Building a New Power Line Gave BC crews a Chance to Shine

On The Job BC Power

Stringing new power lines, called conductors, requires careful coordination between crews on the ground and helicopter pilots.

Foreman Bill Dalling can’t imagine doing anything else but working in the line trade. His crews worked on slopes of up to 30% grade capable of snapping chains or towing straps securing heavy loads. And then there was the spring thaw, where snow turned to mud “thick like gumbo.”But to hear Dalling describe it, building a new transmission line is about as good as it gets, at least for someone who’s made a career out of building power lines.

Dalling has been working since August 2014 as the foreman for the Merritt Area Transmission Project, leading BC Hydro construction crews as they built the 35-kilometre, 138-kilovolt transmission line, scheduled to be in-service in the fall of 2015.

The new line, which passes through tough mountainous terrain in B.C.’s southern interior, begins near the Highland substation 12 kilometres south of Logan Lake, and continues up over the mountains towards the Coquihalla Highway. It will provide power to the growing community of Merritt and the surrounding area.

The construction services team was responsible for every aspect of constructing the transmission poles and stringing the conductor, and as he explains, it’s not exactly easy.

Crews start by clearing a right-of-way for the new line

Before the familiar power poles can be constructed, and before power lines can be strung into place, crews need to clear the next stretch of right-of-way for the transmission line. Access roads need to be built so that trucks and equipment can access the transmission line route, and vegetation needs to be cleared to ensure crews can work safely.

Once the right-of-way is cleared, setting crews can move in to place the structures. In this case, wooden transmission towers known as “H-frames.” Part of his role was to coordinate construction so that the 30-person crew could always easily and safely move on to work on erecting the next structure. Once the structures are up, the chopper moves in. Thanks to the steep terrain and the difficult access along the transmission line route, the power lines are strung by helicopters, working closely with crews on the ground.

Helicopter pulls lines into place – carefully

“It starts with stringing what’s called hard line steel,” says Dalling, explaining that the hard line steel goes through pulleys called travellers in a series of structures, six kilometres at a time. These act as the ‘bull line” that attaches to the actual power lines, known as conductors, and is pulled by the helicopter to string the conductors through the same travellers. One of the important parts of stringing the lines is ensuring the appropriate “sag” in the line. There aren’t a lot of times in life when something sagging is positive, but building a power line is one of them.

“Every power line in the system has to be sagged according to the outdoor temperature to allow for expanding and contracting,” says Dalling, adding that it’s critical to get just the right amount of slack in the lines. Seasonal fluctuations in temperature, especially in colder climates, can wreak havoc on transmission lines and poles.

“In the winter, the lines can contract so much that they can break structures and poles as they pull tighter if they’re sagged improperly,” he says.

And if contending with helicopters wasn’t enough of a challenge, building a power line in B.C. is never easy. Crews here face some of the toughest terrain around.

“We were working in deep mud, it was like gumbo”

The terrain was steep and rough, says Dalling, and something as simple as keeping your footing while you were working was a challenge. Working through the winter meant slippery, snowy conditions, and the warmer weather wasn’t any easier, creating deep mud everywhere that the crews needed to work.

“We were working in deep mud some of the time, it was thick like gumbo,” says Dalling of the conditions setting crews faced as snows thawed.

And the mountainous location made it harder to keep track of the crews. Like most construction sites, safety is paramount, particularly with helicopters working overhead. Crews need to stay in constant contact, but there’s limited radio communications in the mountains around Merritt.

Crews would be stationed as much as six kilometres apart, so often someone needed to be placed in the middle to relay messages from the yard to the site where the stringing was taking place.

And at one end of the new line, near Highland Substation, crews were working parallel to an existing 138-kilovolt line, creating additional hazards and challenges in order to create proper grounding and work safely near a live power line.

Despite the challenges, Dalling is upbeat and enthusiastic about the whole project, citing it as a great one for the team, which included working with additional BC Hydro construction crews from Prince George and Nanaimo. As he says, everyone really enjoyed the project, did an exceptional job, and there was a great sense of camaraderie around the crew from beginning to end.

