PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • Skills Ontario Supports Ontario’s Investments in Skilled Trades in Budget Announcement

    Skills Ontario Supports Ontario’s Investments in Skilled Trades in Budget Announcement

    March 28. 2024 As demand for skilled trades professionals rises, Skills Ontario is commending the government for continued investments in skilled trades and technology programing, working to address the shortfall and need to build the workforce of the future in Ontario.  The skilled trades shortage is costing Ontario approximately $25 billion in foregone GDP. A… Read More…

  • IVRY Launches 7 New VR Lessons

    IVRY Launches 7 New VR Lessons

     IVRY Technologies, a division of IDEAL Electrical, is launching seven new virtual reality (VR) lessons in Canada as part of its Virtual Electrical Training (VET) Series 2 training module. The cutting-edge training will serve as a learning resource for International Brotherhood of Electrical Workers (IBEW) training centers across Canada. Read More…

  • PEI Budget 2024 Signals Continued Focus on Healthcare, Housing and Affordability for all Islanders 

    PEI Budget 2024 Signals Continued Focus on Healthcare, Housing and Affordability for all Islanders 

    March 28, 2024 Hon. Jill Burridge, Minister of Finance, presented government’s 2024-25 operating budget to the legislative assembly, outlining $3.2 billion in investments for Prince Edward Island with a continued focus on healthcare, housing and affordability measures. “This budget signals where we’re headed as a province and shows Islanders where we will be making key… Read More…

  • BC’s Budget 2024 Prioritizes Actions for Low-Carbon Economy

    BC’s Budget 2024 Prioritizes Actions for Low-Carbon Economy

    March 28, 2024 Josie Osborne, Minister of Energy, Mines and Low Carbon Innovation, and Brittny Anderson, MLA for Nelson-Creston, met with community climate leaders in Nelson to discuss how Budget 2024 can help support people in the region to transition to a low-carbon economy and meet shared CleanBC goals. “Our government’s budget this year reflects the… Read More…