Carleton University expects to fire up a new co-generation plant at its Ottawa-based campus next spring as the post-secondary institution implements its sophomore energy master plan.

The decision to install a co-generation plant stemmed from an evaluation of existing equipment for its ability to satisfy the anticipated heating and cooling needs of the projected campus build-out, says Darryl Boyce, assistant vice-president of facilities management and planning. Evaluation found that the steam-heating system was not up to the task. Its boilers were old enough to have gone through the public school system and graduated from university at least twice.

“We needed a reliable source of energy to provide the heat for the campus,” says Boyce. “And, at the same time, we realized we would benefit from lower cost electricity from the same system if we put in a co-generation plant.”

Only 60% of the electricity consumed by the campus is expected to come from the grid once the installation is operational. The remainder will be generated on site. The installation, a 4.6-megawatt turbine powered by natural gas, will be accompanied by a heat recovery boiler, which will take over steam production, boosting its efficiency by a projected 7-9%.

All told, Carleton University expects to generate energy savings of 17% through the implementation of its updated energy master plan, which covers the years 2018 through 2021. The plan will see seven buildings undergo energy retrofits including equipment optimization and lighting upgrades. The post-secondary school is striving to further the results it achieved between 2014 and 2017 as it eyes an overall target of trimming energy use by 2% per year on its growing campus.

Achievements to date

Working with Honeywell, its energy services partner, Carleton University was able to shed 2,693,988 kilowatt hours from its yearly electricity bill through the implementation of its first energy master plan, as well as 25,247 cubic metres from its yearly water bill and 19,076 cubic metres from its yearly natural gas bill. This worked out to an average energy and water savings of 16% across five buildings.

Honeywell helped the post-secondary institution zero in on good candidates for retrofits based on facility conditions captured in an audit. Once Carleton University shortlisted the buildings with the most room to improve operationally, the energy services partner itemized potential projects and expected outcomes for each.

Sub-meters were installed in all of the buildings that underwent retrofits to monitor process loads, such as those generated by the operation of a printing centre, as Carleton University confirmed that the projects achieved the savings promised by its energy services partner.

Related Articles


Latest Articles

  • Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    September 3, 2026 By Blake Marchand In this Q&A with Stephanie Medeiros, the Head of Mobility at Schneider Electric Canada provides insight into her perspective on EV charging infrastructure in Canada, factors that will contribute to growing EV adoption, grid modernization for commercial fleets, the role of Vehicle-to-Grid and other innovative approaches to electrification. The focus of… Read More…

  • LEDVANCE: Understanding Light Beam Angles

    LEDVANCE: Understanding Light Beam Angles

    September 3, 2026 Light Beam Angles: How It Affects Different Types of Lighting, Where It Is Applied & What to Consider When Choosing the Right One Beam angle is important in lighting design. It determines how light spreads within a space and influences both functionality and atmosphere. By understanding beam angles, you can achieve both… Read More…

  • ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    September 2, 2026 By ITC Electrical Components When selecting industrial electrical components, certification is more than a logo on a datasheet. A certification mark indicates that a product or component has been independently evaluated against specified requirements for its intended market. In North America, selecting products with the appropriate certification can affect regulatory acceptance, equipment… Read More…

  • Project Spotlight: Leigh Square Fountain

    Project Spotlight: Leigh Square Fountain

    September 2, 2026 In spring 2025, the City of Port Coquitlam unveiled a transformed Leigh Square, reimagined as a vibrant, accessible, and welcoming gathering place in the heart of downtown. At the heart of the renewed plaza, a Bellagio-style programmable dancing fountain is integrated directly into the paving—three interlocking rings where jets rise, fall, and… Read More…


Changing Scene

  • Leviton Canada Appoints Salex as Network Solutions Sales Agency for Ontario

    Leviton Canada Appoints Salex as Network Solutions Sales Agency for Ontario

    September 9, 2026 Leviton Canada is pleased to announce the appointment of Salex Inc. as their authorized sales agent for the Network Solutions (NS) product portfolio across the Ontario market, effective immediately. This appointment reflects their commitment to strengthening customer engagement, expanding market coverage, and providing enhanced local support throughout the province. Salex brings a… Read More…

  • Ontario Electrical League Brings Free Electrical Industry Roadshow to Barrie September 22

    Ontario Electrical League Brings Free Electrical Industry Roadshow to Barrie September 22

    September 9, 2026 The Ontario Electrical League is bringing its Roadshow to Barrie on Tuesday, September 22, 2026, and the invitation is simple: if you are part of Ontario’s electrical industry, or interested in becoming part of it, you are welcome. The free event will bring together independent electrical companies, Licensed Electrical Contractors, business owners,… Read More…

  • 2026 Ontario Apprenticeship Awards Call for Nominations

    2026 Ontario Apprenticeship Awards Call for Nominations

    September 3, 2026 Skilled Trades Ontario is proud to open nominations for the 2026 Ontario Apprenticeship Awards, recognizing outstanding apprentices, journeypersons, organizations and skilled trades leaders who are helping strengthen Ontario’s apprenticeship system. Award recipients will be announced at the Ontario Apprenticeship Summit on November 4, 2026, at the Toronto Congress Centre. Nominations must be submitted… Read More…

  • Bartle & Gibson Announces New Partnership with Hubbell Canada

    Bartle & Gibson Announces New Partnership with Hubbell Canada

    September 3, 2026 Bartle & Gibson Co. Ltd., an Alberta-based premier plumbing, heating and electrical distributor and Hubbell Canada have announced a new regional partnership enabling increased access to Hubbell Canada’s end-to-end electrical product portfolio across Western Canada. “With our strong presence in the west through 31 branches and counting located in Alberta, Saskatchewan, British… Read More…