Guide to the Canadian Electrical Code, Part I — Instalment 39

Bill Burr

 

July 9, 2018

By William (Bill) Burr

The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook** but will hopefully provide some help in navigating, while reading the code.

The 24th Edition of the CE-C, Part I, (C22.1-18)* is now available from CSA Group. This discussion of Section 78 — Marine Wharves, Docking Facilities, Fixed and Floating Piers, and Boathouses is based on the new edition.

Rule 78-000 notes that notes that this is a supplementary or amendatory section of the code and applies to the installation of electric equipment and wiring methods on marine wharves, fixed or floating piers, docking facilities, and boathouses that are used for the construction, repair, storage, launching, berthing, and fuelling of watercraft. Appendix B and the CEC Handbook provide additional information.

Rule 78-002 contains definitions for special terminology used in this section for Boathouse, Docking facility, Fixed pier, Floating pier, and Marine wharf. It is important to understand these terms because of the specific applications for each situation.

General

The rules in this General part apply to all installations under this section.

Rule 78-050 outlines the requirements for receptacles and requires that

  • receptacles installed outdoors on fixed or floating piers, docking facilities, marine wharves, boathouses, and supplying shore power to boats be
    • straight blade or locking type conforming to either Diagram 1 or 2 for receptacles rated 15 A and 20 A
    • locking type conforming to Diagram 2 or of the pin and sleeve type for receptacles rated over 20 A up to and including 60 A
    • pin and sleeve type for receptacles rated over 60 A (note: other configurations for shore power are permitted for specific applications), and
  • all receptacles be
    • made of corrosion-resistant materials and provided with weatherproof enclosures (Appendix B discusses suitable materials)
    • installed in accordance with Rule 26-708 where exposed to the weather
    • located above the maximum normal water level and protected from splashing
    • protected by a ground fault circuit interrupter of the Class A type for all receptacles rated at 125 V, 15 A or 20 A

Rule 78-052 provides the requirements for branch circuits and feeders, and requires that

  • a separate and individual branch circuit supply shore power to boats and not supply any other equipment
  • ground fault protection be provided to de-energize all ungrounded conductors of each feeder for distribution equipment for floating piers, docking facilities, and boathouses, set low enough to permit normal operation, but not greater than 30mA
  • additional ground fault protection for branch circuits installed in or on fixed or floating piers, docking facilities, and boathouses is not required where distribution conductors are provided protection, as above

Rule 78-054 provides the demand factors for the load for each feeder and service supplying receptacles intended for supplying shore power to boats and are calculated as follows:

  • 100% of the sum of the first four receptacles having the highest ampere ratings, plus
  • 65% of the sum of the ampere ratings of the next 4 receptacles having the same or next smaller ratings, plus
  • 50% of the sum of the ampere ratings of the next 5 receptacles having the same or next smaller ratings, plus
  • 25% of the sum of the ampere ratings of the next 16 receptacles having the same or next smaller ratings, plus
  • 20% of the sum of the ampere ratings of the next 20 receptacles having the same or next smaller ratings, plus
  • 15% of the sum of the ampere ratings of the next 20 receptacles having the same or next smaller ratings, plus
  • 10% of the sum of the ampere ratings of the remainder of the receptacles, plus
  • other loads added in accordance with the Rules of Sections 8 and 14

Rule 78-056 requires wiring methods that

  • protect installations from mechanical damage, corrosion and severe weather conditions, including exposure to moisture, splashing of water and spray using
    • corrosion-resistant rigid metal, RTRC or PVC conduit
    • mineral-insulated cable having a copper sheath
    • non-metallic-sheathed cable of the NMWU type
    • armoured cable having moisture-resistant insulation and overall corrosion protection, or
    • metal-sheathed cable having overall corrosion protection;
  • allow for tidal movement, or flexibility using a hard usage, outdoor flexible cord suitable for wet locations selected in accordance with Rule 12-402, and supported by gripping at both ends unless fastened to a structure
  • avoid mechanical damage of conduit, cable, and overhead wiring by installing and routing to avoid conflict with other users of the facility
  • prevent damage to conduit, cable, and wiring systems from wave action, ice, storm damage, and mooring hooks and lines
  • provide fastening hardware of galvanized steel, stainless steel, PVC-coated steel, brass, or other materials with similar corrosion-resistant properties

Rule 78-058 requires that bonding and grounding conductors be copper, be installed in accordance with Section 10, and be a minimum No. 12 AWG, if installed in areas subject to salt water splashing or spray.

Where it is impractical to install a shore-based grounding electrode because of poor earth conductivity, an underwater grounding grid conforming to the following methods may be used:

  • a readily accessible grounding conductor connection, to a steel piling, founded in the harbour bottom and continually immersed in salt water with the grounding conductor mechanically protected throughout its length; or
  • a thermit-welded grounding conductor connection to a minimum 10 mm thick and 0.36 m2 in area, steel plate electrode, founded on the harbour bottom on the prevailing wind lee side of the wharf. The connection must be mechanically protected to a point 2 m below the normal low tide elevation.

