|

Conductor Selection in Practice: A Code-Based Approach to Cable Sizing

July 6, 2026

By Sophia Shereni, P.Eng

Proper cable sizing is a critical part of electrical system design, it directly affects safety, reliability, and equipment performance. At first pass, it’s easy to assume that matching a conductor’s ampacity to the circuit’s full load current is sufficient. In practice, it rarely is. Cable sizing under the Canadian Electrical Code is not a single lookup; it’s a sequence of constraints, each one capable of overriding the last.

A conductor that satisfies ampacity may fail after ambient correction. One that clears derating may still be disqualified by its termination temperature rating. This article walks through each criterion in order using a worked example, a 28 hp, 3-phase, 600 V motor circuit to show how the conductor selection evolves from first pass to final selection.

Ambient Temperature

The ampacity tables in CSA C22.1 are based on a standard ambient temperature of 30 °C. In practice, many installations exceed this reference condition.

Electrical rooms, rooftops, and areas near heat-generating equipment are common examples. When the actual ambient temperature is higher than 30 °C, the allowable current-carrying capacity of the conductor must be reduced.

This adjustment to account for ambient temperature is done by applying a temperature correction factor from CSA C22.1, Table 5A.

Termination Temperature Limits

Electrical cables are manufactured with defined insulation temperature ratings. However, the equipment they connect to may be rated for a lower temperature.

Circuit breakers, panelboards, generators, and motor terminals all have termination ratings. To avoid overheating at connection points, conductor ampacity must be based on the termination temperature rating, not solely on the insulation rating. Where the two differ, the lower rating governs.

This is an important practical point. Although 90 °C cables are commonly installed, they cannot always be loaded to their full 90 °C ampacity. In many applications, a larger conductor is required to meet the ampacity requirement while staying within the termination limit.

Cable Bundling

When multiple conductors are installed in the same conduit or cable tray, heat dissipation is reduced. A single conductor can transfer heat to the surrounding air relatively efficiently. When conductors are grouped together, the overall heat output raises the local ambient temperature.

The result is a higher conductor operating temperature and a lower allowable current-carrying capacity for each conductor in the group.

Because of this, a derating factor must be applied when more than three current-carrying conductors are grouped together (CSA C22.1, Table 5C). As more conductors are added, the derating becomes greater, meaning a conductor that is adequate when installed alone may no longer be sufficient when bundled.

Voltage Drop

Electrical equipment is designed to operate at a specific voltage, and CSA C22.1, Rule 8-102 typically limits voltage drop to 3% for branch circuits and 5% overall from service entrance to point of use.

As current flows through a conductor, a voltage drop occurs due to its impedance. This loss increases with circuit length – a factor that ampacity calculations don’t account for. A conductor can be perfectly sized for current-carrying capacity and still deliver insufficient voltage at the load end.

This is especially important for motors. Low voltage reduces starting torque, increases current draw, and can prevent the motor from reaching its rated speed. At this point, circuit length becomes a key design factor.

For longer runs, voltage drop can become the governing factor, requiring a larger conductor even where all ampacity checks have already been satisfied.

Worked Cable Sizing Example

PARAMETERVALUE
LOAD28 hp, 3-phase motor
SUPPLY VOLTAGE600V, 3-phase
CABLE TYPECopper, 90 °C rated
INSTALLATION METHODCable Tray
AMBIENT TEMPERATURE40 °C
NUMBER OF CONDUCTORS IN TRAYMaximum
NUMBER OF CONDUCTORS IN CABLE2+
CABLE LENGTH30 m
FULL LOAD CURRENT (FLA)28 A
AMPACITY35 A

CSA C22.1 Rule 28-106 Minimum Ampacity: Motor branch circuit conductors must be sized for a minimum of 125% of FLA.

Design Ampacity = 1.25 × 28 A = 35 A (this value governs all subsequent steps)

Step 1 – Base Ampacity (CSA C22.1 Table 2)

From CSA C22.1, Table 2, a #10 AWG copper conductor has a base ampacity of 40 A at 90 °C. This exceeds the FLA of 35 A and is selected as the starting candidate.

