OPG Decommissioning Nanticoke in Preparation for Solar Project

OPG Decommissioning Nanticoke in Preparation for Solar Project

February 2, 2017

Ontario Power Generation (OPG) has begun decommissioning the Nanticoke Generating Station site in advance of constructing a 44 MW solar facility.

Decommissioning the existing site, an undertaking by OPG and its partners Sun Edison Canadian Construction LP and Six Nations Development Corporation, involves removing numerous buildings, including the main powerhouse.

OPG estimates it will take about a year to remove and salvage equipment and materials from the powerhouse, where possible. Removal of the main buildings will not likely occur until 2018. However, smaller buildings and structures will be removed sometime this year.

The Nanticoke Solar Project is expected to begin generating power in in 2018-2019, and operate for 20 years. It’s possible the project could continue to operate for an additional 10 or more years.

Project components include installation of

  • arrays of solar photovoltaic (PV) panels with the cumulative capacity to generate up to 50 MW power, mounted to racking and anchored to the ground or foundation
  • electrical inverters to convert DC electricity generated by the solar panels to AC
  • intermediate step-up transformers, which will be connected to a main transformer prior to interconnection to the provincial grid
  • electrical cables to connect all the panels and inverters and transformers
  • site drainage and access roads
  • weather stations
  • security fencing
  • temporary construction laydown area and facilities during construction

 

More than 99% of power generated by OPG is free of smog and greenhouse gas emissions.

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…