Part 1, 26th Edition Section 28 – Motors and Generators

    Code Quiz: Canadian Electrical Code, Part 1, 26th Edition Section 28 – Motors and Generators

    by William (Bill) Burr Question:  Adam is working in his garage cutting wood on his table saw. Suddenly the lights go out and the sump pump and the table saw stop running. There is obviously a power outage. After a short time, the lights and the sump pump come back on, but thetable saw stays off. Adam needs to restart it.  Can you explain why the lights and sump pump come back on… Read More…


Changing Scene

  • Andrey Goreev Joins Mersen Electrical Power as Regional Sales Manager

    Andrey Goreev Joins Mersen Electrical Power as Regional Sales Manager

    June 9, 2025 MERSEN CANADA TORONTO INC. is pleased to announce effective June 2nd, 2025, Andrey Goreev has joined Mersen Electrical Power as Regional Sales Manager for the Western Canada Region. He will report to Tom Arbanas, Vice President of Distribution Sales and Customer Care, Canada. Andrey has over 18 years of experience in industrial… Read More…

  • Electric Avenue Powers Ahead with Major Win and New Flagship Product: Watti Pro Echo

    Electric Avenue Powers Ahead with Major Win and New Flagship Product: Watti Pro Echo

    June 9, 2025 In an industry dominated by global giants, a startup from Canada’s East Coast is quickly becoming one of the most compelling cleantech success stories in the country. Electric Avenue, a Nova Scotia–based EV charging manufacturer, is making waves in the North American market with the official launch of its Watti Pro Echo… Read More…

  • Manitoba and BC Establish Free Trade Agreements

    June 9, 2025 The Manitoba government will sign a new memorandum of understanding with British Columbia to advance free trade between the two provinces and cabinet will pass regulations by July 1 to ensure mutual recognition of other provinces by Canada Day, Premier Wab Kinew announced today at the MBiz Breakfast Series hosted by the… Read More…

  • Nova Scotia Removing Trade Barriers With Other Provinces, Federal Government

    Nova Scotia Removing Trade Barriers With Other Provinces, Federal Government

    June 9, 2025 Trade barriers between Nova Scotia, several provinces and the federal government will soon be removed. Nova Scotia, along with Alberta, British Columbia, Manitoba, Ontario and Prince Edward Island have taken action to remove barriers and red tape that will open up new trade and investment opportunities. It is also anticipated that the… Read More…