Guide to the Canadian Electrical Code, Part I — Instalment 10

William (Bill) Burr

July 12, 2020

By William (Bill) Burr

The code is a comprehensive document. Sometimes, it can seem quite daunting to quickly find the information you need. In this current series of articles, I will provide a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating while reading the code. Here in this issue: Section 18 Hazardous locations, Part B.

Section 18 covers installation of electrical equipment in hazardous locations as defined in Section 0, such as areas in which there is a potential for the ignition of explosive gases or combustible dusts, fibres or flyings due to the design, installation or use of electrical equipment. Since the information in this instalment is extensive, it is presented in two parts. This is Part B.

Explosive gas atmospheres

Rules 18-090 to 18-110 apply to the installation of electrical equipment in all locations where explosive gas may be present.

Installations in Zone 0 locations

Rule 18-090 outlines that Zone O is the hazardous location where explosive gas atmospheres are present continuously or for long periods and is the most restrictive. No electrical equipment or wiring may be installed in a Zone 0 hazardous location unless it meets the requirements of subrule 18-090 (2). Also note the marking requirements for Zone 0.

Rule 18-092 specifies that seals are required where conduit leaves a Zone 0 location, and at the first point of termination of cables after entry to the Zone 0 location. Note that unbroken rigid conduit passing through a Zone 0 need not be sealed if the termination points are outside Zone 0. In addition, seals are not required to be explosion-proof or flame-proof but must be identified for minimizing the passage of fluids or dusts and be accessible.

Installations in Zone 1 locations

Rule 18-100 outlines that electrical equipment suitable for Class I Division 1 with protection level Ga or Gb and protection levels as outlined in 18-100(c) may be installed in a Zone 1 location.

Rule 18-102 requires that rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands be used for wiring in Zone 1 locations. In addition, threads and joints need to comply with rule 18-102 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-104 provides the rules for sealing conduits and cables entering enclosures in and leaving Zone 1 locations.

Rule 18-106 provides requirements for the installation of motors in Zone 1 locations. Additional guidance is given in Appendix B.

Rule 18-108 provides the rules for installation of luminaires in Zone 1.

Rule 18-110 allows that flexible cords are permitted in Zone 1 where flexibility is required but must be installed in accordance with Rules 18-110 (1) and (2).

Installations in Zone 2 locations

Rule 18-150 provides the rules for the installation of equipment in Zone 2. Note that equipment suitable for Class I Division 2 and Zone 0 and Zone 1 are permitted to be installed in Zone 2. Also note that transformers, capacitors, solenoids, and other non-arcing, non-sparking or non-heat-producing devices are permitted in Zone 2 locations.

Rule 18-152 provides rules for wiring methods in Zone 2.

Rule 18-154 provides rules for sealing conduit, cable, and equipment in Zone 2.

Rule 18-156 provides rules on installation of luminaires in Zone 2.

Rule 18-158 allows that flexible cords are permitted in Zone 2 where flexibility is required but must be installed in accordance with Rule 18-158 (1).

Explosive dust atmospheres

Rules 18-190 to 18-196 apply to the installation of electrical equipment in all locations where combustible and explosive metal dust may be present.

Installations in Zone 20 locations

Rule 18-190 outlines that like Zone O, Zone 20 is the most restrictive hazardous location where explosive dust atmospheres are present in the form of a cloud of dust in air continuously or for long periods. No electrical equipment or wiring may be installed in a Zone 20 hazardous location unless it meets the requirements of Subrule 18-190 and Table 18

Rule 18-192 provides requirements for wiring methods in Zone 20.

Rule 18-194 provides requirements for seals for a Zone 20 location.

Rule 18-196 allows that flexible cords are permitted in Zone 20 where flexible connections are required and must be extra-hard-usage cord with cable glands.

Installations in Zone 21 locations

Rule 18-200 provides rules for installation of equipment in Zone 21. Equipment suitable for Class II Division 1 is permissible as well as equipment with the noted types of protection in Table 18.

Rule 18-202 requires that rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands must be used for wiring in Zone 21. In addition, threads and joints need to comply with Rule 18-202 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-204 provides rules for sealing raceway equipment in Zone 21.

Installations in Zone 22 locations

Rule 18-250 provides rules for installation of equipment in Zone 22. Equipment suitable for Class II Division 2 is permissible as well as equipment with the noted types of protection in Subrules (b) and (c). This rule also provides rules for installation of cranes, hoists and other material handling equipment in Zone 22 locations.

Rule 18-252 provides rules for wiring methods in Zone 22.

Rule 18-254 provides the same sealing requirements as Zone 21.

In the next instalment we will discuss Section 20 — Flammable liquid and gasoline dispensing, service stations, garages, bulk storage plants, finishing Processes and aircraft hangars.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

Related Articles


Latest Articles


Changing Scene

  • Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    October 19, 2026 “Rexel Canada welcomes Rexel USA agreement to acquire GCG (Genuine Cable Group)—a transformational step that will strengthen our capabilities, expand our reach and support continued growth across Canada, North America and global markets,” Rexel Canada CEO, Jeffrey Moyle announced on LinkedIn. GCG is a leading specialty infrastructure platform providing wire and cable,… Read More…

  • Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    October 19, 2026  The Ontario government has allocated 40,000 new funded seats at publicly assisted colleges and universities to connect more students to good-paying, in-demand careers. This allocation, which is part of a broader $1.7 billion investment to support a total of 70,000 new seats, supports the province’s plan to protect Ontario and build a… Read More…

  • QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    October 19, 2026 Construction of the new acute care tower at the QEII Halifax Infirmary has reached another milestone, with the Level 8 podium structure now in place. The podium is the lower, wider portion of the building that forms the base of the 14-storey acute care tower. It will house a range of hospital… Read More…

  • Ontario Starts Major Construction on Grimsby GO Station

    Ontario Starts Major Construction on Grimsby GO Station

    October 19, 2026 The Ontario government has awarded a contract for major construction on Grimsby GO Station, marking another milestone in its plan to protect Ontario by building the transportation infrastructure needed to reduce gridlock, shorten travel times and support economic growth across the province. Expected to be completed in the second half of 2027,… Read More…