Don’t Put Your Business At Risk By Guessing At What Mark-up To Use

Business Markup

 

Shawn McCadden

Mark-ups on any product or service you sell need to be based on projected overhead costs and net profit requirements for producing a specified volume of work. Be careful using someone else’s mark-up suggestions, particularly if they have not done the math to figure it out.

Fact is about 9 out of 10 contractors eventually go out of business because they don’t know the true costs of doing business. They are either guessing at what mark-up to use or guessing at which contractor’s mark-up they should copy.If you’re going to risk copying the mark-up of another contractor, make sure you get your mark-up info from that 1 out of 10.

Think about it, it’s like asking how much money you need for gas to drive across county. Depends on where you start, cost of the gas, how fast you drive, how many miles/gallon, summer or winter, who’s driving…

Also, many magazine articles advise contractors to apply a “professional mark-up” to their bids. But what, exactly, is a professional mark-up? Does a 50% mark-up make you a professional, or should you apply 67% to qualify? The simple answer is, if you don’t know what mark-up your company needs to use, you’re not a professional, and therefore you’re not using a professional mark-up. But if you know the formulas for determining margin and mark-up, you have a working financial tool, rather than a magic number suggested by some remodelling guru or pulled out of a hat by another remodeler.

Different mark-ups, same price

To determine your company’s mark-up, divide your anticipated annual indirect costs (costs of overhead and profit) by your anticipated annual direct costs (costs to produce projects):

Business Markup Table

Therefore, if one company considered its field employees’ health insurance a direct cost, and another company defined it as an indirect cost, those two companies would apply different mark-ups. In theory, if both companies had all of their other costs covered somewhere within their annual budget or estimate, they’d sell their projects at the same price, even though their mark-ups differed.

Remember this the next time you’re impressed or puzzled by what your fellow contractors claim to be using as a mark-up. 


Read more in EIN from Shawn McCadden:

3 Ways To Get Fewer Leads But Close More Remodeling Sales
Don’t Underestimate Your Estimating System’s Potential
Tips on Ball Park Pricing and Charging for Estimates
Is A Contractor Really a Salesperson If He or She Hits Send?
3 Ways To Get Fewer Leads But Close More Remodeling Sales
3 Simple Steps to Covering an Employee’s Non-Productive Time
Setting the Example: Getting Employees to Think Like Owners
Comparing Contractor Mark-ups Can Be Pointless and Very Risky
Don’t Put Your Business At Risk By Guessing At What Mark-up
Simple Profit Sharing Plan for Contractors

Check out Shawn’s website http://www.shawnmccadden.com/ and blog www.shawnmccadden.com/Subscribe-to-The-Design-Builders-Blog.

* “Understanding what impacts your construction company’s reputation,”

http://www.pn-projectmanagement.com/construction-management-tips/understanding-what-impacts-your-construction-companys-reputation

 

Related Articles


Latest Articles

  • Navigating Tariff Uncertainty as an Electrical Contractor

    April 15, 2025 By Matthew Biswas These three words put me into a catatonic shock – Supply Chain Disruption. It seems like just yesterday I was standing at a counter asking for products I’d bought 100’s of times before and being told they are on backorder with no expected delivery date. Circuit breakers, dimmers, panels,… Read More…

  • Four Ways Permanent Power Enahnces Outdoor Spaces

    Four Ways Permanent Power Enahnces Outdoor Spaces

    April 14, 2025 Today’s workplaces are expanding beyond the four walls of an office. As technology continues to evolve, employees are looking for new and alternative workspaces to inspire creativity and increase productivity. This includes taking their work to outdoor spaces. Bringing technology to outdoor spaces has become a challenge for facility managers and property… Read More…

  • CAF-FCA Provides Recomendations on Apprenticeship Investment

    CAF-FCA Provides Recomendations on Apprenticeship Investment

    April 13, 2025 CAF-FCA have provided an outline of actionable recommendations—developed through national consultation—to enhance accessibility, reduce financial barriers, and better align apprenticeship training with industry needs. Source Read More…

  • New Report: Preparing Alberta’s Buildings for Severe Weather

    New Report: Preparing Alberta’s Buildings for Severe Weather

    April 13, 2025 Alberta is facing more severe weather events, with rising temperatures, wildfires, and more frequent extreme storms threatening homes and businesses. Our report, Preparing Alberta’s Buildings for Severe Weather−written in partnership with the Alberta Ecotrust Retrofit Accelerator program−highlights the need for deep retrofits to ensure the province’s buildings can withstand these changing conditions. Four… Read More…


Changing Scene