Step 2 – Ambient Temperature Correction (CSA C22.1 Table 5A)

Ampacity tables assume a 30 °C ambient temperature. Since the actual ambient is 40 °C, a correction factor must be applied. From CSA C22.1, Table 5A, for 90 °C insulation at 40 °C ambient, correction factor is 0.91.

#10 AWG:

 Calculation Result
Base ampacity (#10 AWG, 90 °C, Table 2)40 A
Ambient correction (×0.91, Table 5A)40 × 0.91 = 36.4 A ✓

36.4 A > 35 A. #10 AWG passes ambient correction. Proceed to bundling check

Step 3 – Bundling Derating (CSA C22.1 Table 5C)

Mutual heating in cable tray reduces each conductor’s ability to dissipate heat.

Design Note: Raceway often start out only partially filled, but as projects grow and routing changes, they usually end up fully loaded. Designing for the worst-case derating (43+ conductors) from the beginning helps avoid having to resize conductors later.

#10 AWG

 Calculation Result
Base ampacity (#10 AWG, 90 °C, Table 2)40 A
Ambient correction (×0.91, Table 5A)40 × 0.91 = 36.4 A ✓
Bundling derating (×0.5, Table 5C)36.4 × 0.5 = 18.2 A ✗

18.2 A < 35 A. #10 AWG fails bundling derating. Step up to #8 AWG.

#8 AWG

 Calculation Result
Base ampacity (#8 AWG, 90 °C, Table 2)55 A
Ambient correction (×0.91, Table 5A)55 × 0.91 = 50.1 A ✓
Bundling derating (×0.5, Table 5C)50.1 × 0.5 = 25.1 A ✗

25.1 A < 35 A. #8 AWG fails bundling derating. Step up to #6 AWG.

#6 AWG

 Calculation Result
Base ampacity (#6 AWG, 90 °C, Table 2)75 A
Ambient correction (×0.91, Table 5A)75 × 0.91 = 68.3 A ✓
Bundling derating (×0.5, Table 5C)68.3 × 0.5 = 34.1 A ✗

34.1 A < 35 A. #6 AWG fails bundling derating. Step up to #4 AWG.

#4 AWG

 Calculation Result
Base ampacity (#4 AWG, 90 °C, Table 2)95 A
Ambient correction (×0.91, Table 5A)95 × 0.91 = 86.5 A ✓
Bundling derating (×0.5, Table 5C)86.5 × 0.5 = 43.2 A ✓

43.2 A > 35 A. #4 AWG satisfies ampacity after bundling derating

Step 4 – Termination Temperature Limitation (CSA C22.1 Rule 4-006)

Although the cable is rated 90 °C, the connection terminals are rated 75 °C. Per CSA C22.1 Rule 4-006, the lower temperature governs. Ampacity must be re-evaluated using the 75 °C column of CSA C22.1 Table 2. The ambient correction factor at 40 °C for 75 °C insulation is 0.88 (Table 5A).

#4 AWG at 75 °C:

 Calculation Result
Base ampacity (#4 AWG, 75 °C, Table 2)85 A
Ambient correction (×0.88, Table 5A)85 × 0.88 = 74.8 A ✓
Bundling derating (×0.5, Table 5C)74.8 × 0.5 = 37.4 A ✓

37.4 A > 35 A, #4 AWG satisfies ampacity under all conditions including the 75 °C termination constraint.

Step 5 – Voltage Drop Verification (CEC Rule 8-102)

CSA C22.1, Rule 8-102 limits voltage drop to 3% for branch circuits. With a 30 m run, voltage drop is evaluated to confirm it is not a governing sizing factor.

#4 AWG at 75 °C:

 Calculation Result
Voltage Drop AC Cosφ=power factor=0.8, R=1.01 Ω/km, X=0.109 Ω/km= √3 × I × L × (R cosφ + X sinφ) = √3 × 28 × (30/100) × [(1.01 × 0.8) + (0.109 × 0.6)] = 12.7 V
%VD(12.7 / 600) × 100 = 2.12% ✓

