How the Canadian Electrical Code, Part I Is Amended

Code Amended

William Burr

I am often asked how new rules get in the Code and how one could go about amending a code rule. All of these procedures are outlined in Appendix C of the Canadian Electrical Code, Part I. However, being written as a standard it is sometimes a struggle to follow.I trust this article easily explains the process. 

To start this discussion we need to understand the structure of the Technical Committee of the Canadian Electrical Code, Part I (TC), which is responsible for the development of the Code.

The TC has a maximum of 41 members, consisting of

• chair
• vice-chair

• executive committee (EC) elected by the members
• non-voting project manager appointed by the Canadian Standards Association (CSA)
• sub-committee (SC) for each section of the Code
• Regulatory Authority Committee (RAC).

The chair of the TC, with the advice of the EC appoints a chair for each section SC from among the TC members, and the SC chairs appoint the members of their SC. Anyone representing the following major interests can apply to be a member of a sub-committee: 

• inspection authorities
• manufacturers
• employers
• employees
• consultants
• utilities
• testing laboratories
• underwriters
• fire marshals
• primary and secondary industries
• respective code-making panels of the National Electrical Code
• users

The 41 regular members of the TC are drawn from three main interest groups in conjunction with the following balanced matrix.

Technical Committee Composition

Technical Committee

• The regulatory authorities represent the various provincial, territorial and municipal electrical inspection authorities across the country.
• Owner/operator/producers represent electrical manufacturers, electrical installation designers and installers and electrical installation user groups.
• The general interest category is drawn from fire chiefs, electric utilities, other codes and standards committees, fire insurers, labour, issuers of building codes, and educators groups.

All these members are nominated by the organization they represent and are approved for membership by the executive committee. I will discuss the function of the RAC later in this article.

The TC meets once a year.Additional meetings may be called if warranted. However, much of the business of the TC and Section SCs takes place between meetings through correspondence and electronic media.

Anyone can propose a new Code rule or an amendment to the project manager at CSA using the form contained inAppendix C of the Code.
The proposal must be specifically worded and must:

• improve safety
• address new technology
• correlate with product standard requirements
• correlate with other relevant standards, or
• clarify existing wording

Supporting information for the proposal must also be supplied. 

The PM assigns a subject number to the proposal and sends it to the relevant section SC chair and alsosubmits it for public review on the CSA website. The SC chair distributes the proposal to the subcommittee members with the chair’s comments for discussion. The sub-committee deliberates the proposal, along with any public review comments, and may recommend it, amend it, keeping the original intent, or reject the proposal. The SC chair then provides a report with the recommendations of the sub-committee to the TC for letter ballot.

If the letter ballot is affirmed by more than 50% of the total voting membership with no negative votes, it is approved and, except for a recommendation of rejection, will be published in the next version of the Code. In the case of negative votes, the chair of the SC in consideration of the negative votes has a number of courses of action:

• resolve the negative by editorial changes or further explanation
• rule the negative vote non-germane if it is not accompanied by supporting comments, if it doesn’t deal with the intent, the procedure, technical content or conflict with another rule or standard, of the proposal
• the negative vote and supporting reasons are not considered to be relevant to the original proposal
• the negative vote can be ruled non-persuasive if the reasons have previously been discussed by the subcommittee as outlined in the subcommittee report.

If there are any negative votes that cannot be resolved by the SC chair, then the subject is put on the agenda of the next meeting of the TC.

When a letter ballot is on the agenda of a meeting, the subject is introduced by the chair of the SC who explains the deliberations of the SC and the negatives that couldn’t be resolved. An open discussion takes place followed by a vote. If the subject is affirmed by a two-thirds majority, with no Regulatory Negative, then the subject is approved.

Whoa! What’s a Regulatory Negative? Well, I mentioned earlier that I would discuss the Regulatory Authority Committee later in this article.

