NL Hydro Says Transmission Line On Schedule Despite Deadly Tower Collapse

NL Hydro

October 19, 2017

Newfoundland and Labrador Hydro says a new transmission line from Bay d’Espoir to the Avalon Peninsula will be completed as expected in December, despite a tower collapse that resulted in the death of two linemen and an extended work stoppage.

just a handful of the 583 steel towers were left to be erected, and half of the wire stringing had been completed.

A new terminal station at Bay d’Espoir is finished and a similar station on the western Avalon Peninsula near Chapel Arm will also be completed this month, according to the company.

“As construction has progressed, we have remained focused and committed to ensuring that the work is carried out in a safe manner,” NL Hydro wrote in a statement to CBC News.

Project within budget

The new 230-kilovolt, 188-kilometre line will bring power to the Avalon Peninsula from the 600-megawatt hydro generating station in Bay d’Espoir.

The line was estimated to cost just under $300 million, and Hydro says the project “remains within budget.” 

Work was stopped on the project after a tower collapsed on June 19 near Come by Chance, killing Jared Moffat, 34, of Prince Albert, Sask. and Tim McLean, 31, of Nipigon, Ont.

An investigation by the contractor, Alberta-based Forbes Bros. Ltd., determined that a “deviation from standard process in the change out of a guy wire” was the reason for the collapse.

A stop-work order halted the erection of new towers for two months as a safety audit and investigation were conducted.

More than 300 towers have been installed since work resumed in August, according to figures provided by NL Hydro.

The installation of the final tower in the coming days will mark another milestone for the province’s electrical grid.

Earlier in October, crews installed the last of more than 3,200 steel transmission towers on the $3.4-billion Labrador-Island Link from Muskrat Falls in Labrador to Soldiers Pond on the Avalon Peninsula.

http://www.cbc.ca/news/canada/newfoundland-labrador/nl-hydro-transmission-line-on-schedule-after-deadly-tower-collapse-1.4358021

Related Articles


Latest Articles

  • Littelfuse: Solid-State Industrial Relays Quality Test Report

    Littelfuse: Solid-State Industrial Relays Quality Test Report

    April 21, 2025 Littelfuse Provides Insights Into Their Solid-State Industrial Relays Introduction Solid-State Relays (SSRs) are a critical component in modern electrical & electronic systems, providing reliable switching capabilities for various applications from industrial automation to consumer electronics. When it comes to choosing the right solid-state relay for your application, it’s important to know the… Read More…

  • PataBid vs. Accubid Classic: How Electrical Estimating Software is Evolving

    PataBid vs. Accubid Classic: How Electrical Estimating Software is Evolving

    April 21, 2025 By Melvin Newman, Patabid CEO The landscape of construction technology — especially in electrical estimating software—is evolving at a rapid pace. With the rise of cloud-based platforms, AI-driven automation, and advanced data integration, contractors now have more options than ever when choosing the right digital estimating tool.    With the rise of… Read More…

  • ESA has Identified Increasing Safety Concern Surrounding Meter Base Installations

    ESA has Identified Increasing Safety Concern Surrounding Meter Base Installations

    April 18, 2025 ESA and EFC are raising awareness on an increasing safety concern the ESA has identified surrounding meter base installations. ESA identified an increase of installed meter bases where the neutral block is isolated from the enclosure. According to OESC Rule 10-210 a bonding conductor must be installed between the meter base and… Read More…

  • Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    April 18, 2025 Overall, investment in building construction rose 1.8% (+$393.7 million) to $22.1 billion in January. The residential sector increased 2.3% to $15.4 billion, while the non-residential sector was up 0.8% to $6.7 billion. Year over year, investment in building construction grew 5.7% in January. On a constant dollar basis (2017=100), investment in building construction increased 1.5% from the previous month to $13.2 billion… Read More…


Changing Scene

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…

  • New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    April 18, 2025 The governments of New Brunswick and Ontario have signed a memorandum of understanding on free trade and labour mobility. “Ontario is New Brunswick’s second-biggest trading partner, and we are excited to be building on the positive momentum to reduce internal trade barriers across Canada,” said Premier Susan Holt. “Today’s signing of this… Read More…