Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • 2024 Call for Nominations CAF-FCA Board of Directors

    2024 Call for Nominations CAF-FCA Board of Directors

    June 28, 2024 The Canadian Apprenticeship Forum is now accepting nominations for its Board of Directors. This is a great opportunity for those who want to be involved in setting the organization’s strategic direction and overseeing its work on behalf of Canada’s apprenticeship community. Review the CAF-FCA Board Member Job Description. For the 2024/2025-year CAF-FCA… Read More…

  • IDEAL Introduces Sneak Peek Sweepstakes

    IDEAL Introduces Sneak Peek Sweepstakes

    June 28, 2024 IDEAL Electrical has a new opportunity for electricians to win a trip to Chicago with its “Road to Sneak Peek Sweepstakes.” The sweepstakes is open from June 17-July 15 and electricians in the United States and Canada can enter to win by filling out a form to join the IDEAL Electrical loyalty program, Champions Club™…. Read More…

  • Agence Ricard Announces New Partnership with Hydel

    Agence Ricard Announces New Partnership with Hydel

    June 28, 2024 Agence Ricard has announced a new partnership with Hydel, a recognized provider in the manufacture of high-quality electrical products. This strategic partnership will allow Agence Ricard to expand its product range by adding Hydel’s meter sockets and other innovative products. Hydel is known for its reliable and sustainable solutions that meet the evolving… Read More…

  • Glen Dimplex Americas Announces Direct Distribution of Convectair and Dimplex Products in Canada

    Glen Dimplex Americas Announces Direct Distribution of Convectair and Dimplex Products in Canada

    June 28, 2024 Glen Dimplex Americas is pleased to announce that, starting September 16, 2024, it will take over the direct sales and distribution of all Convectair and Dimplex products in the Canadian electrical distribution market. This change follows Glen Dimplex Americas decision to end its distribution agreement with Ouellet Canada Inc., which has been… Read More…