Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles

  • Celebrating 30 Years of Innovation and Collaboration at EFC’s 2025 Conference in Niagara

    Celebrating 30 Years of Innovation and Collaboration at EFC’s 2025 Conference in Niagara

    By Luc Rodier, Chair of the Board of Electro-Federation Canada (EFC) The 2025 EFC Conference in Niagara was a landmark occasion—marking 30 years of innovation, collaboration, and collective progress in the Canadian electrical industry. Set against the symbolic backdrop of the Canadian-U.S. border, this year’s theme, Electrifying Connections, couldn’t have been more fitting. As President and… Read More…

  • Industrial Wiring Devices: A Brief Intro and How to Choose Them

    Industrial Wiring Devices: A Brief Intro and How to Choose Them

    June 9, 2025 Introduction: With the multitude of options on the market, it can be difficult to decide whether you need a pin and sleeve wiring device or a plug and connector in your industrial plant or facility. You might find your head swirling with thoughts about which option is best. Or you may not… Read More…

  • Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    June 9, 2025 By Electro-Federation Canada On June 3 and 4, a high-level delegation from Canada’s electrical and automation sector travelled to Montreal and Quebec City for a series of strategic meetings with Quebec government officials and key stakeholders. Organized by Electro-Federation Canada (EFC), this mission underscores the critical role the industry plays in advancing… Read More…

  • Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    June 9, 2025 By Electro-Federation Canada This year’s Annual Industry Conference, held against the breathtaking backdrop of Niagara Falls, Ontario, was a landmark event with more than 710 Electro-Federation Canada community members. More than just a celebration of our shared history, it was a launchpad for new ideas, future-based dialogue, and deeper connections.   The energy and… Read More…


Changing Scene

  • Eaton and Siemens Energy Partner to Provide Power and Technology to Accelerate New Data Center Capacity

    Eaton and Siemens Energy Partner to Provide Power and Technology to Accelerate New Data Center Capacity

    June 13, 2025 Eaton, and Siemens Energy have announced a fast-track approach to building data centers with integrated onsite power. They will address urgent market needs by offering reliable grid-independent energy supplies and standardized modular systems to facilitate swift data center construction and deployment. The collaboration will enable simultaneous construction of data centers and associated… Read More…

  • Latest Social Media Challenge Puts Students at Risk of Electrical Shock

    Latest Social Media Challenge Puts Students at Risk of Electrical Shock

    June 13, 2025 The Electrical Safety Authority (ESA) is warning Ontarians that a shocking new social media trend is putting students at risk of serious electrical injury including shock, burns or even fires. A pair of dangerous social media trends have been gaining interest from students. One has kids “challenging” each other to stick a… Read More…

  • Plan Group Announce New VP of Electrical

    Plan Group Announce New VP of Electrical

    June 13, 2025 Plan Group are proud to announce the promotion of Dave Scott as Vice President of Electrical. Dave has been a key part of Plan Group’s success for the last 16 years, leading with drive, accountability, and a deep understanding of what it takes to get the job done right. He will now… Read More…

  • Electro-Federation Canada Announces New Chair and Board of Directors for 2025-26

    Electro-Federation Canada Announces New Chair and Board of Directors for 2025-26

    June 13, 2025 On Monday, May 26, 2025, Electro-Federation Canada (EFC) held its Annual General Meeting, which included an update on key initiatives, the welcoming of a new Chair, and the election of the 2025-2026 Board of Directors. EFC President & CEO Carol McGlogan shared key highlights from the past year and provided a summary of the… Read More…