$Millions Being Invested in Major Refit at NS Power’s Lingan 4 Generating Unit

Major Refit at NS Power’s Lingan 4 Generating Unit

It was a delicate operation despite the fact it involved a 35 tonne piece of equipment. In less than three hours, a key component of a generator in Lingan, NS was slid out of its housing, hoisted up into the air by a 100 tonne crane and placed onto a flatbed truck bound for Wisconsin.

Removing the 30-foot long rotor — the cylindrical core of the generator — and shipping it to Milwaukee to replace the copper wire wrapped around it is part of a $15 million investment underway at Lingan 4 generating unit. “Everything went very smoothly,” says Senior Plant Manager Tony Stevens. “We planned carefully for this with the safety of our employees in the plant our top priority throughout this event.”

It took 2-1/2 hours to slide the rotor out of the generator, supporting it with straps as it was removed. Once it was on the flatbed, the rotor was carefully wrapped in tarps and plastic to keep it dry and securely strapped into place for the 2,000 kilometre journey. More than 200 employees at the plant will spend the coming eight weeks refurbishing the generating unit. “This is extremely specialized work that involves a great deal of precision,” Stevens says. “Our employees here at Lingan truly do have world class skills and they’re putting them to work right here in Cape Breton.”

Machinist and millwright Barrie Campbell is one of them. The father of three was devastated when the Cape Breton Development Corporation shut down in 2001, leaving him unemployed at the age of 42.

“This work is pretty amazing, it’s a lot different from working in a coal mine,” said Campbell, who at 57 has been working full time at Lingan for 8 years. He will be involved in stripping apart the turbine and replacing and repairing components of the machine that runs at 3,600 revolutions per minute.

Components must be accurate to within hundredths of a millimetre to prevent damage and ensure the unit runs safely, when it is called on to provide electricity to Nova Scotians.

Though the rotor has been shipped away for refurbishment, regular maintenance is done by the employees at Lingan. “To me that says a whole lot about everybody from the engineers to the machinists. Everyone here works together toward the end game of having safe, reliable units,” Campbell says.

Indeed, five of Nova Scotia Power’s generating units made top ranking in a national assessment of their performance in 2014 by the Canadian Electrical Association, with Lingan 3 placing first in Canada for being available when it’s needed. That happened 99.91% of the time.

Though a record 26.6% of electricity was generated from renewable sources in Nova Scotia in 2015, thermal plants such as Lingan 4 provide a reliable source of energy and continue to be a vital part of providing electricity to Nova Scotia families and businesses.

Photo courtesy of NS Power.

Related Articles


Latest Articles

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…

  • Goal Zero YETI 3000X Power Stations Recalled due to Fire and Burn Hazards

    Goal Zero YETI 3000X Power Stations Recalled due to Fire and Burn Hazards

    September 16, 2026 This recall involves Goal Zero YETI 3000X power stations. The silver and black portable power stations measure about 62 centimetres (24.4 inches) high, 47 centimetres (18.5 inches) wide, 57 centimetres (22.3 inches) deep and weigh approximately 42 kilograms (92 pounds). The power stations have yellow handles and a digital display at the… Read More…


Changing Scene

  • Innovair Solutions Acquires TRM Heating Cables

    Innovair Solutions Acquires TRM Heating Cables

    September 18, 2026 Innovair Solutions has announced the acquisition of TRM Heating Cables, a Toronto-based Canadian company specializing in heating cables for commercial and industrial applications. Founded in 2001, TRM has built strong technical expertise in the sale and installation of specialized products, including self-regulating cables, mineral-insulated cables and electric floor heating systems. The company… Read More…

  • Electrical Safety Authority Honours Leaders Helping Build a Safer, More Electrified Future

    Electrical Safety Authority Honours Leaders Helping Build a Safer, More Electrified Future

    September 17, 2026 From preparing the next generation of skilled workers to supporting one of the world’s largest sporting events, this year’s recipients demonstrate how electrical safety supports Ontario’s future As Ontario electrifies homes, transportation and industry, the Electrical Safety Authority (ESA) has recognized the organizations and individuals helping ensure safety keeps pace with that… Read More…

  • NERVA Energy to Support Deep Energy Retrofits Across Selected Morguard Properties

    NERVA Energy to Support Deep Energy Retrofits Across Selected Morguard Properties

    September 17, 2026 The Canada Infrastructure Bank (CIB) has reached financial close on a $100 million loan with Morguard Corporation to enable energy‑efficient retrofits across a portfolio of approximately 30 properties in Canada. Morguard is a fully integrated real estate firm with more than $24.2 billion in assets under management across North America. Morguard will collaborate… Read More…

  • Government of Canada Welcomes Major New Investment in Sovereign AI Infrastructure in Saskatchewan

    Government of Canada Welcomes Major New Investment in Sovereign AI Infrastructure in Saskatchewan

    September 16, 2026 New Canadian-led infrastructure project will help build secure and reliable computing capacity responsibly On September 14, 2026, the Government of Canada welcomed Bell Canada’s planned investment to expand its Bell AI Fabric capacity in Saskatchewan, an important step toward building the sovereign computing capacity Canada needs to compete and succeed in the… Read More…