Test Your Knowledge of the Canadian Electrical Code – Part 1 — The Answers: Fire Alarm Systems

EIN Code Quiz2 400

June 11, 2021

In the last installment, you had the opportunity to answer our questions about the Code and best practices. Here are the answers to those questions.

Fire Alarm Systems, Smoke and Carbon Monoxide Alarms, and Fire Pumps

Q: What rule specifies the requirements for insulated conductors and cables in fire alarm systems and what are the requirements?

A: Rule 32-100 specifies the requirements for insulated conductors and cables in fire alarm systems which include:

  • copper material
  • ampacity
  • use of optical fiber cables
  • use of stranded conductors
  • insulation rated at 300 volts
  • determining wire size for raceways or integral assemblies
  • selection in accordance with rules 12-102(3)or 12-122(1)

Q: What rule requires that no disconnecting means, overcurrent protection or device capable of interrupting the fire pump circuit may be placed between the service box from the normal power supply and the fire pump transfer switch or controller, except?

A: Rule 32-306 requires that no disconnecting means, overcurrent protection or device capable of interrupting the fire pump circuit may be placed between the service box from the normal power supply and the fire pump transfer switch or controller:

  • Except a circuit breaker that is permanently labeled identifying it as a fire pump disconnect.
  • In addition, the circuit breaker must be lockable in the closed position and may be in the separate service box as in Rule 32-304

Q: In the case where this circuit breaker is installed in an emergency power supply circuit between the emergency power source and the fire pump transfer switch, the rating of the circuit breaker shall be?

A: As per rule 28-200:

  • Be set or rated to not less than the rating of the overcurrent protection provided integral with the fire pump transfer switch
  • Indefinitely carry the locked rotor current of the fire pump
  • Where it is installed in a normal supply circuit be rated not less than the overcurrent protection of the fire pump controller
  • Where the circuit breaker is installed in an emergency supply feeder between the emergency generator and the fire pump transfer switch, the feeder must bypass the generator main circuit breaker and be connected directly to the emergency generator.

Go HERE to discuss

Related Articles


Latest Articles


Changing Scene

  • Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    Rexel Canada Welcomes Rexel USA Agreement to acquire Genuine Cable Group

    October 19, 2026 “Rexel Canada welcomes Rexel USA agreement to acquire GCG (Genuine Cable Group)—a transformational step that will strengthen our capabilities, expand our reach and support continued growth across Canada, North America and global markets,” Rexel Canada CEO, Jeffrey Moyle announced on LinkedIn. GCG is a leading specialty infrastructure platform providing wire and cable,… Read More…

  • Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    Ontario Announces Additional Funding for Training Seats for In-Demand Careers

    October 19, 2026  The Ontario government has allocated 40,000 new funded seats at publicly assisted colleges and universities to connect more students to good-paying, in-demand careers. This allocation, which is part of a broader $1.7 billion investment to support a total of 70,000 new seats, supports the province’s plan to protect Ontario and build a… Read More…

  • QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    QEII Halifax Infirmary Tower Project Reaches Milestone, Wins Collaboration Award

    October 19, 2026 Construction of the new acute care tower at the QEII Halifax Infirmary has reached another milestone, with the Level 8 podium structure now in place. The podium is the lower, wider portion of the building that forms the base of the 14-storey acute care tower. It will house a range of hospital… Read More…

  • Ontario Starts Major Construction on Grimsby GO Station

    Ontario Starts Major Construction on Grimsby GO Station

    October 19, 2026 The Ontario government has awarded a contract for major construction on Grimsby GO Station, marking another milestone in its plan to protect Ontario by building the transportation infrastructure needed to reduce gridlock, shorten travel times and support economic growth across the province. Expected to be completed in the second half of 2027,… Read More…