NL Hydro Says Transmission Line On Schedule Despite Deadly Tower Collapse

NL Hydro

October 19, 2017

Newfoundland and Labrador Hydro says a new transmission line from Bay d’Espoir to the Avalon Peninsula will be completed as expected in December, despite a tower collapse that resulted in the death of two linemen and an extended work stoppage.

just a handful of the 583 steel towers were left to be erected, and half of the wire stringing had been completed.

A new terminal station at Bay d’Espoir is finished and a similar station on the western Avalon Peninsula near Chapel Arm will also be completed this month, according to the company.

“As construction has progressed, we have remained focused and committed to ensuring that the work is carried out in a safe manner,” NL Hydro wrote in a statement to CBC News.

Project within budget

The new 230-kilovolt, 188-kilometre line will bring power to the Avalon Peninsula from the 600-megawatt hydro generating station in Bay d’Espoir.

The line was estimated to cost just under $300 million, and Hydro says the project “remains within budget.” 

Work was stopped on the project after a tower collapsed on June 19 near Come by Chance, killing Jared Moffat, 34, of Prince Albert, Sask. and Tim McLean, 31, of Nipigon, Ont.

An investigation by the contractor, Alberta-based Forbes Bros. Ltd., determined that a “deviation from standard process in the change out of a guy wire” was the reason for the collapse.

A stop-work order halted the erection of new towers for two months as a safety audit and investigation were conducted.

More than 300 towers have been installed since work resumed in August, according to figures provided by NL Hydro.

The installation of the final tower in the coming days will mark another milestone for the province’s electrical grid.

Earlier in October, crews installed the last of more than 3,200 steel transmission towers on the $3.4-billion Labrador-Island Link from Muskrat Falls in Labrador to Soldiers Pond on the Avalon Peninsula.

http://www.cbc.ca/news/canada/newfoundland-labrador/nl-hydro-transmission-line-on-schedule-after-deadly-tower-collapse-1.4358021

Related Articles


Latest Articles


Changing Scene

  • ABB Acquires Bel Products Inc. to Expand Enclosures Portfolio in North America

    ABB Acquires Bel Products Inc. to Expand Enclosures Portfolio in North America

    June 3, 2025 ABB Electrification Canada Inc. announced it has completed its acquisition of Bel Products Inc., a Canadian manufacturer of commercial, industrial and custom-made enclosures. This acquisition enhances ABB’s market presence in Canada and the U.S., expanding its product portfolio and enabling the company to leverage its manufacturing, warehousing and supply chain capabilities to better meet growing customer demand. The financial terms of the transaction are undisclosed. The enclosures market is experiencing strong growth, fueled… Read More…

  • WAGO Now Available at Vanco Electrical Solutions

    WAGO Now Available at Vanco Electrical Solutions

    June 2 2025 Vanco Electrical Solutions are excited to announce that Vanco Electrical Solutions has partnered with WAGO, making their full line of innovative spring‑pressure connection and automation products available online at vancoelectrical.com. From their groundbreaking Push‑in CAGE CLAMP® technology to flexible I/O systems, WAGO has built a reputation for reliability and ease of use across… Read More…

  • Sonepar Announces the Appointment of Rob Thibeault to President of Robertson Electric

    Sonepar Announces the Appointment of Rob Thibeault to President of Robertson Electric

    June 2, 2025 Sonepar is pleased to announce the promotion of Rob Thibeault to President Robertson Electric effective June 2, 2025. Rob joined Robertson in 2017, bringing with him extensive experience in retail and marketing. Rob’s skill and dedication quickly saw him taking on additional responsibilities in operations, pricing, and analytics. Demonstrating a keen understanding… Read More…

  • Hammond Power Solutions Appoints Phill Picassinos as New Regional Sales Manager for Eastern GTA

    Hammond Power Solutions Appoints Phill Picassinos as New Regional Sales Manager for Eastern GTA

    June 2, 2025 Hammond Power Solutions is pleased to announce the appointment of Phill Picassinos as the Regional Sales Manager for Eastern GTA, Ontario. Phill will lead HPS’ sales efforts in the Eastern GTA, focusing on strengthening customer relationships and implementing regional strategies that align with national sales objectives. “Phill brings a wealth of experience… Read More…