Electrical Contractor Fined $80,000 After Two Workers Suffer Burns

Workers Suffer Burns

An overhead and underground utility contractor has pleaded guilty and has been fined $80,000 after two workers suffered burns while working on electrical equipment that had not been properly shut off. The incident occurred at a Toronto condo building in February 2014. The two workers were from Powerline Plus, which was under contract to Toronto Hydro.

The workers were instructed by their supervisor to enter an electrical vault to begin preparing termination of conductors that had been pulled into the vault.The vault contained various energized electrical equipment, including step-down transformers and switchgears. The handle on one of the switchgears was in an open position with a blue tag attached indicating that there was work being conducted on the unit. Neither worker was aware that the switchgear remained energized, and since both workers believed the panel was not live they did not test to see if it was energized. No rubber gloves were worn and no barriers were used.

As the workers positioned themselves and began work, an arc flash occurred within the switchgear unit. Both workers received second- and first-degree burns; one of them also received third-degree burns.

Powerline Plus pleaded guilty to failing as an employer to ensure that the lockout measures and procedures prescribed by Ontario Regulation 213/91 (the Construction Projects Regulation) were carried out, contrary to the Occupational Health and Safety Act.

 

Related Articles


Latest Articles


Changing Scene

  • Nesco Announces New Sales Agent for Northern Ontario

    Nesco Announces New Sales Agent for Northern Ontario

    January 16, 2025 Nesco is pleased to announce the appointment of Sean Atkinson at Resilient Sales as their sales agent for Northern Ontario, effective January 1st, 2025. “Sean is replacing Steve Wallace, who after decades of providing tireless customer service and sales support is focusing on family and enjoying some well-deserved downtime in retirement,” commented… Read More…

  • ABB and Wieland Electric Partner to Redefine Efficiency in Modular Construction

    ABB and Wieland Electric Partner to Redefine Efficiency in Modular Construction

    January 15, 2025 ABB Electrification’s Smart Buildings Division and Wieland Electric have announced a strategic partnership to revolutionize modular and serial construction with advanced prefabricated electrical installation systems. The collaboration combines Wieland’s innovative connector technology with ABB’s extensive portfolio – including switches, sockets, installation boxes, energy distribution, and smart home solutions – to deliver plug-and-play… Read More…

  • ABB Expands Residential Energy Management Portfolio in North America with Lumin Acquisition

    ABB Expands Residential Energy Management Portfolio in North America with Lumin Acquisition

    January 15, 2025 ABB has announced the acquisition of Lumin, a U.S.-based pioneer and leading provider of responsive energy management systems, to expand its home energy management capabilities in the North American residential sector. The acquisition follows a strategic minority investment by ABB into the company in 2023. Financial terms of the transaction were not… Read More…

  • Mattr Completes Acquisition of AmerCable, Establishing US Wire and Cable Manufacturing Footprint

    Mattr Completes Acquisition of AmerCable, Establishing US Wire and Cable Manufacturing Footprint

    January 10, 2025 Mattr Corp. has announced that it has closed its previously announced acquisition of AmerCable Incorporated [see press release], which now forms part of Mattr’s Connection Technologies reporting segment. Under the terms of the transaction, Mattr has acquired all of the outstanding shares of AmerCable from Nexans USA Inc. for a purchase price… Read More…