Ontario Introduces Prompt Payment Legislation

Ontario Introduces Prompt Payment Legislation

June 9, 2017

Ontario has introducing legislation that would, if passed, introduce a prompt payment system, modernize construction lien and holdback rules, and create a new process to speed up dispute resolution.

If passed, the proposed legislative and regulatory changes under the Construction Lien Act would come into effect in 2018. These changes come as the province proceeds through what it claims is its largest ever infrastructure investment in hospitals, schools, public transit, roads and bridges — more than $190 billion over 13 years, starting in 2014-15. The changes would bring Ontario’s construction laws up to date to reflect current construction industry practices and support the thousands of workers and businesses in this sector.

The Construction Lien Act regulates the way payments are made in the construction industry, and provides reasonable certainty that those who have contributed services or materials to the improvement of real property will be paid for the contribution they made. Under the proposed legislation, the act would be amended to establish a prompt payment system with clear payment timelines for all parties involved in a construction project. Disputes that slow down payment could be addressed through a new adjudicative process outside of court.

Specific features of the changes appear below.

Creating a prompt payment system

Under the proposed changes, the owner and general contractor on a project would be able to agree to a deadline to submit an invoice. If they do not agree, they would be required to submit invoices on a monthly basis. Once they receive an invoice, owners would be required to pay general contractors within 28 days. After they receive payment, general contractors would have to pay subcontractors within seven days. Subcontractors would be required to pay other subcontractors within seven days of receiving payment, and so on.

Parties would be free to agree to a timeline for the submission of invoices, before triggering the prompt payment timelines. Where there is a dispute about the amount owed or the quality of the work, owners would be permitted to deliver a notice of non-payment within 14 days of receiving the invoice.

Successive payers would be permitted to deliver a notice of non-payment within seven days. Any undisputed amounts must be paid.

Contractors and subcontractors would receive mandatory interest on late payments. They would also be able to suspend work on a project if the matter is heard by an adjudicator and the payer does not comply with the decision.

Updating construction lien and holdback rules

Among the proposed changes to modernize the construction lien and holdback rules are the following: • extending timelines for contractors and subcontractors to file liens and start court actions from 90 days to 150 days to allow for more time to resolve disputes outside of court

  • requiring holdbacks to be paid once the timeline to file liens has passed. This would give contractors and subcontractors greater certainty about when the holdback will be paid, allowing them to plan and accept contracts for new work
  • requiring contractors and subcontractors to follow specific bookkeeping requirements to protect subcontractors in the event of bankruptcy
  • requiring surety bonding on public sector projects above a certain amount to protect subcontractors and workers if the general contractor files for bankruptcy
  • providing for the referral of construction lien claims under $25,000 to the small claims court

Speeding up dispute resolution

The proposed changes include a new interim adjudication system to prevent payment disputes from delaying work on construction projects, speed up the payment process and reduce time and money spent on litigation.

Adjudication would

  • provide an interim binding decision in approximately six weeks. Adjudication would
  • give parties an alternative to court or provide an interim, binding solution while matters are being heard in court

Adjudication can be used to resolve payment disputes that could result in project delay, including disputes about the valuation of work, payments and set-offs against amounts due under a contract. The adjudications would be informal and inquisitorial.

Parties would be free to establish a process by contract or use the default process, which would be available in regulations. If, after adjudication, the party owing money refuses to comply with the decision, the party eligible for an award would be entitled to suspend further work under the contract.

Adjudicator’s decisions could not be appealed, but the decision could be challenged on the grounds of adjudicator bias or a decision on a matter other than the matter referred. If the parties are satisfied with the adjudicator’s decision, they may agree to treat the decision as final. Whether or not the person owing money complies with the adjudication, the parties may continue to pursue ordinary legal remedies to address the dispute.

Time limits for preserving a lien would be extended to encourage parties to adjudicate first. The adjudicators would be experts who have had extensive experience in the construction industry and who have experience or training in dispute resolution.

Federal prompt payment legislation also in the works

Canada’s Senate recently passed Bill S-224, the Canada Prompt Payment Act, regulating payments on federal construction contracts. The bill now goes to the House of Commons.

Find out more: http://www.electricalindustry.ca/changing-scenes/3090-senate-approves-prompt-payment-act.

Related Articles


Latest Articles

  • Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    There are many different types of wire connectors, and sometimes it can be hard for electricians to determine which one is best to use. Read More…

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…


Changing Scene

  • Government of Canada Introduces Legislation to Transform how Canada Builds

    Government of Canada Introduces Legislation to Transform how Canada Builds

    October 2, 2026 The world is changing rapidly. In response, Canada is focused on what we can control: building a stronger, more independent, and more sustainable economy. We are leveraging our strengths and moving with speed to open new markets, strengthen supply chains, accelerate projects, and unlock our natural resources. As we build, we are… Read More…

  • Ontario Awards Construction Contract for New Little Current Swing Bridge

    Ontario Awards Construction Contract for New Little Current Swing Bridge

    October 2, 2026 The Ontario government has named a construction manager for the Little Current Swing Bridge replacement project. The new bridge will replace the existing bridge on Highway 6 connecting Manitoulin Island to the mainland, providing reliable, year-round access to the provincial highway network and making it easier for workers and families to connect… Read More…

  • Construction Starting on new Pitt Meadows Secondary School in BC

    Construction Starting on new Pitt Meadows Secondary School in BC

    October 2, 2026 Construction is beginning on the new Pitt Meadows Secondary school, which will provide students with a safer and more modern environment to learn. “Pitt Meadows is a vibrant community with a bright future and I’m proud that the local high school will soon better reflect the community it serves,” said Lisa Beare,… Read More…

  • Major Construction Underway at Woodbine GO Station

    Major Construction Underway at Woodbine GO Station

    October 2, 2026 Major construction is underway at Woodbine GO Station, marking another significant milestone in the Ontario government’s plan to provide two-way, all-day service across core segments of the GO Transit network. Crews are now building station platforms that will connect thousands of daily riders to the Kitchener GO Line, Union-Pearson (UP) Express and… Read More…