Guide to the Canadian Electrical Code, Part I

William (Bill) Burr

Dec 6, 2020

By William (Bill) Burr

In Section 24 — Health care areas, Rule 24-000 Scope outlines that this section amends or supplements the general requirements of the code. It has been compiled by the Technical Committee on Applications of Electricity in Health Care along with the Committee on the Canadian Electrical Code, Part I, and provides specific rules for patient care areas and essential electrical systems in health care facilities. This section does not amend or supplement the provisions of Section 60 – Electrical communications systems, except for bonding as per rule 24-104(7) or equipment in shower stalls and bathtub enclosures as per rule 24-108.

Rule 24-002, Special terminology, provides definitions for terms used in this section, which is additional or supplementary to the definitions in Section 0.

Section 24 is divided into three main parts: Patient care areas, Isolated systems, and Essential electrical systems.

Patient care areas

According to 24-002, patient care areas are areas intended primarily for the provision of diagnosis, therapy, or care. Also, note that patient care areas include not only hospitals but also patient care areas of other health care facilities and medical clinics where basic, intermediate, or critical care is carried out. Appendix B contains important additional notes for this section.

Rule 24-100 describes that the rules of this part apply to patient care areas designated as basic, intermediate, or critical care. These areas are designated by the administration of the health care facility in accordance with CSA Z32-15 Electrical safety and essential electrical systems in health care facilities and CSA Z8000-11 Canadian health care facilities.

Rule 24-102 contains the rules for the characteristics of circuits in basic care areas. Note that communication or nurse call equipment must follow the rules of Section 16 for a Class 1 circuit.

Rule 24-104 deals with bonding to ground in basic care areas. Note also that exposed non-current-carrying metal parts of communication, radio, television, and non-electrical equipment must be bonded to ground with a copper conductor sized as per Table 16 and connected to an equipment bonding conductor or bonding busbar.

Rule 24-106 outlines the requirements for installing receptacles in basic care areas. Where receptacles are intended for patient care they need to be located to prevent unintended use. Receptacles located where cleaning takes place need to be located 300mm above the floor. Receptacles installed in washrooms must be within 1.5m of a sink, outside of bathtub or shower stall, and protected by a class A GFCI. Housekeeping receptacles need to be identified as such. All non-locking receptacles except those in bathrooms or washrooms must be hospital grade. Receptacles supplied from the essential electrical system must be exclusively coloured red. Isolated ground type receptacles cannot be used in this area.

Rule 24-108 permits emergency signaling, and similar equipment manufactured to CAN/CSA-C22.2 No.60601 series of standards, to be installed at normal heights in bathtub enclosures and shower stalls.

Rule 24-110 deals with the characteristics of branch circuits in intermediate and critical care areas. These circuits may be either a grounded system as in 24-102 or an isolated ground system as per rule 24-200. Branch circuits supplying loads within patient care environments must be 2-wire circuits except for multiphase equipment.

Rule 24-112 requires that bonding to ground in intermediate and critical care areas conform to rule 24-104, whether supplied from a grounded distribution system or an isolated wiring system.

Rule 24-114 specifies that receptacles in intermediate and critical care areas must meet the requirements of rule 24-106. In addition, they must be clearly identified if supplied from an isolated system.

Rule 24-116 requires that receptacles in areas subject to standing or drenching fluids be protected with a class A GFCI or be supplied by an isolated system.

Isolated systems

According to 24-002, an isolated system is an electrical distribution system in which no circuit conductor is connected directly to ground.

Rule 24-200 outlines that rules 24-202 to 24-208 apply to isolated systems for circuits in intermediate and critical care patient care areas. Branch circuits supplying only fixed luminaires and permanently connected equipment may be supplied by a conventional grounded system as long as the circuits are in separate raceways.

Rule 24-202 specifies the means of supply of isolated systems be by the secondary of an isolating transformer, a motor-generator set, or an isolated battery powered inverter. Where multiple isolated power systems serve one patient care area, they must be bonded together.

Rule 24-204 outlines the required characteristics for single-phase isolated circuits.

Rule 24-206 provides that an individually isolated single phase system supplying only a single load may optionally use a line isolation monitor and that overcurrent devices need not be installed.
Rule 24-208 specifies the requirements for three-phase isolated systems.

Essential electrical systems

According to 24-002, an essential electrical system is a system that has the capability of restoring and sustaining a supply of electrical energy to specified loads in the event of a loss of the normal supply of energy.

Rule 24-300 sets out that rules 24-302 to 24-306 apply to portions of a health care facility in which the interruption of the normal power supply would jeopardize the safe and effective care of patients.

Rule 24-302 outlines that the health care administration designates which supply load circuits are essential electrical circuits and that the wiring of the essential electrical system must be kept separate from other wiring and equipment.

Rule 24-304 provides for the selection, installation, and operation of transfer switches for essential electrical systems.

Rule 24-306 describes the requirements for an emergency supply

In the next instalment, we will discuss Section 28 — Motors and Generators.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

Related Articles


Latest Articles


Changing Scene

  • Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    October 19, 2026 “Rexel Canada welcomes Rexel USA agreement to acquire GCG (Genuine Cable Group)—a transformational step that will strengthen our capabilities, expand our reach and support continued growth across Canada, North America and global markets,” Rexel Canada CEO, Jeffrey Moyle announced on LinkedIn. GCG is a leading specialty infrastructure platform providing wire and cable,… Read More…

  • Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    October 19, 2026  The Ontario government has allocated 40,000 new funded seats at publicly assisted colleges and universities to connect more students to good-paying, in-demand careers. This allocation, which is part of a broader $1.7 billion investment to support a total of 70,000 new seats, supports the province’s plan to protect Ontario and build a… Read More…

  • QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    October 19, 2026 Construction of the new acute care tower at the QEII Halifax Infirmary has reached another milestone, with the Level 8 podium structure now in place. The podium is the lower, wider portion of the building that forms the base of the 14-storey acute care tower. It will house a range of hospital… Read More…

  • Ontario Starts Major Construction on Grimsby GO Station

    Ontario Starts Major Construction on Grimsby GO Station

    October 19, 2026 The Ontario government has awarded a contract for major construction on Grimsby GO Station, marking another milestone in its plan to protect Ontario by building the transportation infrastructure needed to reduce gridlock, shorten travel times and support economic growth across the province. Expected to be completed in the second half of 2027,… Read More…