The RAC comprises the regulatory authority representatives on the TC and is essentially the guardian of the legal framework of the Code. Since the Code is a legally adopted document by provincial, territorial, and municipal governments, the regulatory authorities need to make sure that the wording of any rules are suitable for enforcement.If any RAC member feels that a proposal for amendment to the Code is not enforceable in their jurisdiction, they may vote a Regulatory Negative. This member must declare that their negative vote is a Regulatory Negative as opposed to a negative for any other technical reason.The subject is then referred to the Regulatory Authority Committee, which must develop a revised amendment carrying the same intent, in terms of safety and technical requirements, and submit it to the Section SC for further consideration.It must be noted that this is not a veto, but an alternative wording with the same intent as the original proposal.

Note: information for this article has been sourced from The Canadian Electrical Code, Part I, published by CSA Group.


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Take the Lesson

    Take the Lesson

    September 2, 2024 By Keith Sones, seasoned utility industry executive “I really don’t want to do this.” “You have to Keith. You have no choice. You can’t leave him hanging” replied my wife. I stared at the phone like a child looks at liver on their plate. They know you have to eat it but also… Read More…

  • Quebec Drives the Growth in Residential Building Construction in June, 2024

    Quebec Drives the Growth in Residential Building Construction in June, 2024

    Investment in building construction grew 2.8% to $21.4 billion in June, after a slight increase of 0.8% in May. These increases partly reflect April’s record high of $13.4 billion in total building permits value, since investment levels for a given period are driven by permits issued in prior months. The June increase in investment in building construction was primarily… Read More…

  • Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    August 16, 2024 The new Western Memorial Regional Hospital in Corner Brook is home to Canada’s largest geothermal system, which has set a precedent for modern infrastructure for both Newfoundland and Labrador and North America. The geothermal field is approximately 600 feet below the hospital’s parking lot, and provides 100 per cent of the ground… Read More…

  • Brightening Communities: LED Technology in Action

    Brightening Communities: LED Technology in Action

    August 15, 2024 By Alex Price, Brand & Planning Manager, Current LightingTechnical Contributor: Gary Steinberg, Senior System Manager (Outdoor LED Fixtures), Current Lighting As the landscape of Canadian cities continues to evolve, the importance of outdoor lighting cannot be overstated. From enhancing public safety to promoting economic activity and fostering a sense of community, well-planned… Read More…


Changing Scene

  • Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric is transforming its Digital Buildings business in Canada with the launch of the SMART Buildings Division. This evolution marks a strategic move to deliver comprehensive solutions and services that support building owners and operators in achieving their decarbonization and sustainability goals. The demand for smart buildings is surging, driven by a global shift… Read More…

  • Introducing Alan Bearden as Interim President of Southwire Canada

    Introducing Alan Bearden as Interim President of Southwire Canada

    September 4, 2024 Southwire Canada is pleased to announce that Alan Bearden has been appointed Interim President. In this role, Alan will provide leadership and guidance for Southwire’s Canada-based organization, ensuring continuity and driving growth during this transitional period. Alan Bearden brings a wealth of experience to the position, having joined Southwire in 2008. Over… Read More…

  • A Partnership Between Electromag Graybar Canada and Phoenix Contact

    A Partnership Between Electromag Graybar Canada and Phoenix Contact

    September 3, 2024 Electromag Graybar Canada, a pioneer in industrial automation solutions and pneumatic products, is excited to announce a partnership with Phoenix Contact, a global leader in electrification, networking, and industrial automation. This collaboration, which initially began in the Langley and Ontario branches, is now expanding to Quebec. The alliance aims to provide cutting-edge… Read More…

  • Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    September 2, 2024 William (Bill) C. Smith, Director, Transitional Business of Electrozad Supply Company Limited announced his retirement as of August 30th, 2024 after 49 years of leadership. Bill began his electrical career working part-time at Electrozad Supply while completing a Sales & Marketing Program at St. Clair College.  After his first full-time position in… Read More…