It’s been a long time coming, but good news is here! IEEE 802.3bt — the 100W Power over Ethernet (PoE) standard — has been ratified and approved as a new standard.

Now that it’s a standard, we wanted to answer a few common questions about IEEE 802.3bt.

1. What will 802.3bt allow us to do?

As the newest PoE standard, 802.3bt calls for two power variants: Type 3 (60W) and Type 4 (100W). This means that you can now carry close to 100W of electricity over a single cable to power devices like wireless access points, thermal cameras with PTZ features, LED lighting fixtures and large display screens (and the list goes on).

As a frame of reference, the original PoE standard — IEEE 802.3af — allowed for maximum delivery of 15.4W. From there, IEEE 802.3at increased maximum power to 30W. IEEE 802.3bt allows for more than six times the amount of power than the original PoE standard created in 2003.

2. Why is 802.3bt important (or necessary)?

This ratification comes at the perfect time to support smart buildings and Internet of Things (IoT). To make these concepts a reality, making more power available to devices is required (along with more bandwidth to accommodate more wired and wireless devices).

Without PoE, smart buildings would be more expensive to design and build. Case in point: instead of several different, standalone networks with their own wiring, connectors and pathways, single IP networks are being used. Before PoE, systems connected to IP networks required separate data and electrical connections, as well as proximity to electrical outlets. With PoE, one single cable provides data and an electrical connection (with power levels now close to 100W).

3. How is 802.3bt different than other PoE standards?

IEEE 802.3af and 802.3at standards call for power delivery over two pairs of a four-pair cable, using either pairs 1 and 4 or pairs 2 or 3 (but not both pairs).

IEEE 802.3bt takes advantage of all four pairs in a 4-pair cable, spreading current flow out among them. Power is transmitted along with data, and is compatible with data rates of up to 10GBASE-T.

4. What are the cabling requirements for 802.3bt?

Although the new standard states that Category 5e cable or higher is needed, it’s crucial that Category 6A 4-pair balanced twisted-pair cable is used with new 100W PoE installations for the best possible thermal and power efficiency.

Less power is dissipated in a Category 6A cable, so more of the power running through the cable is actually transferred to the device instead of being wasted. Some Category 6A cables are even designed with enough insertion loss margin to handle the extra heat generated when PoE cables are bundled. This extra margin ensures that your channel will still reach 100 m under maximum PoE load.

By running Category 6A cables to each powered device, and implementing a zone distribution architecture, you’ll create a futureproof infrastructure that supports 100W PoE along with higher data rates.

To learn more about 100W PoE and the impact it will have on your network, download a free white paper: The Time to Prepare for 100W Power over Ethernet is Now.

This article was first published online by Belden. Ron Tellas joined Belden in 2016 to help define the roadmap of technology and applications in the enterprise. Prior to this, he developed cables and connectivity for Panduit and Andrew Corp. Ron Tellas is a SME in RF design and Electromagnetic Propagation and has a BSEE from Purdue University, a MSEE from IIT, and a MBA from Purdue University.

 

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…