Final Summary

Sizing CheckRequirement#10 AWG#8 AWG#6 AWG#4 AWG
Base ampacity
(90 °C, Table 2)
> 35 A40 A ✓55 A ✓75 A ✓95 A ✓
After ambient correction (×0.91)> 35 A36.4 A ✓50.1 A ✓68.3 A ✓86.5 A ✓
After bundling derating (×0.5)> 35 A18.2 A ✗25.1 A ✗34.1 A ✗43.2 A ✓
After termination limit 75 °C (×0.88, ×0.5)> 35 A37.4 A ✓
Voltage Drop< 3%2.12 % ✓

Cable sizing is not a one-step process. In this example, a circuit that first looked suitable for #10 AWG ended up requiring #4 AWG once real installation conditions were considered. Each adjustment may seem small, but together they add up. Designing based on ideal conditions can easily lead to undersized conductors in practice.

Related Articles


Latest Articles

  • Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    September 3, 2026 By Blake Marchand In this Q&A with Stephanie Medeiros, the Head of Mobility at Schneider Electric Canada provides insight into her perspective on EV charging infrastructure in Canada, factors that will contribute to growing EV adoption, grid modernization for commercial fleets, the role of Vehicle-to-Grid and other innovative approaches to electrification. The focus of… Read More…

  • LEDVANCE: Understanding Light Beam Angles

    LEDVANCE: Understanding Light Beam Angles

    September 3, 2026 Light Beam Angles: How It Affects Different Types of Lighting, Where It Is Applied & What to Consider When Choosing the Right One Beam angle is important in lighting design. It determines how light spreads within a space and influences both functionality and atmosphere. By understanding beam angles, you can achieve both… Read More…

  • ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    September 2, 2026 By ITC Electrical Components When selecting industrial electrical components, certification is more than a logo on a datasheet. A certification mark indicates that a product or component has been independently evaluated against specified requirements for its intended market. In North America, selecting products with the appropriate certification can affect regulatory acceptance, equipment… Read More…

  • Project Spotlight: Leigh Square Fountain

    Project Spotlight: Leigh Square Fountain

    September 2, 2026 In spring 2025, the City of Port Coquitlam unveiled a transformed Leigh Square, reimagined as a vibrant, accessible, and welcoming gathering place in the heart of downtown. At the heart of the renewed plaza, a Bellagio-style programmable dancing fountain is integrated directly into the paving—three interlocking rings where jets rise, fall, and… Read More…


Changing Scene

  • 2026 Ontario Apprenticeship Awards Call for Nominations

    2026 Ontario Apprenticeship Awards Call for Nominations

    September 3, 2026 Skilled Trades Ontario is proud to open nominations for the 2026 Ontario Apprenticeship Awards, recognizing outstanding apprentices, journeypersons, organizations and skilled trades leaders who are helping strengthen Ontario’s apprenticeship system. Award recipients will be announced at the Ontario Apprenticeship Summit on November 4, 2026, at the Toronto Congress Centre. Nominations must be submitted… Read More…

  • Bartle & Gibson Announces New Partnership with Hubbell Canada

    Bartle & Gibson Announces New Partnership with Hubbell Canada

    September 3, 2026 Bartle & Gibson Co. Ltd., an Alberta-based premier plumbing, heating and electrical distributor and Hubbell Canada have announced a new regional partnership enabling increased access to Hubbell Canada’s end-to-end electrical product portfolio across Western Canada. “With our strong presence in the west through 31 branches and counting located in Alberta, Saskatchewan, British… Read More…

  • Bartle & Gibson Opens Salmon Arm Location

    Bartle & Gibson Opens Salmon Arm Location

    September 3, 2026 Bartle & Gibson opened their new Salmon Arm location on July 20th. The Salmon Arm location features: This site is strategically positioned in the city of Salmon Arm, located near to the busy Picadilly Mall.  Salmon Arm branch is located at: 621- 10 Street SW Salmon ARM, BC V1E 1T1 Photo Source Read More…

  • MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    September 3, 2026 MacKinnon Magnetics is pleased to welcome Resilient Sales Corporation as their newest sales agency partner. Resilient Sales will represent MacKinnon Magnetics across Northeastern Ontario, including the Districts of Muskoka and Parry Sound. Key markets include Sudbury, North Bay, Timmins, Kirkland Lake, Sault Ste. Marie, Huntsville, Bracebridge and Parry Sound. “This partnership expands… Read More…