How the Canadian Electrical Code, Part I Is Amended

Code Amended

William Burr

I am often asked how new rules get in the Code and how one could go about amending a code rule. All of these procedures are outlined in Appendix C of the Canadian Electrical Code, Part I. However, being written as a standard it is sometimes a struggle to follow.I trust this article easily explains the process. 

To start this discussion we need to understand the structure of the Technical Committee of the Canadian Electrical Code, Part I (TC), which is responsible for the development of the Code.

The TC has a maximum of 41 members, consisting of

• chair
• vice-chair

• executive committee (EC) elected by the members
• non-voting project manager appointed by the Canadian Standards Association (CSA)
• sub-committee (SC) for each section of the Code
• Regulatory Authority Committee (RAC).

The chair of the TC, with the advice of the EC appoints a chair for each section SC from among the TC members, and the SC chairs appoint the members of their SC. Anyone representing the following major interests can apply to be a member of a sub-committee: 

• inspection authorities
• manufacturers
• employers
• employees
• consultants
• utilities
• testing laboratories
• underwriters
• fire marshals
• primary and secondary industries
• respective code-making panels of the National Electrical Code
• users

The 41 regular members of the TC are drawn from three main interest groups in conjunction with the following balanced matrix.

Technical Committee Composition

Technical Committee

• The regulatory authorities represent the various provincial, territorial and municipal electrical inspection authorities across the country.
• Owner/operator/producers represent electrical manufacturers, electrical installation designers and installers and electrical installation user groups.
• The general interest category is drawn from fire chiefs, electric utilities, other codes and standards committees, fire insurers, labour, issuers of building codes, and educators groups.

All these members are nominated by the organization they represent and are approved for membership by the executive committee. I will discuss the function of the RAC later in this article.

The TC meets once a year.Additional meetings may be called if warranted. However, much of the business of the TC and Section SCs takes place between meetings through correspondence and electronic media.

Anyone can propose a new Code rule or an amendment to the project manager at CSA using the form contained inAppendix C of the Code.
The proposal must be specifically worded and must:

• improve safety
• address new technology
• correlate with product standard requirements
• correlate with other relevant standards, or
• clarify existing wording

Supporting information for the proposal must also be supplied. 

The PM assigns a subject number to the proposal and sends it to the relevant section SC chair and alsosubmits it for public review on the CSA website. The SC chair distributes the proposal to the subcommittee members with the chair’s comments for discussion. The sub-committee deliberates the proposal, along with any public review comments, and may recommend it, amend it, keeping the original intent, or reject the proposal. The SC chair then provides a report with the recommendations of the sub-committee to the TC for letter ballot.

If the letter ballot is affirmed by more than 50% of the total voting membership with no negative votes, it is approved and, except for a recommendation of rejection, will be published in the next version of the Code. In the case of negative votes, the chair of the SC in consideration of the negative votes has a number of courses of action:

• resolve the negative by editorial changes or further explanation
• rule the negative vote non-germane if it is not accompanied by supporting comments, if it doesn’t deal with the intent, the procedure, technical content or conflict with another rule or standard, of the proposal
• the negative vote and supporting reasons are not considered to be relevant to the original proposal
• the negative vote can be ruled non-persuasive if the reasons have previously been discussed by the subcommittee as outlined in the subcommittee report.

If there are any negative votes that cannot be resolved by the SC chair, then the subject is put on the agenda of the next meeting of the TC.

When a letter ballot is on the agenda of a meeting, the subject is introduced by the chair of the SC who explains the deliberations of the SC and the negatives that couldn’t be resolved. An open discussion takes place followed by a vote. If the subject is affirmed by a two-thirds majority, with no Regulatory Negative, then the subject is approved.

Whoa! What’s a Regulatory Negative? Well, I mentioned earlier that I would discuss the Regulatory Authority Committee later in this article.

