Meeting National Building Code of Canada Requirements

Building Code Requirements

 

Pierre McDonald

For an electrical installation, meeting the minimum code requirements is not achieved simply by following the installation requirements of the Canadian Electrical Code Part 1 (CE Code). While electricians might believe that they are responsible just for that part of the installation that meets the CE Code, it might be shocking (no pun intended) to learn that they must also meet certain requirements of the National Building Code of Canada (NBCC). 

Here’s an example: for residential construction, the vapour barrier is an important part of the NBCC requirements, yet it is the electrician who is charged with installing vapour hats around all exterior wall and ceiling outlets. This is a very small example of requirements outside of the CE Code that should be understood by electrical tradespeople.

The CE Code includes an Appendix G, which is an informative appendix that lists requirements related to installations that are not governed by Rules of the CE Code, but are required by the NBCC. CE Code rules that are referenced to the NBCC will have the words “See Appendix G” in brackets associated with them. These references only cover those rules that are part of the fire protection requirements contained within the NBCC so you will not find the reference to the vapour barrier requirement mentioned above. (FYI, see NBCC 9.25.3 for Air Barrier Systems and 9.25.4 for Vapour Barriers.)

The application of Appendix G is stated as follows. It should be noted that the appendix is based on the 2015 edition CE Code and the 2010 edition NBCC:

• G2.1 – The intent of this Appendix is to advise Canadian Electrical Code, Part I users of performance requirements for electrically connected fire-protective equipment required by the National Building Code of Canada.

• G2.2 – Special fire protection requirements, such as use of thermal insulation, fire spread, flame spread requirements for electrical wiring and cables, flame-spread requirements for combustible raceways, and construction of electrical equipment vaults are covered by this Code (e.g., Rules 2-126, 2-128, 2-130, 2-132, 26-354, etc.).

• G2.3 – Provincial and municipal building codes may deviate from the National Building Code of Canada, and users of this list should also check those codes.

Looking into a few examples as to how this appendix will assist, we can begin with the CE Code Rules 2-128 Fire Spread, 2-130 Flame spread requirements for electrical wiring and cables, and 2-132 Flame spread requirements for totally enclosed non-metallic raceways. All mandate that they meet some requirements within the NBCC. While there are also Appendix B notes to these rules, the Appendix G notes refers the reader to several sections, articles and sentences within the NBCC. For example, Rule 2-128, refers the reader to:

• 3.1.9.1.(1) and (2), Fire stopping of service penetrations through fire-rated assemblies of fire separations

• 3.1.9.3., Penetration of fire-rated assemblies or fire separations by wires, cables, boxes, and raceways

• 3.1.13.4., Flame-spread rating for combustible light diffusers and lenses 

• 9.10.9.6., Electrical wiring and boxes and penetrating a fire separation

Rule 2-130 references:

• 3.1.4.3.(1), Wires and cables in combustible buildings

• 3.1.5.18.(1), Wires and cables in noncombustible buildings

• 3.1.5.18.(2) and (3), Wires and cables within plenums of noncombustible buildings or wiring and cables that extend from plenums

• 3.4.4.4.(1)(b), Restrictions on wiring and raceways penetrating an exit enclosure

• 3.6.4.3.(1), Equipment and wiring within plenums

And Rule 2-132 references

• 3.1.5.20., Combustible raceways in noncombustible buildings

• 3.1.5.20.(2), Combustible raceways within plenums of noncombustible buildings

In a nutshell, these references point the code user to requirements that could affect the installation or at least provide additional information for the installation. Details of these references should be fully investigated and understood by the electrical installer to ensure compliance with the CE Code rules. These references include:

• Fire stop requirements that are subjected to the fire test method in CAN/ULC-S115 – Fire Tests for Fire stop Systems
• Requirements for wiring, cables, conduit, outlet boxes and similar equipment that are allowed to penetrate a fire rated assembly under certain conditions
• Information regarding flame spread ratings of combustible light diffusers and lenses, as well as limits on the installation of these products
• Information regarding the FT rating of wires and cables, including optical fibre cables as well as installation requirements in combustible and non-combustible installations

Section 32 and certain rules within Section 32 also have substantial references in Appendix G to the sections, articles and sentences within the NBCC. This stands to reason as Section 32 “applies to the installation of electrical local fire alarm systems, permanently connected carbon monoxide alarms, and fire pumps required by the National Building Code of Canada.” While the rules in Section 32 cover conductors, wiring methods, equipment bonding, electrical supervision, circuitry and over current devices for power supplies, and smoke alarms and carbon monoxide alarms in residential occupancies, the substantial requirements for installating fire alarm systems exists within the NBCC. It is the NBCC which mandates when a fire alarm system must be installed, zoning and annunciation of fire alarm systems, elevator emergency recall (alternate floor recall for elevators), visual signal devices in a fire alarm system, and the mandatory use of CAN/ULC-S524 – Installation of Fire Alarm Systems as per 3.2.4.5, to mention just a few.

