Working among the electrical components in an enclosure comes with inherent risks. The power in any one enclosure can range from 2kw up to 200kw depending on the power density. One of the most common and dangerous risks is an arc flash (or flashover).

When an explosive release of energy erupts from a phase-to-phase or phase-to-ground arc fault, the results range from devastating to deadly. This air to ground electrical explosion is a critical concern.

The destructive force of an arc flash

The dangers from an arc flash are all too well known. When metal expands and vaporizes at the fault, it causes extreme heating of the air, upwards of 10,000°C/18,032°F. The concussive pressure wave can knock personnel off their feet; the ultraviolet light flash can cause blindness; the sound blast, deafness; and the molten metal and heat can cause second and third degree burns. The specific death toll has been estimated to be up to 1-2 people every day worldwide.

An arc flash can result from unsafe work procedures, accidental contact, or more systemic problems such as corrosion of components and connections or insulation failure. Arc flash prevention should be incorporated into any application from the beginning of the design process.

Minimizing arc flash exposure

Design and retrofit approaches can limit exposure by using components installed outside the enclosure to permit qualified personnel in personal protective equipment (PPE) to service equipment inside without opening the enclosure door. Interface flaps and window kits permit data retrieval, equipment monitoring or routine maintenance to be performed from outside. Collapsible fold down shelves be raised for use with laptops and monitoring equipment. External data pockets can hold wiring diagrams, operation manuals and other documents.

Arc flash protection

Sometimes components must be accessed from inside the enclosure. For example, Rittal’s arc flash solution keeps high and low voltage equipment within the confines of their own respective enclosures. Low voltage enclosures house equipment that is used for programming, data acquisition and system adjustment.

High voltage components are isolated within their own disconnect enclosure, while line side power is segregated within the power isolation enclosure. A partition wall acts as a barrier to high voltage line side power. An interlocking door system ensures that the high voltage enclosure cannot be opened while the disconnect switch is in “ON” position.

For additional safety, all interlocked doors and master door must be closed in order to re-energize the enclosure. This removes potential for accidental contact with the inline power when the disconnect enclosure is put in a safe power-off position, and locked and tagged out.

Minimizing exposure to line side power can help protect personnel from accidents. A qualified person wearing PPE and following appropriate safe work practices can perform visual inspections and tasks, such as diagnosis, testing, troubleshooting and voltage measurement with the door open even when the main enclosure is energized.

Safety is always your priority, so download Rittal’s Arc Flash and How to Prevent it free whitepaper for the first step towards arc flash prevention: http://info.rittalenclosures.com/arch-flash-lp-0.

Steve Sullivan is a training manager with Rittal. This article was first published online as a blog: http://blog.rittalenclosures.com/blog/author/steve-sullivan-training-manager.

 

Related Articles


Latest Articles

  • Virtual Training for Electricians Available at Many IBEW Canada Training Centres Across the Country

    Virtual Training for Electricians Available at Many IBEW Canada Training Centres Across the Country

    June 23, 2025 Virtual Training for Electricians (VET) is now available at many IBEW Canada Training Centres nationwide — and more are coming online soon! Whether your centre is already equipped or in the process of setting up, this is a game-changing opportunity you won’t want to miss. Need assistance? Contact the NETCO team. What… Read More…

  • Designing for Demand: The Role of Transformers in a Resilient EV Future

    Designing for Demand: The Role of Transformers in a Resilient EV Future

    June 23, 2025 Transformers in the EV Charging Boom: Are We Ready for the Load? As electric vehicles (EVs) continue their rapid rise, one question looms over the energy sector, municipalities, and developers alike: Is our infrastructure truly ready for the surge in demand? From city streets to highway rest stops, new EV chargers are… Read More…

  • The Time is Now: An Industrial Energy Efficiency Action Plan

    The Time is Now: An Industrial Energy Efficiency Action Plan

    June 23, 2025 In a whitepaper released on June third, ABB has set out the scale of the challenge facing the global industrial sector and emphasizes the critical role of industrial energy efficiency in meeting rising energy demand while strengthening energy security & affordability and driving industrial competitiveness. With 45% of the world’s electricity converted… Read More…

  • Multi-Family Construction Intentions Weigh Down Residential Sector

    Multi-Family Construction Intentions Weigh Down Residential Sector

    June 23, 2025 In April, the total value of building permits issued in Canada decreased by $829.6 million (-6.6%) to $11.7 billion. British Columbia (-$1.2 billion) led this decrease in construction intentions, which was mitigated by Ontario (+$299.3 million). On a constant dollar basis (2023=100), the total value of building permits issued in April fell by 6.6% from the previous… Read More…


Changing Scene

  • Stanpro Makes Significant Donation to Help Haven on the Queensway Move to a Larger Facility

    Stanpro Makes Significant Donation to Help Haven on the Queensway Move to a Larger Facility

    June 23, 2025 In an effort to provide essential resources to individuals and families in need in the GTA, EFC members once again stepped up to support Haven on the Queensway, a community resource centre in Etobicoke, ON. Earlier this year, Haven secured a new, larger location nearby its existing facility to meet growing demand… Read More…

  • Metalumen Manufacturing, Inc. Announces NRG INTENSI-T as New Sales Agency in Quebec

    Metalumen Manufacturing, Inc. Announces NRG INTENSI-T as New Sales Agency in Quebec

    June 23, 2025 Metalumen Manufacturing, Inc. is pleased to welcome NRG INTENSI-T as its new sales agency for the Quebec region. This partnership strengthens regional support and reflects a shared commitment to innovation and excellence. Since 1977, Metalumen has been designing, engineering, and manufacturing lighting products that blend functionality with design, offering luminaires tailored to… Read More…

  • IDEAL Electrical™ and BILT® Make it Easier to Learn Conduit Bending

    IDEAL Electrical™ and BILT® Make it Easier to Learn Conduit Bending

    June 23, 2025 Conduit bending – one of the hardest skills for professional electricians to master – is now easier than ever to learn, thanks to a first-of-its kind partnership between BILT, an app that has revolutionized step-by-step interactive instructions for DIYers and IDEAL Electrical, a 108-year old manufacturer of electrical tools and supplies for professional electricians…. Read More…

  • Introducing the New WAGO App: Your Jobsite Sidekick

    Introducing the New WAGO App: Your Jobsite Sidekick

    WAGO at your fingertips — scan the QR to get the app now. Stay connected with WAGO wherever you go. Download the WAGO App to access product details, documentation, configuration tools, as well as local distributors — all from your mobile device. Scan the QR code to get started on the App Store or Google… Read More…