Nova Scotia Power Rebuilding Powerline on Long Island

Nova Scotia Power

October 26, 2017

Nova Scotia Power is rebuilding the power line along Over Cove Road on Long Island to maintain service reliability for its customers in the Freeport area. This work is necessary due to the condition and age of the existing power line and poles.

“Each year we assess and prioritize areas of our system that are aging and in need of replacement to prevent future unplanned outages,” said project engineer James Young. “The line along Over Cove Road has reached the end of its expected service life, and with no alternative power source, we need to move ahead with replacing the line, poles and other components to ensure ongoing service reliability.”

Crews began work on the line, including setting new poles, this week. Approximately 70 structures along a 3.5 kilometre stretch of power line will be rebuilt as part of this project. Traffic on Over Cove Road may be reduced to one lane for two to three weeks to ensure the safety of workers and members of the public. Traffic control personnel will be onsite to assist safe travel through the area while work is underway.

Most customers on the road can expect one 45 minute power outage as they are transferred to the new conductor. Customers will receive advance notification of the outage time line to make any necessary preparations.

This project represents a $400,000 investment in service reliability for over 60 Freeport-area customers.

Related Articles


Latest Articles


Changing Scene

  • IDEAL Electrical Partners with Habitat for Humanity Greater Toronto Area to Support Affordable Housing Initiatives

    IDEAL Electrical Partners with Habitat for Humanity Greater Toronto Area to Support Affordable Housing Initiatives

    August 17, 2026 Earlier this month, approximately 30 IDEAL Electrical employees and skilled electricians volunteered alongside Habitat for Humanity Greater Toronto Area (GTA) to help construct Countryside, an affordable 15-unit townhome development in Brampton that will welcome families later this year. Volunteers assisted with electrical wiring and rough-in installation and provide general construction support, helping… Read More…

  • Hubbell Canada Forms Strategic Alliance with Mac’s II Agencies to Strengthen Harsh & Hazardous Market Presence in British Columbia

    Hubbell Canada Forms Strategic Alliance with Mac’s II Agencies to Strengthen Harsh & Hazardous Market Presence in British Columbia

    August 17, 2026 Hubbell Canada is pleased to announce a new strategic partnership with Mac’s II Agencies, effective August 1, 2026, to represent Hubbell Canada’s Harsh & Hazardous portfolio throughout British Columbia. This newly formed alliance further strengthens Hubbell Canada’s commitment to serving customers operating in some of the most demanding industrial environments, while supporting… Read More…

  • AEA Scholarships and Bursaries Apply by August 31st

    AEA Scholarships and Bursaries Apply by August 31st

    August 17, 2026 The Alberta Electrical Alliance is proud to support our industry with over $320,500 of postsecondary scholarships for current members and their children. Your participation in AEA events helps fund AEA scholarships and build our industry’s future. AEA Sponsored Scholarships Open to employees, dependents, and children of parents who are members of the… Read More…

  • Contractors’ Corner at the 2026 NETCO Conference

    Contractors’ Corner at the 2026 NETCO Conference

    August 17, 2026 ECAO and CECA look forward to joining industry leaders at the NETCO – National Electrical Trade Council 2026 Conference for an important conversation on AI and its growing role in electrical contracting. R. Graeme Aitken, Executive Director of ECAO, Terry Milot, President of the Canadian Electrical Contractors Association, and Témoc Vega, PhD,… Read More…