The same holds true regarding the rules for Fire Pumps, 32-200 to 32-212. It is the actual reference within Appendix G to the NBCC sentence 3.2.5.18. that mandates the use of NFPA 20 standard – Installation of Stationary Pumps for Fire Protection.In fact, Section 32 has 53 references to requirements in the NBCC. 

For some electrical installers this might not mean too much, while for others these requirements must be clearly laid out. This informative Appendix G first appeared in the 1998 edition CE Code and has provided references to those installers who must understand these requirements to fulfill contractual obligations. I have simplified the NBCC requirements to illustrate a few of the requirements associated with the NBCC that could affect the electrical Installer. It is clear that not all requirements regarding electrical installations are written in the CE Code and can easily be found. Using all the tools available, including the Appendix G references, will provide those answers.


 

Pierre McDonald, CET, is Senior Regulatory Affairs Representative/Répresentant Principal, Affaires Réglementaires, Underwriters Laboratories of Canada Inc. Based in St. Albert, AB, Pierre has been a member of the Canadian Electrical Code Part 1 technical committee as well as several subcommittees including serving as Chair of Sections 6 and 76 and as a member representing regulators on several other CSA committees. Pierre is still active with code development and interpretation.

Other articles by Pierre McDonald:

2015 CE Code: Changes on “Approved Electrical Equipment” 

Code and Public Safety 

Section 62: Fixed Electric Heating Systems 

Now Available: CAN/ULC Standard on Electric Utility Workplace Electrical Safety

Establishing When the CE Code Becomes Mandatory
 

UL Code Link 

CAN/ULC-S576-14, Standard for Mass Notification System Equipment and Accessories 

Canadian CE Code Changes: Section 20 and More 

Conductor Ampacities and Their Temperature Rating 

Codes and Standards – Provincial Legislation and the Administrative Requirements of the CE Code 

Changes to Section 12 Wiring Methods 

Section 4 Conductors — Changes from the Canadian Electrical Code’s 2009, 21st Edition to the 2012, 22nd Edition 

Related Articles


Latest Articles

  • Take the Lesson

    Take the Lesson

    September 2, 2024 By Keith Sones, seasoned utility industry executive “I really don’t want to do this.” “You have to Keith. You have no choice. You can’t leave him hanging” replied my wife. I stared at the phone like a child looks at liver on their plate. They know you have to eat it but also… Read More…

  • Quebec Drives the Growth in Residential Building Construction in June, 2024

    Quebec Drives the Growth in Residential Building Construction in June, 2024

    Investment in building construction grew 2.8% to $21.4 billion in June, after a slight increase of 0.8% in May. These increases partly reflect April’s record high of $13.4 billion in total building permits value, since investment levels for a given period are driven by permits issued in prior months. The June increase in investment in building construction was primarily… Read More…

  • Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    August 16, 2024 The new Western Memorial Regional Hospital in Corner Brook is home to Canada’s largest geothermal system, which has set a precedent for modern infrastructure for both Newfoundland and Labrador and North America. The geothermal field is approximately 600 feet below the hospital’s parking lot, and provides 100 per cent of the ground… Read More…

  • Brightening Communities: LED Technology in Action

    Brightening Communities: LED Technology in Action

    August 15, 2024 By Alex Price, Brand & Planning Manager, Current LightingTechnical Contributor: Gary Steinberg, Senior System Manager (Outdoor LED Fixtures), Current Lighting As the landscape of Canadian cities continues to evolve, the importance of outdoor lighting cannot be overstated. From enhancing public safety to promoting economic activity and fostering a sense of community, well-planned… Read More…


Changing Scene

  • Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric is transforming its Digital Buildings business in Canada with the launch of the SMART Buildings Division. This evolution marks a strategic move to deliver comprehensive solutions and services that support building owners and operators in achieving their decarbonization and sustainability goals. The demand for smart buildings is surging, driven by a global shift… Read More…

  • Introducing Alan Bearden as Interim President of Southwire Canada

    Introducing Alan Bearden as Interim President of Southwire Canada

    September 4, 2024 Southwire Canada is pleased to announce that Alan Bearden has been appointed Interim President. In this role, Alan will provide leadership and guidance for Southwire’s Canada-based organization, ensuring continuity and driving growth during this transitional period. Alan Bearden brings a wealth of experience to the position, having joined Southwire in 2008. Over… Read More…

  • A Partnership Between Electromag Graybar Canada and Phoenix Contact

    A Partnership Between Electromag Graybar Canada and Phoenix Contact

    September 3, 2024 Electromag Graybar Canada, a pioneer in industrial automation solutions and pneumatic products, is excited to announce a partnership with Phoenix Contact, a global leader in electrification, networking, and industrial automation. This collaboration, which initially began in the Langley and Ontario branches, is now expanding to Quebec. The alliance aims to provide cutting-edge… Read More…

  • Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    September 2, 2024 William (Bill) C. Smith, Director, Transitional Business of Electrozad Supply Company Limited announced his retirement as of August 30th, 2024 after 49 years of leadership. Bill began his electrical career working part-time at Electrozad Supply while completing a Sales & Marketing Program at St. Clair College.  After his first full-time position in… Read More…