Guide to the Canadian Electrical Code, Part 1, 25th Edition– A Road Map: Section 76

December 12, 2022

Section 76 — Temporary Wiring – 25th Edition

 (The 25th Edition of the CE-C, Part I, (C22.1-21)* is available from CSA Group. This discussion of Section 74 is based on the 25th edition.)

Sometimes it is impracticable to follow the rules for permanent installations when installing temporary wiring for construction or demolition projects. In many instances, the wiring needs to be portable, flexible and easily modified. In addition to this Section, Appendix G references Section 5.6.1.9. (3) of the National Fire Code of Canada, 2015, Temporary Electrical Installations on Construction and Demolition Sites.

Rule 76-000 notes that this is a supplementary or amendatory section of the code and applies to temporary wiring installations for buildings or projects under construction or demolition and experimental or testing facilities of a temporary nature.  Section 76 does not apply to temporary installations in amusement parks, midways, carnivals, film and TV sets, TV remote broadcasting sites, home shows, live theatre, and travelling shows that are held indoors, outdoors, or in tents, which are covered by Section 66.

Rule 76-002 requires that conductors be:

  • Section 12, rules 12-402(1) or 12-406(1) and power supply cable or flexible, outdoor, extra-hard usage cord Conductors.
  • 10-116.
  • Sections 6, 10, and 36 for service conductors; and

Rule 76-004 requires that all grounding and bonding be in accordance withSection 10.

Rule 76-006 specifies that where service entrance equipment is installed outdoors, it must be:

  • accessible to only authorized persons,
  • lockable,
  • protected from weather and mechanical damage, and
  • not exceed 200 amps mounted on a single pole.

Rule 76-008 provides that distribution centres:

  • Have adequate capacity and number of branch circuits in accordance withSection 14.
  • Be of weatherproof construction or installed in a weatherproof building;
  • Be mounted in an upright position.

Rule 76-010 requires that feeders supplying distribution centres be:

  • Installed armoured cable or equivalent,
  • Installed in outdoor, extra-hard usage flexible cord or power supply cable containing a bonding conductor in accordance with 12-402(1) or 12-406(1) for a portable distribution Center,
  • Protected from mechanical damage and
  • Protected with suitable over-current devices and a disconnecting means.  

Rule 76-012 governs the installation of branch circuits and requires that:

  • Non-metallic-sheathed cable be installed in accordance with Rules 12-500 to 12-526,
  • Lighting branch circuits be kept separate from power branch circuits,
  • luminaires or lampholders be of a type and installed in compliance with Section 30,
  • The connected load of each lighting branch circuit may not exceed 80% of the circuit breaker rating in accordance with Rule 30-104,
  • Power branch circuits be provided with separate circuits for:
    • Motors sized and protected in accordance with Section 28,
    • Known loads limited to 80% of the rating of the circuit breaker,
    • General-use receptacles with the breaker not exceeding the rating of the lowest-rated receptacle.

Rule 76-014 specifies that temporary installations must be separate and not interconnected with any circuits of the permanent installation without special permission as per Rule 2-030.

Rule 76-016 states that all CSA configuration 5-15R or 5-20R receptacles be protected by a Class A GFCI.

In the next installment, we will be discussing Section 78 – Marine Wharves, Docking Facilities, Fixed and Floating Piers, and Boathouses.


Source: CSA C22.1:21, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. © 2021 Canadian Standards Association. Please visit store.csagroup.org. With the permission of CSA Group, material is reproduced from CSA Group standard CSA C22.1:21, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. This material is not the complete and official position of CSA Group on the referenced subject, which is represented solely by the Standard in its entirety. While use of the material has been authorized, CSA Group is not responsible for the manner in which the data are presented, nor for any representations and interpretations. No further reproduction is permitted. For more information or to purchase standard(s) from CSA Group, please visit store.csagroup.org or call 1-800-463-6727.

William (Bill) Burr is an associate member of the Canadian Electrical Code, Part 1, Technical Committee and formerly Chair of the Canadian Advisory Council on Electrical Safety (CACES), Chief Electrical and Elevator Inspector for the Province of BC & the Northwest Territories, Director of Electrical and Gas Standards Development and Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com..

Related Articles


Latest Articles

  • ESA Provides an Update on its New Self-Serve Licensing Platform

    ESA Provides an Update on its New Self-Serve Licensing Platform

    March 27, 2026 In October 2025 Electrical Safety Authority (ESA) officially launched its new self-serve licensing platform, a modern system designed to transform how Master Electricians (MEs) and Licensed Electrical Contractors (LECs) manage their licensing needs. The platform replaces paper-based processes and provides a centralized, web-based experience for renewing and applying for licences, paying fees Read More…

  • BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    March 27, 2026 Starting April 1, 2026, our battery rebate offer is changing. The offer will include: Applications submitted before April 1, 2026, will be reviewed under the current rebate amounts. New requirement for working with contractors Beginning June 1, 2026, solar and battery installations must be completed by a Home Performance Contractor Network (HPCN) member to Read More…

  • CSA Report: Online Sales of Unapproved Consumer Electrical Products in Canada

    CSA Report: Online Sales of Unapproved Consumer Electrical Products in Canada

    March 27, 2026 Canadian electrical regulators have identified that the online sales of unapproved consumer electrical products are of a serious concern, and with the growing number of online marketplaces globally there is likely a higher volume of unapproved, or non-compliant, consumer electrical products available for purchase to Canadian consumers. In 2025, Canadian Standards Association Read More…

  • Tackling Unsafe Electrical Products Sold Online: Key Outcomes from the National Workshop Agreement 

    Tackling Unsafe Electrical Products Sold Online: Key Outcomes from the National Workshop Agreement 

    March 27, 2026 By Electro-Federation Canada The rapid growth of e-commerce has transformed how Canadians purchase electrical products, but it has also introduced new safety risks. EFC members have been raising concerns for several years about the increasing availability of unsafe and unapproved electrical products sold online, often without clear evidence of certification or compliance with Canadian requirements. To Read More…


Changing Scene

  • Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    March 27, 2026 — Skills Ontario welcomes the 2026 Ontario Budget: A Plan to Protect Ontario, released today by the Ontario Government and Minister of Finance Peter Bethlenfalvy, and applauds the continued commitment to investing in skilled trades, technologies, and workforce development. Skills Ontario was pleased to see the government maintain and strengthen its support Read More…

  • Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    April 27, 2026 Toronto Hydro is launching a trailblazing customer pilot project designed to help local builders electrify multiplex housing without complex service upgrades. Through Toronto Hydro’s Multiplex PowerPlay, up to six multiplex projects can qualify to receive funding toward a smart energy load management system. Smart load management systems continuously monitor total building energy Read More…

  • Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    March 25, 2026 Gescan, a Sonepar Company, is proud to highlight its continued commitment to supporting communities across Saskatchewan through their meaningful alliance with George Gordon Developments Ltd. (GGDL). With a strong focus on community development, workforce participation and inclusive growth, Gescan is working closely with GGDL to create training, employment and business opportunities for Saskatchewan residents. These efforts are particularly focused on supporting individuals Read More…

  • Electric Avenue Launches Incentive Program for EV Charging Installers

    Electric Avenue Launches Incentive Program for EV Charging Installers

    March 23, 2026 Halifax-based EV charging solutions provider Electric Avenue has announced the official launch of its new Contractor Incentive Program, a first-of-its-kind initiative in the EV charging industry, built exclusively for contractors who have completed the company’s Installer Certification course. The program rewards certified installers for every verified and networked installation they complete, offering cash Read More…