Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • EFC Letter on China Tariffs

    EFC Letter on China Tariffs

    September 15, 2024 The Canadian federal government intends to apply a 25 per cent surtax on imports of steel and aluminum products from China, effective October 15, 2024. See announcement here. The initial list of impacted goods was released for public comment and submissions are due September 20, 2024.  The list of products is available… Read More…

  • Changing How we Build Homes: A Year of the Housing Accelerator Fund

    Changing How we Build Homes: A Year of the Housing Accelerator Fund

    September 15, 2024 The Government of Canada is highlighting key results that have come from the first Housing Accelerator Fund since the start of the Program. This week marks the closure of the application portal for the second round of the HAF. HAF was created to incentivize local governments to implement structural and lasting reforms that will increase… Read More…

  • Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    September 15, 2024 Month over month, the total value of building permits in Canada surged 22.1% to $12.4 billion in July, rebounding from two consecutive monthly declines. Both the residential and non-residential sectors expanded in July. On a constant dollar basis (2017=100), the total value of building permits in July was up 22.9% compared with the previous month,… Read More…

  • B.C. Building Code Updated to Support More Homes

    B.C. Building Code Updated to Support More Homes

    September 15, 2024 Changes to the BC Building Code (BCBC) will allow single egress stair (SES) designs in low- and mid-rise buildings to support more multi-bedroom apartment options. The Province has updated the BCBC to remove the code requirement for a second egress, or exit, stairwell per floor in buildings up to six storeys. This change will… Read More…


Changing Scene

  • Leviton Canada Achieves Another Year of Carbon Neutrality

    Leviton Canada Achieves Another Year of Carbon Neutrality

    September 15, 2024 Leviton Canada proudly reaffirms its commitment to sustainability by achieving carbon neutrality once again in 2023. The company has significantly reduced their environmental footprint by 32% compared to 2022, with a substantial impact on transportation. Despite having energy-efficient lighting and relying on hydropower—a clean and renewable energy source—for their facility, transportation (both… Read More…

  • Grand Opening: Legrand BCS Office in Markham

    Grand Opening: Legrand BCS Office in Markham

    September 15, 2024 Legrand is thrilled to announce the grand opening of their new BCS facility in the heart of downtown Markham, ON, located at 85 Enterprise Blvd, Suite 400, which is set to take place on Thursday, September 19th, 2024. “Our facility in Vaughan will remain open to continue to stock inventory for Canada… Read More…

  • Gescan Announces Partnership with PataBid

    Gescan Announces Partnership with PataBid

    September 15, 2024 Gescan is excited to announce our partnership with PataBid Quantify. PataBid is a Canadian company, with software built for contractors which integrates live supplier pricing, manual drafting, and AI technology with human expertise to maximize take offs and bidding. Patabid’s Quantify software will allow contractors to access live pricing from Gescan’s website… Read More…

  • Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    September 15, 2024 The Electrical Safety Authority (ESA) cut the ribbon on its new interactive experience, “The A-MAZE-ing Adventures of Carter Current”, located at the Peel Children’s Safety Village. The interactive space is designed to help educate and keep kids safe from electrical harm by learning about electrical hazards through play. “We are excited to partner with… Read More…