Don’t Underestimate Your Estimating System’s Potential

Shawn McCadden

Shawn McCadden

Knowing what to charge clients for the work you do is often the difference between long-term success and eventual failure for the business. Many contractors look at estimating simply as a way to determine the cost of a project. In the traditional design-bid model of project delivery, this simplistic approach may work, assuming your price generates enough gross profit to cover your overhead and profit requirements. However, if your current estimating system is limited to only producing the number you charge clients for a project, you may be missing out on many other possible benefits.

First, a few assumptions

By gathering the material, labour, equipment and possible subcontractor costs of a project, contractors determine the direct cost of a project and then use a mark-up amount to determine the sell price for a project.For the sake of this discussion, we must also assume that the contractor has created a business budget. By knowing or predicting the costs of being in business for a predicted sales volume and adding in a net profit requirement, the contractor can determine burdened labour costs and know the company’s mark-up requirement over and above direct costs. We must also assume the estimator knows how to estimate and has experience estimating the kind of work the business performs. Your estimating system must become a tool that facilitates how you do business, not just a way to get to the price.

An estimating system should
• be fast and easy to use. Typically, the yellow pad and calculator method does not apply here. A computerized system allows the estimator to concentrate on estimating, not adding up numbers over and over again to gain or confirm confidence in the end result
• allow for on the spot “what-if” adjustments. The estimator must be able to quickly estimate the effects of any changes or suggested alternatives to the project during design.

By having this ability, the client’s decisions during design are better qualified by simultaneously knowing the financial impacts of those decisions
Estimating must be accurate and adequately detailed

To increase accuracy, estimating should be done so it is comparable to the company’s job costing system. Information within the estimate, and job costing, should be broken down to a level of detail that allows the insight you need to make future estimating adjustments.

Estimating in one computer program then job costing in another may become cumbersome, or may not work at all. Accounting programs will often allow job costing, but not estimating. Typically, after a project is sold, a summary of estimating information is entered into the accounting package as a budget for purposes of job cost comparison. This limitation does not allow for fast estimating or what-if adjustments. Also, it may not be easy, secure or wise to allow an estimator access to the company’s accounting information.

The formatting of each individual estimate, as well as the overall estimating system format, may be the most important consideration. How information is entered into the estimate can limit or expand how it can be used or who uses it. Strive for a format that allows the information created by the estimator to be shared throughout the company. If you build your estimate the same way you build the project, step by step, you can create a critical path for how the project will be produced. This can be a huge benefit to supervisors and others. A predefined path, showing labour and material breakdowns, allows your team to predict and schedule resources including subs, material lists, material lead times, just on time material deliveries, and overall labour requirements.

If done correctly, you can also use individual project information to create one master schedule for all company projects and resources. You will know when you need which employee or sub, depending on skills or abilities, and identify schedule conflicts or shortfalls before they occur. This critical path can also help identify cash flow needs during the project while assisting in generating payment schedules.

Separate costs and quantities

Another formatting consideration is how you break apart the information for each line item inside your estimate.Rather than enter lump sum amounts for materials and or labour, separate the costs and the quantities. By formatting your information in this way you can quickly apply what-if options for material substitutions, other material changes, and/or additional labour considerations for any changes. This also facilitates quick pricing updates when a client calls back two years later and wants to go ahead with the project.There’s no need to redo the entire estimate because you’re not sure how the lump sums were determined, just check for pricing changes as the quantity will likely still be the same.


Read more in EIN from Shawn McCadden:

3 Ways To Get Fewer Leads But Close More Remodeling Sales
Don’t Underestimate Your Estimating System’s Potential
Tips on Ball Park Pricing and Charging for Estimates
Is A Contractor Really a Salesperson If He or She Hits Send?
3 Ways To Get Fewer Leads But Close More Remodeling Sales
3 Simple Steps to Covering an Employee’s Non-Productive Time
Setting the Example: Getting Employees to Think Like Owners
Comparing Contractor Mark-ups Can Be Pointless and Very Risky
Don’t Put Your Business At Risk By Guessing At What Mark-up
Simple Profit Sharing Plan for Contractors

Check out Shawn’s website http://www.shawnmccadden.com/ and blog www.shawnmccadden.com/Subscribe-to-The-Design-Builders-Blog.