And for Dalling, that’s what he’s looking for each time he heads to work in the morning. Construction services gives him the opportunity to work on the whole spectrum of the power line trade, from building transmission lines, working in substations to working on distribution lines.

“I really enjoy this trade, I can’t think of doing anything else,” he says.

 

Related Articles


Latest Articles

  • Ontario Drives Growth in Residential Building Construction in September

    Ontario Drives Growth in Residential Building Construction in September

    November 25, 2024 Investment in building construction rose 2.1% to $21.6 billion in September, following a 0.2% increase in August. The residential sector increased 2.9% to $15.2 billion in September, while the non-residential sector edged up 0.3% to $6.4 billion. Year over year, investment in building construction grew 6.7% in September. On a constant dollar basis (2017=100), investment in building construction increased 1.6% from… Read More…

  • Ontario’s Institutional Construction Intentions Push up the Non-Residential Building Permits in September

    Ontario’s Institutional Construction Intentions Push up the Non-Residential Building Permits in September

    November 25, 2024 The total value of building permits in Canada increased by $1.3 billion (+11.5%) to $13.0 billion in September, reaching the second-highest level since the start of the new series in January 2017. Ontario’s construction intentions grew by $1.2 billion (+25.0%) to $5.9 billion in September 2024, leading gains in both the non-residential and residential sectors. On a constant… Read More…

  • Red Seal Self-Assessment Questions

    Red Seal Self-Assessment Questions

    November 25, 2024 Each trade’s self-assessment tool is available to help you understand your own readiness for challenging the Red Seal exam in that trade. It goes through all topics that are included in the trade’s standard (Red Seal Occupational Standard/National Occupational Analysis) and asks you to reflect on whether you have the experience and knowledge in each… Read More…

  • Halifax Regional Municipality Seeking Deep Energy Retrofit Service Providers

    Halifax Regional Municipality Seeking Deep Energy Retrofit Service Providers

    November 25, 2024 Halifax Regional Municipality (HRM) is seeking qualified deep energy retrofit service providers to be added to its roster of approved contractors. Submit your response to be considered for future deep energy retrofit projects with HRM by the January 6 deadline. Go HERE for more information Read More…


Changing Scene

  • ITC Electrical Components Celebrates 30 Years of Service to the Electrical, Automation and OEM Market in Canada

    ITC Electrical Components Celebrates 30 Years of Service to the Electrical, Automation and OEM Market in Canada

    November 25, 2024 Celebrating its 30th anniversary, ITC Electrical Components has recently launched its new and improved website at www.itcproducts.com. After a successful 15-year career in the electrical components industry Luca Fontana founded ITC Electrical Components in 1994.  Since that time the company has grown from a home-based operation to a successful business with 15 employees and… Read More…

  • Eaton Canada Investing $15m to Expand Manufacturing Capacity

    Eaton Canada Investing $15m to Expand Manufacturing Capacity

    November 25, 2024 Eaton Canada is investing approximately $15 million to expand manufacturing capacity to meet growing demand for its electrical solutions driven by the ongoing electrification of Canada’s economy. These investments will expand the company’s low-voltage manufacturing footprint by 20%, increasing its ability to produce the switchboards, switchgear and panelboards needed to support Canada’s… Read More…

  • Bartle & Gibson Announces Partnership with Electric Avenue

    Bartle & Gibson Announces Partnership with Electric Avenue

    November 25, 2024 Bartle & Gibson Co. Ltd., a Western Canada-based premier plumbing, heating and electrical distributor, proudly announced a new regional partnership to distribute Electric Avenue, providers of convenient, affordable and easy-to-use smart charging solutions for residential and commercial use, across Western Canada. Electric Avenue was founded in 2021 with one simple mission: to… Read More…

  • Federal Investment to Add 989 New Montreal Homes

    Federal Investment to Add 989 New Montreal Homes

    November 18, 2024 The federal government is providing nearly $364 million to help build 989 new homes in Montreal. The announcement took place at 5200 rue de la Savane, in Montreal, which received $100 million dollars through the Apartment Loan Construction Program (ACLP) to build 303 homes and will be operated by Olymbec. This rental building, named Lynk, is designed to… Read More…