Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Regulations Amending the Products Containing Mercury Regulations – A Call to Consultation

    Regulations Amending the Products Containing Mercury Regulations – A Call to Consultation

    January 29, 2023 By Line Goyette Under the Canadian Environmental Protection Act, 1999, the Canadian government is proposing the Regulations amending the products containing mercury. Consultation is open until March 9, 2023. The Products Containing Mercury Regulations (the Regulations), which were published on November 19, 2014, and came into force on November 8, 2015, prohibit the manufacture and import of products containing mercury… Read More…

  • A Career with Purpose – Apprentices Building Canada’s Reduced Carbon Future

    A Career with Purpose – Apprentices Building Canada’s Reduced Carbon Future

    January 27, 2023 By Yoana Turnin, Project Manager, EHRC In 2021, Canada joined 120+ other countries in committing to achieving net-zero emissions by year 2050 in an effort to “avert the worst impacts of climate change.” In a few words, that means either reducing or offsetting the economy’s greenhouse gas emissions through electrification, energy efficiency… Read More…

  • Challenges, Opportunity, and Labour Demand in the Construction Industry

    Challenges, Opportunity, and Labour Demand in the Construction Industry

    January 27, 2023 By Blake Marchand There is some uncertainty in the overall market right now, relating to inflation, interest rates, even global events like the war in Ukraine have an impact. These factors will have an impact on the construction industry, which may have an impact on broader opportunities for electrical contractors. Although, anecdotally… Read More…

  • First Retrofit Financed by the Canada Infrastructure Bank Receives IREE Certification

    First Retrofit Financed by the Canada Infrastructure Bank Receives IREE Certification

    January 27, 2023 The Canada Green Building Council (CAGBC) and the Canada Infrastructure Bank (CIB) have announced Dream’s 366 Bay St. redevelopment in Toronto is the first retrofit project financed by the CIB to achieve Investor Ready Energy Efficiency (IREE) certification. IREE certification is part of the CIB’s Building Retrofits Initiative and is administered through… Read More…


Changing Scene

  • City Electric Supply Opens Two New Branches

    City Electric Supply Opens Two New Branches

    January 31, 2023 City Electric Supply has annouced two new branches in Sudbury and Kemptville. CES Sudbury: 2302 Algonquin Rd, Greater Sudbury, ON P3E 4Z6 Go HERE for more informaton on the Sudbury branch. CES Kemptville: 11 Precision Dr, Kemptville, ON K0G 1J0 Go HERE for more information on the Kemptville branch. Source Read More…

  • Ouellet Group Rebrands as Innovair Solutions

    Ouellet Group Rebrands as Innovair Solutions

    Ouellet Group has annouced they have changed the name of the parent company for their various business units to Innovair Solutions. Read More…

  • Rexel Canada aims to Advance Digital Transformation with New Appointment

    Rexel Canada aims to Advance Digital Transformation with New Appointment

    January 30, 2023 Jeffery Moyle, VP Suplier & Digital Strategy with Rexel Canada Electric announced the appointment of Nadia Teixeira as Director of Digital for Canada to lead the Rexel Canada’s digital transformation. “In this role, Nadia will lead our digital transformation efforts and will be responsible for the development, maintenance, and acceleration of our… Read More…

  • Legrand Announces Its Intention to Disengage from Russia

    Legrand Announces Its Intention to Disengage from Russia

    January 30, 2023 In view of recent developments, including rising operational complexity and uncertainty, Legrand has decided to divest its Russian operations and is currently reviewing options for transferring their control in a timely and orderly manner. Legrand’s activities in Russia accounted for approximately 1.5% of full-year sales in 2022. As of December31, 2022, the… Read More…