Fort McMurray West 500-kV Transmission Project Energized 3 Months Ahead of Schedule

Fort

Apr 7, 2019
The 500+ km transmission line from Edmonton to Fort McMurray includes two substations and involved 20 months of construction, and 4.5 years from project start to energization.

When the line was commissioned, it was considered the largest engineering, procurement and construction electric transmission project ever awarded in North America. It increases the capacity of the existing system to meet a growing demand for power in this area, and bolsters the overall reliability of the Alberta transmission network.

The line was constructed by Alberta Powerline, a Valard/ATCO partnership. It has already earned several awards. In 2017, the project received the Transmission Deal of the Year Award in 2017. In April 2018, Valard won a Top Employer of Indigenous Apprentices Award, primarily for a training program built specifically for WFMAC.

“I got to take my hat off to the integrated team under Valard, they kept their eye on the prize, some of them of 6-years,” said Valard President, Adam Budzinski, noting that there were some on the project that saw it through from beginning to the end.

The entire project was done in house by Valard, along with their partners in the Valard Group, Phasor Engineering, Domino High Voltage Supply, Northstar Sharp’s, as well as Dashiell Corp.

Budzinski said the dynamic of the project, being completed entirely in-house, was a primary factor in their ability to finish ahead of schedule. There was no conflict throughout the various points of the project’s massive scope. Everyone was pulling in the same direction. Rather than pointing fingers when issues arose, they simply worked together to find the best possible solution, and in a timely manner. Often with projects of this magnitude, relatively minor issues can escalate to point where progress is held up, Budzinski explained, “This execution model kind of avoids that,” he said, “being done under one company.”

And that also factored into Valard being awarded the tender, becuase it was completed under one company they were able to give a detailed cost breakdown, and were able to quantify a lot of their risk, he explained.

Obviously, as it was a major project for Valard there were certainly challenges, although Budzinsky said they were confident they could complete it successfully. They had experience completing all the various aspects of the project from past jobs, just never all in one project as the Fort McMurray West Transmission Project required. The Muskrat Falls Transmission Line project Valard wrapped in 2016 was a comparable experience, although Budzinski said of the Fort McMurray project, “from a full construction perspective it was different than anything we’ve done.”

“It was a world-class project,” he noted, “and it ended up being built by the home team, for a competitve price.”

“We’re proud of the fact it was built by a made in Canada solution and delivered 3-months ahead of schedule. People shouldn’t doubt we have world-class designers and engineers here in Canada.” 

 

Related Articles


Latest Articles

  • Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    There are many different types of wire connectors, and sometimes it can be hard for electricians to determine which one is best to use. Read More…

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…


Changing Scene

  • Government of Canada Introduces Legislation to Transform how Canada Builds

    Government of Canada Introduces Legislation to Transform how Canada Builds

    October 2, 2026 The world is changing rapidly. In response, Canada is focused on what we can control: building a stronger, more independent, and more sustainable economy. We are leveraging our strengths and moving with speed to open new markets, strengthen supply chains, accelerate projects, and unlock our natural resources. As we build, we are… Read More…

  • Ontario Awards Construction Contract for New Little Current Swing Bridge

    Ontario Awards Construction Contract for New Little Current Swing Bridge

    October 2, 2026 The Ontario government has named a construction manager for the Little Current Swing Bridge replacement project. The new bridge will replace the existing bridge on Highway 6 connecting Manitoulin Island to the mainland, providing reliable, year-round access to the provincial highway network and making it easier for workers and families to connect… Read More…

  • Construction Starting on new Pitt Meadows Secondary School in BC

    Construction Starting on new Pitt Meadows Secondary School in BC

    October 2, 2026 Construction is beginning on the new Pitt Meadows Secondary school, which will provide students with a safer and more modern environment to learn. “Pitt Meadows is a vibrant community with a bright future and I’m proud that the local high school will soon better reflect the community it serves,” said Lisa Beare,… Read More…

  • Major Construction Underway at Woodbine GO Station

    Major Construction Underway at Woodbine GO Station

    October 2, 2026 Major construction is underway at Woodbine GO Station, marking another significant milestone in the Ontario government’s plan to provide two-way, all-day service across core segments of the GO Transit network. Crews are now building station platforms that will connect thousands of daily riders to the Kitchener GO Line, Union-Pearson (UP) Express and… Read More…