2021 Changes in the Canadian Electrical Code: Class 2 Transformer Overcurrent Protection

EIN Douglas Code Series 400

October 15, 2021

By Steve Douglas, Senior Technical Codes Specialist, QPS

This is the fourth in the series of articles detailing significant changes for the 2021 Canadian Electrical Code Part I (CE Code) that may impact electrical equipment manufacturers. 

Through my knowledge and experience, it has been common practice for many years to install a Class 2 transformer with 15 A overcurrent protection in the primary circuit. However, the wording in the 2018 CE Code does not allow this practice.

Allowing this would mean that the primary overcurrent protection for a Class 2 transformer would be required to follow CE Code Rule 26-254 limiting the size of this overcurrent protection to 125% of the primary current. Prior to the rewrite of Section 16 in the 1978 CE Code, the 1975 edition of the CE Code allowed a 15 A overcurrent device in the primary circuit of a Class 2 transformer. This rule from the 1975 edition of the CE Code was deleted as part of a rewrite of Section 16 in the 1978 edition.

 

QPS image for article 4 2108

Image courtesy of QPS, depicts a Class 2 transformer connected to a 15 A branch circuit breaker.

A previous IAEI NEWS (International Association of Electrical Inspectors) article on transformer overcurrent protection raised a question by an IAEI NEWS reader regarding the maximum overcurrent protection allowed for a Class 2 transformer. As a result of the inquiry a proposal was submitted to add new Subrule 2) to Rule 16-202 Methods of installation on the supply side of overcurrent protection, transformers, or devices having Class 2 outputs. The new subrule allows a 20 A-rated overcurrent device to protect the supply side of transformers or other devices having Class 2 outputs. The rating of 20 A aligns with the product standards for transformers or other devices having Class 2 outputs.

For more information or clarification on this topic, please contact Steve Douglas at SDouglas@qps.ca

Steve Douglas is the Senior Technical Codes Specialist for QPS Evaluation Services and is an IAEI International Past President. In addition, Steve is the Immediate Past Vice Chair of the CE Code Part I, Chair of CE Code Part I Subcommittees for Section 2, 12, and 84, and a member on Sections 8, 40, 64, 68, 76, 78 and Appendix A. In addition, Steve is the Chair of the CSA Subcommittees for Standards C22.2 No. 273 Cablebus, C22.2 No. 327 HDPE Conduit, C22.6 No. 1, Electrical Inspection Code for Existing Residential Occupancies committee, SPE-1000 Working Group the Past Chair of the Technical Committee on Wind Turbines, and a member on committees for the Objective Based Industrial Electrical Code, Safety Management Systems, Energy Storage Systems, Solar Photovoltaic Modules, Industrial control panels and assemblies, Industrial Machinery, Photovoltaic Cable, Fuel Cells, Wind Turbines, Distribution transformers, Outlet Boxes, and Wiring Fittings Hardware and Positioning Devices.

Source

Related Articles


Latest Articles

  • Overview of Upcoming Changes to Ontario Construction Act – Joint Leadership Conference Panel Discussion

    Overview of Upcoming Changes to Ontario Construction Act – Joint Leadership Conference Panel Discussion

    November 4, 2025 The inaugural Joint Leadership Conference hosted this October in Toronto by three Ontario contractor associations, Electrical Contractors Association of Ontario (ECAO), the Mechanical Contractors Association of Ontario (MCAO), and the Construction Labour Relations Association of Ontario (CLRAO), featured some interesting discussions around AI and changes coming to the Ontario Construction Act. The… Read More…

  • Illumination Contributes to La Pêche Townhall’s “Building of the Future”

    Illumination Contributes to La Pêche Townhall’s “Building of the Future”

    November 3, 2025 La Pêche (Quebec, Canada) has constructed a new townhall that was designed for the future. The dramatic two-story structure is comprised of solid wood, both inside and out, and presents an impressive facade on the main street of the community. And it incorporates the latest innovations in sustainable construction. With its forthcoming… Read More…

  • Houle Highlight Broadway Subway Project Now Underway

    Houle Highlight Broadway Subway Project Now Underway

    November 3, 2025 Houle has announced the company has begun work on the Broadway Subway Project in BC. The project will extend the TransLink Millennium Line by 5.7 km to serve the Broadway Corridor, one of BC’s busiest routes, becoming a critical link that connects communities, increases frequency and reliability for transit users, and enhances… Read More…

  • Non-Residential Building Investment Increases Slightly in August, 2025

    Non-Residential Building Investment Increases Slightly in August, 2025

    Overall, the total value of investment in building construction edged up 0.1% to $22.8 billion in August. The non-residential sector edged up $22.9 million, while the residential sector increased slightly by $10.5 million. Year over year, investment in building construction grew 8.7% in August. On a constant dollar basis (2023=100), the total value of investment in building construction in August… Read More…


Changing Scene