Rule 78-060 specifies that wiring over and under navigable water must comply with the Government of Canada’s Navigation Protection Act, R.S.C. 1985, c. N-22.

Rule 78-062 requires that installations for gasoline dispensing stations be in accordance with Section 20, with the grade or ground level of the hazardous area determined by the highest water surface and including the total tidal movement space.

Rule 78-064 requires that communication systems be installed in conformance with Section 60.

Marine wharves, fixed and floating piers, and docking facilities

The following rules in this part are specific to the above facilities.

78-100 General

Rule 78-102 applies to electrical installations on marine wharves, fixed and floating piers, and docking facilities.

Rule 78-102 requires that electrical equipment be protected by locating it

  • to avoid interference with vehicular traffic, docking, unloading and loading of vessels, and operation of wharf equipment
  • above the wharf, pier, or docking facility deck and protected from wave action, ice, storm damage, and mooring lines
  • to minimize the risk of damage from wave action and splashing
  • to avoid impact from docking vessels and vehicular traffic on the wharf

In addition, receptacles, communication systems, equipment, and other electrical apparatus, subject to mechanical damage from boats, vehicles, or other apparatus, must be protected by mounting the equipment in robust shrouds or kiosks constructed of metal, concrete bollards, plywood, or fibreglass, or by other equivalent methods.

In the next instalment, we will be discussing Section 80 – Cathodic Protection.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting; billburr@gmail.com

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

**Note the CEC Handbook is also published by CSA.

 

Related Articles


Latest Articles

  • Electrical Permit Requirements for Alarm System and Voice, Data, Video Installations

    Electrical Permit Requirements for Alarm System and Voice, Data, Video Installations

    January 19, 2026 Other than the exceptions listed below, electrical permits and inspections are required for all electrical work involved in the installation of intrusion and similar alarm systems in all structures. Electrical permits and inspections ensure that low -voltage systems are installed safely and in compliance with Code requirements. A permit and inspections must Read More…

  • The Role of Lighting in the AI-Powered Home

    The Role of Lighting in the AI-Powered Home

    January 14, 2026 Elizabeth Parks, President and CMO of Parks Associates, joins Derek Richardson, Founder and CEO of Deako, for a wide-ranging conversation on how lighting is becoming a core layer of the intelligent home. The discussion explores how Deako’s plug-and-play lighting approach is removing long-standing barriers to adoption by simplifying installation, reducing costs, and Read More…

  • What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    January 14, 2025 By John Kerr From the ground, many contractors and plant teams are experiencing the same thing: jobs are there, but they are smaller, more price‑sensitive, and slower to release compared to past years. The Canadian Pulse of Lighting confirms that impression and offers some clear signals about how contractors and plant electrical Read More…

  • Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    January 12, 2026 By Bill Burr The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the Read More…


Changing Scene

  • Leviton Canada Partners with The Titan Group to Strengthen Midwest Presence

    Leviton Canada Partners with The Titan Group to Strengthen Midwest Presence

    January 19, 2026 Leviton Canada is proud to announce its partnership with The Titan Group, who will now represent Leviton’s Residential and Commercial & Industrial product lines across the Midwest provinces, effective January 1, 2026. “We’re excited to begin our partnership with Titan,” said Bill Tischner, Western Sales Director. “Their industry expertise, commitment to service, Read More…

  • Hammond Power Solutions Appoints Xavier Biot as Vice President, Strategic Accounts

    Hammond Power Solutions Appoints Xavier Biot as Vice President, Strategic Accounts

    January 19, 2026 Hammond Power Solutions is pleased to announce the appointment of Xavier Biot as Vice President, Strategic Accounts. In this role, he will lead HPS’s strategic account teams. He will partner with customers to align transformer and power quality solutions with evolving electrification, sustainability, and operational needs. His focus will be on helping Read More…

  • Hammond Manufacturing Expands to Western Canada

    Hammond Manufacturing Expands to Western Canada

    January 13, 2026 Hammond Manufacturing have announced that they are opening a new distribution facility in the Southeast of Calgary, Alberta. The new facility includes over 50,000 sq ft of warehouse space. “This addition will better serve our customers in Western Canada and stock volume and larger products to ensure our distributors have an improve stock Read More…

  • ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    January 12, 2026 ABB will supply a complete package of power, propulsion and control technology for four new double-ended passenger and car ferries operated by British Columbia Ferry Services (BC Ferries). One of the largest ferry operators in the world, BC Ferries provides year-round vehicle and passenger service on 25 routes to 47 terminals, carrying Read More…