PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • Virtual Training for Electricians Available at Many IBEW Canada Training Centres Across the Country

    Virtual Training for Electricians Available at Many IBEW Canada Training Centres Across the Country

    June 23, 2025 Virtual Training for Electricians (VET) is now available at many IBEW Canada Training Centres nationwide — and more are coming online soon! Whether your centre is already equipped or in the process of setting up, this is a game-changing opportunity you won’t want to miss. Need assistance? Contact the NETCO team. What… Read More…

  • Designing for Demand: The Role of Transformers in a Resilient EV Future

    Designing for Demand: The Role of Transformers in a Resilient EV Future

    June 23, 2025 Transformers in the EV Charging Boom: Are We Ready for the Load? As electric vehicles (EVs) continue their rapid rise, one question looms over the energy sector, municipalities, and developers alike: Is our infrastructure truly ready for the surge in demand? From city streets to highway rest stops, new EV chargers are… Read More…

  • The Time is Now: An Industrial Energy Efficiency Action Plan

    The Time is Now: An Industrial Energy Efficiency Action Plan

    June 23, 2025 In a whitepaper released on June third, ABB has set out the scale of the challenge facing the global industrial sector and emphasizes the critical role of industrial energy efficiency in meeting rising energy demand while strengthening energy security & affordability and driving industrial competitiveness. With 45% of the world’s electricity converted… Read More…

  • Multi-Family Construction Intentions Weigh Down Residential Sector

    Multi-Family Construction Intentions Weigh Down Residential Sector

    June 23, 2025 In April, the total value of building permits issued in Canada decreased by $829.6 million (-6.6%) to $11.7 billion. British Columbia (-$1.2 billion) led this decrease in construction intentions, which was mitigated by Ontario (+$299.3 million). On a constant dollar basis (2023=100), the total value of building permits issued in April fell by 6.6% from the previous… Read More…


Changing Scene

  • Stanpro Makes Significant Donation to Help Haven on the Queensway Move to a Larger Facility

    Stanpro Makes Significant Donation to Help Haven on the Queensway Move to a Larger Facility

    June 23, 2025 In an effort to provide essential resources to individuals and families in need in the GTA, EFC members once again stepped up to support Haven on the Queensway, a community resource centre in Etobicoke, ON. Earlier this year, Haven secured a new, larger location nearby its existing facility to meet growing demand… Read More…

  • Metalumen Manufacturing, Inc. Announces NRG INTENSI-T as New Sales Agency in Quebec

    Metalumen Manufacturing, Inc. Announces NRG INTENSI-T as New Sales Agency in Quebec

    June 23, 2025 Metalumen Manufacturing, Inc. is pleased to welcome NRG INTENSI-T as its new sales agency for the Quebec region. This partnership strengthens regional support and reflects a shared commitment to innovation and excellence. Since 1977, Metalumen has been designing, engineering, and manufacturing lighting products that blend functionality with design, offering luminaires tailored to… Read More…

  • IDEAL Electrical™ and BILT® Make it Easier to Learn Conduit Bending

    IDEAL Electrical™ and BILT® Make it Easier to Learn Conduit Bending

    June 23, 2025 Conduit bending – one of the hardest skills for professional electricians to master – is now easier than ever to learn, thanks to a first-of-its kind partnership between BILT, an app that has revolutionized step-by-step interactive instructions for DIYers and IDEAL Electrical, a 108-year old manufacturer of electrical tools and supplies for professional electricians…. Read More…

  • Introducing the New WAGO App: Your Jobsite Sidekick

    Introducing the New WAGO App: Your Jobsite Sidekick

    WAGO at your fingertips — scan the QR to get the app now. Stay connected with WAGO wherever you go. Download the WAGO App to access product details, documentation, configuration tools, as well as local distributors — all from your mobile device. Scan the QR code to get started on the App Store or Google… Read More…