The RAC comprises the regulatory authority representatives on the TC and is essentially the guardian of the legal framework of the Code. Since the Code is a legally adopted document by provincial, territorial, and municipal governments, the regulatory authorities need to make sure that the wording of any rules are suitable for enforcement.If any RAC member feels that a proposal for amendment to the Code is not enforceable in their jurisdiction, they may vote a Regulatory Negative. This member must declare that their negative vote is a Regulatory Negative as opposed to a negative for any other technical reason.The subject is then referred to the Regulatory Authority Committee, which must develop a revised amendment carrying the same intent, in terms of safety and technical requirements, and submit it to the Section SC for further consideration.It must be noted that this is not a veto, but an alternative wording with the same intent as the original proposal.

Note: information for this article has been sourced from The Canadian Electrical Code, Part I, published by CSA Group.


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Lighting Case Study: Metro Toronto Convention Centre

    Lighting Case Study: Metro Toronto Convention Centre

    September 27, 2024 Goal: Upgrade the outdated 350-450-Watt metal halide lighting technology at the Metro Toronto Convention Centre (MTCC) with high-performing, energy-efficient, long-lasting, and low-maintenance LED fixtures from LEDVANCE Products Installed: 1,431 200-Watt UFO High Bay Fixtures from LEDVANCE, which are ideal replacements for metal halide lighting Benefits: LEDVANCE LEDs slashed the MTCC’s previous lighting… Read More…

  • The Consulting Engineer’s Guide to Advanced Electric Boiler Technology

    The Consulting Engineer’s Guide to Advanced Electric Boiler Technology

    September 27, 2024 An international boiler expert helps industry professionals take advantage of high voltage electrode boilers’ virtually 100% efficient, zero-emission capabilities, providing guidance on selection and installation For consulting engineers tasked with planning, designing, and supervising construction projects for a wide range of industries, advanced electric boilers – particularly high voltage electrode boilers –… Read More…

  • Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    September 23, 2024 By Blake Marchand It goes without saying that the Milwaukee brand is historic. Their longevity is a testament to company culture and innovation. As this year marks Milwaukee’s 100th anniversary, the company held a tree planting ceremony earlier in the year to mark the milestone, planting 100 trees in partnership with Tree… Read More…

  • ECABC Provides Platform Recommendations to BC Political Parties

    ECABC Provides Platform Recommendations to BC Political Parties

    September 23, 2024 The Electrical Contractors Association of British Columbia has provided three platform policy recommendations to each of BC’s major political parties in advance of the October 19, 2024 provincial election: implementing prompt payment legislation, increasing capital and operating funding to support electrical apprentices, and naming a Minister responsible for construction in their Cabinet…. Read More…


Changing Scene

  • NOARK Partners With Innovelec, to Power the Electrical Industry in Western Canada

    NOARK Partners With Innovelec, to Power the Electrical Industry in Western Canada

    September 26, 2024 INNOVELEC, a supplier of products and services for the electrical industry in Western Canada for over 25 years,  and NOARK Electric, global manufacturer of low-voltage electrical components for industrial applications, have partnered to electrify Western Canada. Specializing in motor controls and protection for Original Equipment Manufacturers, System Integrators and Panel Builders, Noark Electric… Read More…

  • Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    September 23, 2024 Efficiency Capital (EC), Canada’s first Energy-as-a-Service (EaaS) company, and Mitsubishi Electric Sales Canada Inc. (MESCA) announced a strategic cross promotional partnership to make low-carbon building solutions more accessible to building owners and operators across Canada. Energy efficiency in buildings, despite being one of the critical pathways to meet Canada’s climate goals, faces… Read More…

  • Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    September 23, 2024 Siemens has announced the intention to carve out its eMobility business. The company bundled its eMobility charging activities in 2018 and subsequently organized it into a separate business unit in 2022.  The carve out of Siemens eMobility, which has a strong technological core and portfolio, will give the business entrepreneurial freedom to… Read More…

  • FLO Confirms FLO Station Eligibility for ZEVIP Funding

    FLO Confirms FLO Station Eligibility for ZEVIP Funding

    September 24, 2024 Canada recently announced trade measures impacting vehicles from China and limiting eligibility under the Natural Resources Canada (NRCan) Zero Emission Vehicle Infrastructure Program (ZEVIP) to electric vehicle (EV) charging products manufactured in countries that have negotiated free trade agreements with Canada. Effective October 1, 2024, this directive is expected to have an impact on… Read More…