OPG Celebrates the Early Completion of Darlington Unit 3

July 18, 2023

The second of four OPG refurbished reactors now re-connected to Ontario’s electricity grid

Ontario Power Generation (OPG) has achieved a major milestone by successfully connecting Darlington Nuclear Generating Station’s Unit 3 to Ontario’s electricity grid, 169 days ahead of schedule. This world-class project performance demonstrates OPG’s expertise and commitment to completing the station’s four-unit refurbishment safely, with quality and on budget, by the end of 2026.

Unit 3 is now the second Darlington unit to undergo complete refurbishment and is operating at 100 percent capacity, providing clean, reliable energy for Ontarians during these peak summer months. The early return of Unit 3 will produce an extra 3 terawatt-hours of energy, enough to power 350,000 homes for an entire year. It will also reduce up to 1 megatonne of greenhouse gas emissions, or the equivalent of taking 300,000 cars off the road for an entire year.

Unit 2 was completed in early June 2020. Thanks to the quality of refurbishment work, in the three years since its return to service, Unit 2 has experienced a record 529-day continuous run. This is industry-leading performance for a CANDU reactor post-refurbishment. Overall generation was also 10 plus percent better than target.

Unit 1 refurbishment, expected to be completed mid-2025, is approximately 60 percent complete and is currently in the reassembly phase. Unit 4, the last of Darlington’s four reactors, will come offline shortly to begin its refurbishment.

Once complete, a refurbished Darlington Nuclear Generating Station will provide more than 30 years of carbon-free power. The Refurbishment project, together with the station’s extended operation, will generate approximately $90 billion in economic benefits for Ontario and create an average of 14,200 jobs annually across the province.

Quick Facts

Quotes

“Through this project, OPG is demonstrating that with detailed planning and preparation, large nuclear projects can be completed not only on-time, but ahead of time and with great quality,” said Ken Hartwick, OPG’s President and CEO. “This would not be possible without the performance, expertise, and commitment from our refurbishment project team, project partners, industry experts, energy professionals, and skilled tradespeople.”

Ken Hartwick, OPG’s President and CEO

“The successful refurbishment of Darlington’s Unit 3 ahead of schedule and on-budget will help power the next major international investment in Ontario, the new homes we are building, and industries as they grow and electrify,” said Todd Smith, Minister of Energy. “It’s also proof that this province can deliver the major energy projects we have planned to Power Ontario’s Growth on-time and on-budget, including building a total of four Small Modular Reactors at Darlington, and beginning pre-development work to site Canada’s first large-scale nuclear build in over three decades.”

Todd Smith, Minister of Energy

Source

Related Articles


Latest Articles

  • Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    There are many different types of wire connectors, and sometimes it can be hard for electricians to determine which one is best to use. Read More…

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…


Changing Scene

  • Government of Canada Introduces Legislation to Transform how Canada Builds

    Government of Canada Introduces Legislation to Transform how Canada Builds

    October 2, 2026 The world is changing rapidly. In response, Canada is focused on what we can control: building a stronger, more independent, and more sustainable economy. We are leveraging our strengths and moving with speed to open new markets, strengthen supply chains, accelerate projects, and unlock our natural resources. As we build, we are… Read More…

  • Ontario Awards Construction Contract for New Little Current Swing Bridge

    Ontario Awards Construction Contract for New Little Current Swing Bridge

    October 2, 2026 The Ontario government has named a construction manager for the Little Current Swing Bridge replacement project. The new bridge will replace the existing bridge on Highway 6 connecting Manitoulin Island to the mainland, providing reliable, year-round access to the provincial highway network and making it easier for workers and families to connect… Read More…

  • Construction Starting on new Pitt Meadows Secondary School in BC

    Construction Starting on new Pitt Meadows Secondary School in BC

    October 2, 2026 Construction is beginning on the new Pitt Meadows Secondary school, which will provide students with a safer and more modern environment to learn. “Pitt Meadows is a vibrant community with a bright future and I’m proud that the local high school will soon better reflect the community it serves,” said Lisa Beare,… Read More…

  • Major Construction Underway at Woodbine GO Station

    Major Construction Underway at Woodbine GO Station

    October 2, 2026 Major construction is underway at Woodbine GO Station, marking another significant milestone in the Ontario government’s plan to provide two-way, all-day service across core segments of the GO Transit network. Crews are now building station platforms that will connect thousands of daily riders to the Kitchener GO Line, Union-Pearson (UP) Express and… Read More…