* “Understanding what impacts your construction company’s reputation,”

http://www.pn-projectmanagement.com/construction-management-tips/understanding-what-impacts-your-construction-companys-reputation

 

Related Articles


Latest Articles

  • Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    September 3, 2026 By Blake Marchand In this Q&A with Stephanie Medeiros, the Head of Mobility at Schneider Electric Canada provides insight into her perspective on EV charging infrastructure in Canada, factors that will contribute to growing EV adoption, grid modernization for commercial fleets, the role of Vehicle-to-Grid and other innovative approaches to electrification. The focus of… Read More…

  • LEDVANCE: Understanding Light Beam Angles

    LEDVANCE: Understanding Light Beam Angles

    September 3, 2026 Light Beam Angles: How It Affects Different Types of Lighting, Where It Is Applied & What to Consider When Choosing the Right One Beam angle is important in lighting design. It determines how light spreads within a space and influences both functionality and atmosphere. By understanding beam angles, you can achieve both… Read More…

  • ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    September 2, 2026 By ITC Electrical Components When selecting industrial electrical components, certification is more than a logo on a datasheet. A certification mark indicates that a product or component has been independently evaluated against specified requirements for its intended market. In North America, selecting products with the appropriate certification can affect regulatory acceptance, equipment… Read More…

  • Project Spotlight: Leigh Square Fountain

    Project Spotlight: Leigh Square Fountain

    September 2, 2026 In spring 2025, the City of Port Coquitlam unveiled a transformed Leigh Square, reimagined as a vibrant, accessible, and welcoming gathering place in the heart of downtown. At the heart of the renewed plaza, a Bellagio-style programmable dancing fountain is integrated directly into the paving—three interlocking rings where jets rise, fall, and… Read More…


Changing Scene

  • 2026 Ontario Apprenticeship Awards Call for Nominations

    2026 Ontario Apprenticeship Awards Call for Nominations

    September 3, 2026 Skilled Trades Ontario is proud to open nominations for the 2026 Ontario Apprenticeship Awards, recognizing outstanding apprentices, journeypersons, organizations and skilled trades leaders who are helping strengthen Ontario’s apprenticeship system. Award recipients will be announced at the Ontario Apprenticeship Summit on November 4, 2026, at the Toronto Congress Centre. Nominations must be submitted… Read More…

  • Bartle & Gibson Announces New Partnership with Hubbell Canada

    Bartle & Gibson Announces New Partnership with Hubbell Canada

    September 3, 2026 Bartle & Gibson Co. Ltd., an Alberta-based premier plumbing, heating and electrical distributor and Hubbell Canada have announced a new regional partnership enabling increased access to Hubbell Canada’s end-to-end electrical product portfolio across Western Canada. “With our strong presence in the west through 31 branches and counting located in Alberta, Saskatchewan, British… Read More…

  • Bartle & Gibson Opens Salmon Arm Location

    Bartle & Gibson Opens Salmon Arm Location

    September 3, 2026 Bartle & Gibson opened their new Salmon Arm location on July 20th. The Salmon Arm location features: This site is strategically positioned in the city of Salmon Arm, located near to the busy Picadilly Mall.  Salmon Arm branch is located at: 621- 10 Street SW Salmon ARM, BC V1E 1T1 Photo Source Read More…

  • MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    September 3, 2026 MacKinnon Magnetics is pleased to welcome Resilient Sales Corporation as their newest sales agency partner. Resilient Sales will represent MacKinnon Magnetics across Northeastern Ontario, including the Districts of Muskoka and Parry Sound. Key markets include Sudbury, North Bay, Timmins, Kirkland Lake, Sault Ste. Marie, Huntsville, Bracebridge and Parry Sound. “This partnership expands… Read More…