The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 8 — circuit loading and demand factors.

This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook,* but will hopefully provide some help in navigating the Code.

Section 8 is a general section of the code. It provides you the information you need to selectthe rating of a circuit, feeder or service (i.e., ampacity of the circuit conductors and rating/setting of the circuit over current devices). Rule 8-104 describes the rating of a circuit (feeder or service) and establishes the criteria between the calculated load and circuit (feeder or service) rating. As well, it determines branch circuit positions for dwelling units.

The special terminology used in this section includes:

• Basic Load—only lighting and receptacle circuits based on the dimensions of specific building occupancy as listed in Table 14
• Calculated load – the load calculated in accordance with the rules in this section
• Demonstrated Load— the historical demand watt information recorded over 24 months for the same type of facility

The General section outlines methods of calculating voltage drop, maximum circuit loading, use of demand factors, number of branch circuit positions and determination of living areas.It specifies standard voltage divisers to be used when calculating currents from watts or volt-amperes in low voltage systems; maximum allowable voltage drop in installations; maximum circuit loading based on the overcurrent device used; and the calculated load. You will also find here the factors for determining a continuous, cyclic, or intermittent load, and how this affects the selection of conductors and equipment.

This section also outlines conditions for Use of demand factors; that is, where

• the size required for conductors and switches is not available in a standard size
• two or more loads are installed, but only one can be used at a time
• air conditioning and electric space heating are installed and only the greater load is used for calculating demand
• loads of a cyclic nature are installed such that the maximum load cannot be supplied at one time)

Where additional loads are added to an existing service or feeder, Rule 8-106(9) permits the load to be calculated by adding the sum of the additional loads to the maximum existing demand load measured over 12 months.Other demand factors can be based on demonstrated load calculations by a qualified person, as determined by the authority having jurisdiction.

Another function of this section is to outline the number of branch circuit positions needed for dwelling units. This is based on the ampacity of the service and whether a central electric furnace is intended.

The Services and feeders section outlines the methods of calculating the minimum ampacity of service or feeder conductors for various types of occupancies. Although the various options and conditions may seem complicated, methodically working through the demand factors for each type of occupancy will allow you to determine the correct ampacity for service or feeder conductors.

The methods for determining demand factors for dwelling units are divided intosingle dwellings and apartment and similar buildings.For single dwellings you are given two options depending on the size of the dwelling.In the first criterion, where the living area of the dwelling exceeds 90 m2, the basic load is 5000w and additional loads are added with various demand factors as listed in Rule8-200 (1)(a)(ii to vii). The second criterion is to use a basic load of 100 A if the floor area is 80m2 or more, or 60 A if the floor area is less than 80 m2. Note that Rule8-110 designates how to determine the living area.

For two or more dwelling units of row houses, the minimum ampacity of service or feeder conductors from a main service is based on the above demand factors for each single dwelling, excluding electric space heating and air-conditioning loads, plus the demand factors outlined in Rule 8-202(3).

For apartments and similar buildings, the minimum ampacity of service or feeder conductors from a main service is calculated according to Rule 8-202.As with single dwellings and row houses above, the basic load is based on living area plus the demand factors for various other loads as outlined in Rule 8-202 (1 to 4). It should be noted that the load calculated for a single dwelling or for dwelling units in an apartment building is not considered to be continuous. However, a house load (i.e., load of equipment installed in a common area of an apartment building) is considered to be continuous for the purpose of Rule 8-104.

There are specific rules for determining the ampacity of service or feeder conductors for schools (Rule 8-204), hospitals (Rule 8-206), and hotels, motels, dormitories, and buildings of similar occupancy (Rule 8-208). For other occupancies, as listed in Table 14, the calculations are in Rule 8-210.

One other consideration is exit, emergency and show window lighting where the loads may be spread throughout the building. Exit and emergency lighting demand shall be determined by connected load. In the case of show window lighting, demand is based on 650W/m measured along the base of the windows.

