PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • ABB Acquires Bel Products Inc. to Expand Enclosures Portfolio in North America

    ABB Acquires Bel Products Inc. to Expand Enclosures Portfolio in North America

    June 3, 2025 ABB Electrification Canada Inc. announced it has completed its acquisition of Bel Products Inc., a Canadian manufacturer of commercial, industrial and custom-made enclosures. This acquisition enhances ABB’s market presence in Canada and the U.S., expanding its product portfolio and enabling the company to leverage its manufacturing, warehousing and supply chain capabilities to better meet growing customer demand. The financial terms of the transaction are undisclosed. The enclosures market is experiencing strong growth, fueled… Read More…

  • WAGO Now Available at Vanco Electrical Solutions

    WAGO Now Available at Vanco Electrical Solutions

    June 2 2025 Vanco Electrical Solutions are excited to announce that Vanco Electrical Solutions has partnered with WAGO, making their full line of innovative spring‑pressure connection and automation products available online at vancoelectrical.com. From their groundbreaking Push‑in CAGE CLAMP® technology to flexible I/O systems, WAGO has built a reputation for reliability and ease of use across… Read More…

  • Sonepar Announces the Appointment of Rob Thibeault to President of Robertson Electric

    Sonepar Announces the Appointment of Rob Thibeault to President of Robertson Electric

    June 2, 2025 Sonepar is pleased to announce the promotion of Rob Thibeault to President Robertson Electric effective June 2, 2025. Rob joined Robertson in 2017, bringing with him extensive experience in retail and marketing. Rob’s skill and dedication quickly saw him taking on additional responsibilities in operations, pricing, and analytics. Demonstrating a keen understanding… Read More…

  • Hammond Power Solutions Appoints Phill Picassinos as New Regional Sales Manager for Eastern GTA

    Hammond Power Solutions Appoints Phill Picassinos as New Regional Sales Manager for Eastern GTA

    June 2, 2025 Hammond Power Solutions is pleased to announce the appointment of Phill Picassinos as the Regional Sales Manager for Eastern GTA, Ontario. Phill will lead HPS’ sales efforts in the Eastern GTA, focusing on strengthening customer relationships and implementing regional strategies that align with national sales objectives. “Phill brings a wealth of experience… Read More…