Fort McMurray West 500-kV Transmission Project Energized 3 Months Ahead of Schedule

Fort

Apr 7, 2019
The 500+ km transmission line from Edmonton to Fort McMurray includes two substations and involved 20 months of construction, and 4.5 years from project start to energization.

When the line was commissioned, it was considered the largest engineering, procurement and construction electric transmission project ever awarded in North America. It increases the capacity of the existing system to meet a growing demand for power in this area, and bolsters the overall reliability of the Alberta transmission network.

The line was constructed by Alberta Powerline, a Valard/ATCO partnership. It has already earned several awards. In 2017, the project received the Transmission Deal of the Year Award in 2017. In April 2018, Valard won a Top Employer of Indigenous Apprentices Award, primarily for a training program built specifically for WFMAC.

“I got to take my hat off to the integrated team under Valard, they kept their eye on the prize, some of them of 6-years,” said Valard President, Adam Budzinski, noting that there were some on the project that saw it through from beginning to the end.

The entire project was done in house by Valard, along with their partners in the Valard Group, Phasor Engineering, Domino High Voltage Supply, Northstar Sharp’s, as well as Dashiell Corp.

Budzinski said the dynamic of the project, being completed entirely in-house, was a primary factor in their ability to finish ahead of schedule. There was no conflict throughout the various points of the project’s massive scope. Everyone was pulling in the same direction. Rather than pointing fingers when issues arose, they simply worked together to find the best possible solution, and in a timely manner. Often with projects of this magnitude, relatively minor issues can escalate to point where progress is held up, Budzinski explained, “This execution model kind of avoids that,” he said, “being done under one company.”

And that also factored into Valard being awarded the tender, becuase it was completed under one company they were able to give a detailed cost breakdown, and were able to quantify a lot of their risk, he explained.

Obviously, as it was a major project for Valard there were certainly challenges, although Budzinsky said they were confident they could complete it successfully. They had experience completing all the various aspects of the project from past jobs, just never all in one project as the Fort McMurray West Transmission Project required. The Muskrat Falls Transmission Line project Valard wrapped in 2016 was a comparable experience, although Budzinski said of the Fort McMurray project, “from a full construction perspective it was different than anything we’ve done.”

“It was a world-class project,” he noted, “and it ended up being built by the home team, for a competitve price.”

“We’re proud of the fact it was built by a made in Canada solution and delivered 3-months ahead of schedule. People shouldn’t doubt we have world-class designers and engineers here in Canada.” 

 

Related Articles


Latest Articles


Changing Scene

  • Save the Date: Ontario Apprenticeship Summit 2026 – November 4, 2026

    Save the Date: Ontario Apprenticeship Summit 2026 – November 4, 2026

    July 6, 2026 Skilled Trades Ontario (STO) is pleased to announce that the third annual Ontario Apprenticeship Summit will take place during National Skilled Trades and Technology Week. Industry partners, skilled trades professionals, and apprentices are invited to attend the Toronto Congress Centre on Wednesday, November 4, 2026. The Ontario Apprenticeship Summit 2026 is focused… Read More…

  • Fort McMurray Apprentice Electrician to Represent Canada at Skilled Canada National Competition

    Fort McMurray Apprentice Electrician to Represent Canada at Skilled Canada National Competition

    July 6, 2026 In recognition of World Youth Skills Day, which underscores the vital role of skills development among young people, Skills/Compétences Canada (SCC) is proud to officially announce the 31 talented members of WorldSkills Team Canada 2026.These young competitors will begin their training to prepare for the 48th WorldSkills Competition, in Shanghai, China, which will be held… Read More…

  • Westburne Celebrates 100 Years with Brandon Trade Show

    Westburne Celebrates 100 Years with Brandon Trade Show

    July 6, 2026 Recently, Westburne hosted over 200 guests and over 60 partners and suppliers at their Brandon Trade Show to celebrate 100 years of Westburne. “Westburne’s annual Midwest Tradeshow welcomed more than 220 attendees in Brandon this year, including representatives from over 60 partner businesses and suppliers. Taking place annually for over 15 years,… Read More…

  • B.C. Expands Energy Efficiency Program to Provide No-Cost Retrofits to Homeowners, Tenants

    B.C. Expands Energy Efficiency Program to Provide No-Cost Retrofits to Homeowners, Tenants

    July 3, 2026 Together with BC Hydro, FortisBC and Natural Resources Canada, the Province is supporting families with lower incomes to save money on their utility costs through home-energy improvements.  “We are taking action to help people lower their utility bills by expanding our home energy-efficiency programming for lower-income families,” said Adrian Dix, B.C.’s Minister… Read More…