Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles

  • Take the Lesson

    Take the Lesson

    September 2, 2024 By Keith Sones, seasoned utility industry executive “I really don’t want to do this.” “You have to Keith. You have no choice. You can’t leave him hanging” replied my wife. I stared at the phone like a child looks at liver on their plate. They know you have to eat it but also… Read More…

  • Quebec Drives the Growth in Residential Building Construction in June, 2024

    Quebec Drives the Growth in Residential Building Construction in June, 2024

    Investment in building construction grew 2.8% to $21.4 billion in June, after a slight increase of 0.8% in May. These increases partly reflect April’s record high of $13.4 billion in total building permits value, since investment levels for a given period are driven by permits issued in prior months. The June increase in investment in building construction was primarily… Read More…

  • Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    August 16, 2024 The new Western Memorial Regional Hospital in Corner Brook is home to Canada’s largest geothermal system, which has set a precedent for modern infrastructure for both Newfoundland and Labrador and North America. The geothermal field is approximately 600 feet below the hospital’s parking lot, and provides 100 per cent of the ground… Read More…

  • Brightening Communities: LED Technology in Action

    Brightening Communities: LED Technology in Action

    August 15, 2024 By Alex Price, Brand & Planning Manager, Current LightingTechnical Contributor: Gary Steinberg, Senior System Manager (Outdoor LED Fixtures), Current Lighting As the landscape of Canadian cities continues to evolve, the importance of outdoor lighting cannot be overstated. From enhancing public safety to promoting economic activity and fostering a sense of community, well-planned… Read More…


Changing Scene

  • Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric is transforming its Digital Buildings business in Canada with the launch of the SMART Buildings Division. This evolution marks a strategic move to deliver comprehensive solutions and services that support building owners and operators in achieving their decarbonization and sustainability goals. The demand for smart buildings is surging, driven by a global shift… Read More…

  • Introducing Alan Bearden as Interim President of Southwire Canada

    Introducing Alan Bearden as Interim President of Southwire Canada

    September 4, 2024 Southwire Canada is pleased to announce that Alan Bearden has been appointed Interim President. In this role, Alan will provide leadership and guidance for Southwire’s Canada-based organization, ensuring continuity and driving growth during this transitional period. Alan Bearden brings a wealth of experience to the position, having joined Southwire in 2008. Over… Read More…

  • A Partnership Between Electromag Graybar Canada and Phoenix Contact

    A Partnership Between Electromag Graybar Canada and Phoenix Contact

    September 3, 2024 Electromag Graybar Canada, a pioneer in industrial automation solutions and pneumatic products, is excited to announce a partnership with Phoenix Contact, a global leader in electrification, networking, and industrial automation. This collaboration, which initially began in the Langley and Ontario branches, is now expanding to Quebec. The alliance aims to provide cutting-edge… Read More…

  • Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    September 2, 2024 William (Bill) C. Smith, Director, Transitional Business of Electrozad Supply Company Limited announced his retirement as of August 30th, 2024 after 49 years of leadership. Bill began his electrical career working part-time at Electrozad Supply while completing a Sales & Marketing Program at St. Clair College.  After his first full-time position in… Read More…