This section also outlines required branch circuit positions and demand factors. Rule 8-300 provides demand loads for branch circuits supplying electric ranges and cooking units. Rule 8-302 specifies that branch circuits supplying data processing equipment be considered continuous loads. Rule 8-304 specifies that the maximum number of outlets per any 2-wire circuit is 12, unless the actual connected load is known and the load current doesn’t exceed 80% of the overcurrent device rating.This means that the load of a typical 2-wire circuit protected by a 15 A rated overcurrent device is considered to be 12 A.

Rule 8-400 provides guidance for the number and loading of branch circuits for automobile heater receptacles generally, and where the loading on each receptacle is controlled or restricted.

In the next installment we will look at Section 10 — Grounding and bonding.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Take the Lesson

    Take the Lesson

    September 2, 2024 By Keith Sones, seasoned utility industry executive “I really don’t want to do this.” “You have to Keith. You have no choice. You can’t leave him hanging” replied my wife. I stared at the phone like a child looks at liver on their plate. They know you have to eat it but also… Read More…

  • Quebec Drives the Growth in Residential Building Construction in June, 2024

    Quebec Drives the Growth in Residential Building Construction in June, 2024

    Investment in building construction grew 2.8% to $21.4 billion in June, after a slight increase of 0.8% in May. These increases partly reflect April’s record high of $13.4 billion in total building permits value, since investment levels for a given period are driven by permits issued in prior months. The June increase in investment in building construction was primarily… Read More…

  • Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    August 16, 2024 The new Western Memorial Regional Hospital in Corner Brook is home to Canada’s largest geothermal system, which has set a precedent for modern infrastructure for both Newfoundland and Labrador and North America. The geothermal field is approximately 600 feet below the hospital’s parking lot, and provides 100 per cent of the ground… Read More…

  • Brightening Communities: LED Technology in Action

    Brightening Communities: LED Technology in Action

    August 15, 2024 By Alex Price, Brand & Planning Manager, Current LightingTechnical Contributor: Gary Steinberg, Senior System Manager (Outdoor LED Fixtures), Current Lighting As the landscape of Canadian cities continues to evolve, the importance of outdoor lighting cannot be overstated. From enhancing public safety to promoting economic activity and fostering a sense of community, well-planned… Read More…


Changing Scene

  • Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric is transforming its Digital Buildings business in Canada with the launch of the SMART Buildings Division. This evolution marks a strategic move to deliver comprehensive solutions and services that support building owners and operators in achieving their decarbonization and sustainability goals. The demand for smart buildings is surging, driven by a global shift… Read More…

  • Introducing Alan Bearden as Interim President of Southwire Canada

    Introducing Alan Bearden as Interim President of Southwire Canada

    September 4, 2024 Southwire Canada is pleased to announce that Alan Bearden has been appointed Interim President. In this role, Alan will provide leadership and guidance for Southwire’s Canada-based organization, ensuring continuity and driving growth during this transitional period. Alan Bearden brings a wealth of experience to the position, having joined Southwire in 2008. Over… Read More…

  • A Partnership Between Electromag Graybar Canada and Phoenix Contact

    A Partnership Between Electromag Graybar Canada and Phoenix Contact

    September 3, 2024 Electromag Graybar Canada, a pioneer in industrial automation solutions and pneumatic products, is excited to announce a partnership with Phoenix Contact, a global leader in electrification, networking, and industrial automation. This collaboration, which initially began in the Langley and Ontario branches, is now expanding to Quebec. The alliance aims to provide cutting-edge… Read More…

  • Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    September 2, 2024 William (Bill) C. Smith, Director, Transitional Business of Electrozad Supply Company Limited announced his retirement as of August 30th, 2024 after 49 years of leadership. Bill began his electrical career working part-time at Electrozad Supply while completing a Sales & Marketing Program at St. Clair College.  After his first full-time position in… Read More…