The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code. In this article: Section 18 Hazardous locations, Part 2.

Section 18 covers installation of electrical equipment in hazardous locations as defined in Section 0, such as areas in which there is a potential for the ignition of explosive or combustible gases, dusts, fibres or flyings due to the design, installation or use of electrical equipment. Since the information in this instalment is extensive it is presented in two parts. This Instalment is Part 2.

Explosive gas atmospheres

This part contains rules for the installation of electrical equipment in all locations where explosive gas may be present.

Installations in Zone 0 locations

Rule 18-090 — Zone O is the hazardous location where explosive gas atmospheres are present continuously or for long periods and is the most restrictive. No electrical equipment or wiring may be installed in a Zone 0 hazardous location unless it meets the requirements of subrule 18-090 (2). Also note the marking requirements for Zone 0.

Rule 18-092 — seals are required where conduit leaves a Zone 0 location, and at the first point of termination of cables after entry to the Zone 0 location. Unbroken rigid conduit passing through a Zone 0 need not be sealed if the termination points are outside Zone 0. Seals are not required to be explosion-proof or flame-proof but must be identified for minimizing the passage of fluids or dusts and be accessible.

Installations in Zone 1 locations

Rule 18-100 — electrical equipment suitable for Class I Division 1 with protection level Ga or Gb and protection levels as outlined in 18-100(c) may be installed in a Zone 1 location.

Rule 18-102 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 1. In addition, threads and joints need to comply with 18-102 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-104 provides the rules for sealing conduits and cables entering enclosures in and leaving Zone 1 locations.

Rule 18-106 provides requirements for the installation of motors in Zone 1 locations. Additional guidance is given in Appendix B.

Rule 18-108 provides the rules for installation of Luminaires in Zone 1.

Rule 18-110 — flexible cords are permitted in Zone 1 where flexibility is required but must be installed in accordance with 18-110 (1) and (2).

Installations in Zone 2 locations

Rule 18-150 provides the rules for the installation of equipment in Zone 2. Note that equipment suitable for Class I Division 2 and Zone 0 and Zone 1 are permitted to be installed in Zone 2. Also note that transformers, capacitors, solenoids, and other non-arcing, non-sparking or non-heat-producing devices are permitted in Zone 2 locations.

Rule 18-152 provides rules for wiring methods in Zone 2.

Rule 18-154 provides rules for sealing conduit, cable and equipment in Zone 2.

Rule 18-156 provides rules on installation of luminaires in Zone 2.

Rule 18-158 — flexible cords are permitted in Zone 2 where flexibility is required but must be installed in accordance with 18-158 (1).

Explosive dust atmospheres

This part contains rules for the installation of electrical equipment in all locations where combustible and explosive metal dust may be present.
Installations in Zone 20 locations

Rule 18-190 — like Zone O, Zone 20 is the most restrictive hazardous location where explosive dust atmospheres are present in the form of a cloud of dust in air continuously or for long periods. No electrical equipment or wiring may be installed in a Zone 20 hazardous location unless it meets the requirements of Subrule 18-190.

Rule 18-192 provides requirements for wiring methods in Zone 20.

Rule 18-194 provides requirements for seals for a Zone 20 location.

Rule 18-196 — flexible cords are permitted in Zone 20 where flexible connections are required and shall be extra-hard-usage cord with cable glands.
Installations in Zone 21 locations

Rule 18-200 provides rules for installation of equipment in Zone 21. Equipment suitable for Class II Division 1 is permissible as well as equipment with the noted types of protection in (b) and ©.

Rule 18-202 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 21. In addition, threads and joints need to comply with 18-202 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-204 provides rules for sealing raceway equipment in Zone 21.

Installations in Zone 22 locations

Rule 18-250 provides rules for installation of equipment in Zone 22. Equipment suitable for Class II Division 2 is permissible as well as equipment with the noted types of protection in (b) and (c). This rule also provides rules for installation of cranes, hoists and other material handling equipment in Zone 22 locations.

Rule 18-252 provides rules for wiring methods in Zone 22.

Rule 18-254 provides the same sealing requirements as Zone 21.

In the next instalment we will discuss Section 20 — Flammable liquid and gasoline dispensing, service stations, garages, bulk storage plants, finishing Processes and aircraft hangars.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    September 20, 2024 The Evolution of the Electrical Industry was Showcased eariler this month in Victoria, BC with the 2024 installment of NETCO’s Annual Conference Leaders and experts from the electrical industry will gather in Victoria, BC, September 5-6th, at the picturesque Inn at Laurel Point for the annual National Electrical Trade Council (NETCO) educational… Read More…

  • Desdowd Icon Patrick Marion Retires

    Desdowd Icon Patrick Marion Retires

    September 20, 2024 On September 11, more than 200 industry guests and colleagues celebrated Patrick Marion’s 35-year career history to the day. Guests travelled from across the country – some from as far as Vancouver and Halifax – to join those from Montreal and Toronto to celebrate Patrick’s career. Held at a prestigious golf club… Read More…

  • EFC Letter on China Tariffs

    EFC Letter on China Tariffs

    September 15, 2024 The Canadian federal government intends to apply a 25 per cent surtax on imports of steel and aluminum products from China, effective October 15, 2024. See announcement here. The initial list of impacted goods was released for public comment and submissions are due September 20, 2024.  The list of products is available… Read More…

  • Changing How we Build Homes: A Year of the Housing Accelerator Fund

    Changing How we Build Homes: A Year of the Housing Accelerator Fund

    September 15, 2024 The Government of Canada is highlighting key results that have come from the first Housing Accelerator Fund since the start of the Program. This week marks the closure of the application portal for the second round of the HAF. HAF was created to incentivize local governments to implement structural and lasting reforms that will increase… Read More…


Changing Scene

  • Southwire Signs Contract for Solar System at North Campus Plant

    Southwire Signs Contract for Solar System at North Campus Plant

    September 20, 2024 Southwire is pleased to announce that it has signed an agreement with Statewide Renewable, a solar project developer, to install a solar array at its North Campus Plant.  The company has a long-standing commitment to environmental stewardship and corporate sustainability, and in support of that commitment, is investing in renewable energy as… Read More…

  • Schneider Electric Foundation Turns 25 and Launches the ‘25 Years Young’ Campaign in Canada

    Schneider Electric Foundation Turns 25 and Launches the ‘25 Years Young’ Campaign in Canada

    September 20, 2024  To mark the 25th anniversary of its foundation, Schneider Electric is launching a global campaign in celebration of both this key milestone and the next generation of young leaders committed to building a fairer, low-carbon society. Non-profits could win a 50K€ grand prize and one of five local prizes totaling 75K€ to… Read More…

  • New Funding Announced to Install Over 3,000 EV Chargers Across Canada

    New Funding Announced to Install Over 3,000 EV Chargers Across Canada

    September 20, 2024 The federal government has announced investments of $14.9 million for 20 projects that will install more than 3,000 EV chargers across Canada, while raising awareness of the benefits of EVs and advancing training and code upgrades to ensure more communities have access to current information and opportunities to seize the potential of… Read More…

  • ECABC Statement on the Response to BC Hydro’s Call for Clean Power Projects

    ECABC Statement on the Response to BC Hydro’s Call for Clean Power Projects

    September 20, 2024 Electrical Contractors Association of British Columbia President Matt MacInnis issued the following statement on the response to BC Hydro’s call for clean electricity project proposals: “It is very encouraging to see the private sector bring forward projects offering nearly three times the generation capacity BC Hydro is seeking in this first call… Read More…