Guide to the Canadian Electrical Code, Part I – Instalment 3

Electrical Conductors

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 4. It is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 4 – Conductors

The definition of conductor, from Section 0, is a wire or cable, or other form of metal, installed for the purpose of conveying electric current from one piece of electrical equipment to another or to ground.

Section 4 deals with the selection of type, ampacity and installation conditions of insulated conductors. It is a general section and therefore it applies to all conductors supplying lighting, appliances and power circuits. The selection of other conductors, such as for control, grounding, emergency, safety, fire alarms, airport installations, renewable energy, communications, cathodic protection, and others, will be governed by individual sections covering these situations. Individual sections may also apply as general sections, or may have rules that reference or amend Section 4.

For example, Sections

• 6 — Services and service equipment
• 8 — Circuit loading and demand factors
• 10 — Grounding and bonding
• 12 — Wiring methods
• 14 — Protection and control
• 16 — Class I and Class II circuits
• 26 — Installation of electrical equipment

For this reason it is important to compare the rules in Section 4 with the rules governing conductors in the section dealing with your particular installation. For instance, Rule 4-002 requires that the minimum size for all copper conductors, except for flexible cord, equipment wire, or control circuit wire, and cable (which are specifically covered by other sections) is No.14 AWG and No. 12 AWG if aluminum. However, in Section 6, Rule 6-302 Installation of overhead consumer’s service conductors requires that the minimum size for overhead consumer’s service conductors is No.10 AWG copper or No. 8 AWG aluminum. Even though there are amendatory sections and rules later in the code, it is still important that you refer to Section 4 first when selecting and installing any conductor.

Conductor selection factors

When selecting a conductor there are a number of factors to be considered. Because of the complexity of conditions, you need to have a process to determine the correct type and size for your application. The first consideration is to choose the size of conductor you need based on the

• current it will be required to carry
• conditions under which it will be installed
• type of conductor or cable to be used

Rule 4-004 Ampacity of wires and cables contains 7 items each in subrules (1) and (2) covering scenario options each for copper and aluminum that need to be studied and chosen. In addition, there are 21 other factors in the subsequent subrules to be considered.

Although this may seem daunting at first, it is simply a matter of going through the list of options and conditions and choosing the ones that apply to your situation. Rule 4-004 will then direct you to the correct table and correction factor for your situation.In some cases you will be directed to use the IEEE 385 calculation method or the tabulated information tables in Appendix D. The IEEE 385 Standard Power Cable Ampacity Tables contains all pertinent equations and has the electrical/thermal analog circuit and calculation examples in the annex.

Once the right ampacity has been chosen or calculated, the next factor to consider, according to Rule 4-006, is the temperature limitations on the conductor ampacity you have chosen. Where the maximum conductor termination temperature is marked on the equipment, you will have already chosen the minimum size of conductor based on the correct temperature column of tables 1, 2, 3 or 4. Where the maximum conductor termination temperature is not marked on the equipment, the temperature to be used is: 600 C for equipment rated 100 A or less or marked for use with No.1 AWG or smaller conductors, or 750 C for equipment rated more than 100 A or marked for use with conductors larger than No. 1 AWG.

These conditions apply only to the first 1.2 meters of conductor length measured from the termination point of the equipment.One other condition to note when using a single conductor cable with a metal sheath or armour: induced voltages may cause the conductor insulation temperature to exceed its rating. In this case,Rule 4-010 Induced voltages and currents in metal armour or sheaths of single-conductor cables requires you to derate the conductor along with some other procedures to mitigate this situation.

The next important consideration outlined in Rules 4-008, 4-012, 4-014, 4-016, 4-018, 4-020, 4-040 and 4-042 is the selection of the type of insulated conductor, flexible cord, equipment wire or portable power cable. In some cases these rules will specify minimum sizes and ampacities for the various types.

Finally we go back to Rules 4-022, 4-024, 4-026, 4-028, 4-030, 4-032, 4-034, and 4-036, which provide for the use of a common neutral, installation, identification and use of neutral and identified conductors. Rule 4-038 Colour of conductorscovers the colouring of insulated grounding and bonding conductors, and where colour-coded circuits are required.

You will note that Section 4 does not apply to non-insulated grounding or bonding conductors. The use, size and ampacity of these conductors are covered by Section 10, which we will deal with in subsequent instalments.

In the next installment we will explore Section 6 — Services and service equipment.

Read the rest of the instalments in the series:

Part 1: Guide to the CE Code, Part I — A Roadmap (Instalment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I — Instalment 2
Part 3: Guide to the Canadian Electrical Code, Part I — Instalment 3
Part 4: A Road Map to the CE Code, Part 1 — Instalment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Instalment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Instalment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Instalment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Instalment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 — Instalment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 — Instalment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…