Electrical Contractor Fined $80,000 After Two Workers Suffer Burns

Workers Suffer Burns

An overhead and underground utility contractor has pleaded guilty and has been fined $80,000 after two workers suffered burns while working on electrical equipment that had not been properly shut off. The incident occurred at a Toronto condo building in February 2014. The two workers were from Powerline Plus, which was under contract to Toronto Hydro.

The workers were instructed by their supervisor to enter an electrical vault to begin preparing termination of conductors that had been pulled into the vault.The vault contained various energized electrical equipment, including step-down transformers and switchgears. The handle on one of the switchgears was in an open position with a blue tag attached indicating that there was work being conducted on the unit. Neither worker was aware that the switchgear remained energized, and since both workers believed the panel was not live they did not test to see if it was energized. No rubber gloves were worn and no barriers were used.

As the workers positioned themselves and began work, an arc flash occurred within the switchgear unit. Both workers received second- and first-degree burns; one of them also received third-degree burns.

Powerline Plus pleaded guilty to failing as an employer to ensure that the lockout measures and procedures prescribed by Ontario Regulation 213/91 (the Construction Projects Regulation) were carried out, contrary to the Occupational Health and Safety Act.

 

Related Articles


Latest Articles

  • EFC Represents Industry on National EV Infrastructure Strategy

    EFC Represents Industry on National EV Infrastructure Strategy

    May 11, 2026 By Electro Federation Canada Cherith Sinasac, Director of Government Affairs at Electro-Federation Canada (EFC), recently appeared before the House of Commons Standing Committee on Industry and Technology (INDU) to provide industry perspectives on the federal government’s electric vehicle (EV) policies, including the development of a national EV charging infrastructure strategy. In her Read More…

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 62

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 62

    May 11, 2026 Section 62 — Fixed electric heating systems. 62-000 Scope states that this is a supplementary or amendatory section of the Code and applies to the installation of electric heating systems for space heating, surface heating, water heaters and other electric heating system applications. Appendix B and the CE Code Handbook provide additional Read More…

  • EFC Business Confidence Survey Q2 2026

    EFC Business Confidence Survey Q2 2026

    May 8, 2026 EFC Business Confidence Poll in Q2 2026 remains positive but is moderating compared to the previous quarter. With strong participation – 104 respondents, results show most of the industry expects growth. 66% predict increase in FY2026 sales while 25% estimate a decline, yielding a +40% balance of opinion, down from +62% in Read More…

  • When Cheap Wire Isn’t Cheap: A Scenario the Trade Should Consider

    When Cheap Wire Isn’t Cheap: A Scenario the Trade Should Consider

    May 8, 2026 Why price alone is never a purchasing strategy in the electrical trade, and why the distributor channel still matters. An editorial perspective for electrical contractors, distributors, specifiers, end users, and their purchasing managers. Imagine a scenario familiar to many experienced contractors. A team member shows up on site with reels of NMD90 Read More…


Changing Scene

  • RENO Lighting is Celebrating 10 Years of Dedication

    RENO Lighting is Celebrating 10 Years of Dedication

    May 11, 2026 RENO Lighting is celebrating their people as they mark the work-anniversaries for three of their team members, view the company’s LinkedIn post below. At RENO Lighting, growth has never been just about products, warehouses, or market expansion.It has always been about people. We are proud to recognize three incredible team members—Micheal Ercegovic, Read More…

  • RVE and Desdow Announce Representation Agreement in Quebec

    RVE and Desdow Announce Representation Agreement in Quebec

    May 11, 2026 RVE and Desdowed are pleased to announce a representation agreement for Quebec as of May 1, 2026. “With over 15 years of expertise in transportation electrification, Desdowd is a key player in the electrical distribution industry and will ensure continuity in sales activities, technical support, and guidance for engineering firms in the Read More…

  • NETCO Applauds the Federal Government of Canada Spring Economic Update

    NETCO Applauds the Federal Government of Canada Spring Economic Update

    May 11, 2026 Chris Swick, Executive Director, National Electrical Trade Council (NETCO) released a statement on LinkedIn applauding the Federal Government of Canada Spring Economic update, which was announced on April 28th. “Today’s commitments in the Spring Economic Update represent a meaningful and long-overdue investment in Canada’s skilled trades workforce. At NETCO, we strongly support Read More…

  • Spring Economic Update 2026 Skilled Trades Training Investment

    Spring Economic Update 2026 Skilled Trades Training Investment

    May 8, 2026 Spring Economic Update 2026 is the next step in the federal government’s plan to build Canada.  The stated goal is to deliver targeted relief to make life more affordable, support workers, and accelerate the construction of homes and major infrastructure. It also aims to strengthen Canada’s competitiveness and economic growth while investing in strong, Read More…