Manitoba Hydro Scales back Construction on Keeyask Project

EIN Manitoba Hydro logo 400

March 26, 2020

Manitoba Hydro is scaling back work and suspending travel in and out of the Keeyask Project’s construction site to help protect the safety and health of workers as well as residents of nearby communities amid COVID-19 outbreak.

The temporary reduction of personnel at the site and implementation of the suspension was completed Saturday, March 21.

The decision follows guidance and direction from senior Manitoba Health officials and is expected to last between four and eight weeks. Manitoba Hydro will continue to evaluate the suspension based on the latest information and guidance received from provincial health authorities.

Approximately 600 supervisory, construction, and support staff have volunteered to remain at site, and will focus on achieving the in-service date for the hydroelectric station’s first two generating units.

“These are extraordinary times and we are making this decision in the interest of public health and the best interests of our customers, employees, contractors, and neighbouring communities,” said Jay Grewal, President and Chief Executive Officer of Manitoba Hydro. “These measures are temporary in nature and will be re-assessed based on guidance we receive from Manitoba Health officials in a few weeks.”

For employees and contractors who remain at Keeyask, Manitoba Hydro is continuing to follow the preventative and proactive measures outlined in the Keeyask Pandemic Plan, which is informed by Manitoba Health; Health Canada; and the World Health Organization (WHO). These measures include:

  • The requirement that anyone on-site with symptoms of an illness get checked out by the Nurse Practitioner. The Nurse Practitioner will assess the individual following Manitoba Health issued guidelines and if they are recommended for further assessment off-site, the individual will be immediately isolated in special rooms set aside for that purpose, and transferred off-site as soon as it can be arranged following Manitoba Health protocols.
  • Increased cleaning protocols; reminders around camp, offices, and the work trailers detailing proper recommended personal hygiene practices; implementing social distancing by suspending gym classes and intramural activities, closing the on-site theatre, and providing only take-out meals from the Dining Hall.

The Keeyask Project is a 695-megawatt hydroelectric generating station under construction in northern Manitoba. It is a collaborative effort between Manitoba Hydro and four Manitoba First Nations — Tataskweyak Cree Nation and War Lake First Nation (acting as the Cree Nation Partners), York Factory First Nation, and Fox Lake Cree Nation — working together as the Keeyask Hydropower Limited Partnership (KHLP).

Source

Related Articles


Latest Articles

  • The Role of Lighting in the AI-Powered Home

    The Role of Lighting in the AI-Powered Home

    January 14, 2026 Elizabeth Parks, President and CMO of Parks Associates, joins Derek Richardson, Founder and CEO of Deako, for a wide-ranging conversation on how lighting is becoming a core layer of the intelligent home. The discussion explores how Deako’s plug-and-play lighting approach is removing long-standing barriers to adoption by simplifying installation, reducing costs, and Read More…

  • What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    January 14, 2025 By John Kerr From the ground, many contractors and plant teams are experiencing the same thing: jobs are there, but they are smaller, more price‑sensitive, and slower to release compared to past years. The Canadian Pulse of Lighting confirms that impression and offers some clear signals about how contractors and plant electrical Read More…

  • Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    January 12, 2026 By Bill Burr The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the Read More…

  • Tom Penton & Magic Lite: Forty Years of Leadership in Canadian Lighting

    Tom Penton & Magic Lite: Forty Years of Leadership in Canadian Lighting

    January 12, 2026 By John Kerr Sales has always been at the core of Magic Lite’s story, because it was at the core of who its founder Tom Penton was. He genuinely loved sales, loved being independent, and consistently gravitated to roles where he could take personal responsibility for results and build his own customer Read More…


Changing Scene

  • Hammond Manufacturing Expands to Western Canada

    Hammond Manufacturing Expands to Western Canada

    January 13, 2026 Hammond Manufacturing have announced that they are opening a new distribution facility in the Southeast of Calgary, Alberta. The new facility includes over 50,000 sq ft of warehouse space. “This addition will better serve our customers in Western Canada and stock volume and larger products to ensure our distributors have an improve stock Read More…

  • ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    January 12, 2026 ABB will supply a complete package of power, propulsion and control technology for four new double-ended passenger and car ferries operated by British Columbia Ferry Services (BC Ferries). One of the largest ferry operators in the world, BC Ferries provides year-round vehicle and passenger service on 25 routes to 47 terminals, carrying Read More…

  • Federal Government Invests in Four Ontario Steel Companies

    Federal Government Invests in Four Ontario Steel Companies

    January 12, 2026 Through targeted investments, the Government of Canada is committed to providing support to help businesses in all sectors, including steel and automotive, to respond, adapt and compete amid shifting market conditions. Evan Solomon, Minister of Artificial Intelligence and Digital Innovation and Minister responsible for the Federal Economic Development Agency for Southern Ontario Read More…

  • Craftsman V20 150W Power Inverter Recalled Due to Fire Hazard

    Craftsman V20 150W Power Inverter Recalled Due to Fire Hazard

    January 12, 2026 This recall involves the Craftsman V20 150W Power Inverter (Model number: CMCB1150B). The product has a rectangular prism shape with dimensions of 8.13 x 7.62 x 11.68 cm. It is red and black and weighs 320 grams. It has three charging ports for Type-C, Type-A, and AC connections. It contains an LED Read More…