Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • Saskatchewan Investing in Skills Training

    Saskatchewan Investing in Skills Training

    March 28, 2025 Guided by Building the Workforce for a Growing Economy: the Saskatchewan Labour Market Strategy, the Ministry of Immigration and Career Training is investing more than $117.0 million in programs and services. “We continue to make training available for Saskatchewan people to prepare for the record number of jobs being created by our growing… Read More…

  • New Skilled Trades and Technology Building for the New Saskatchewan Polytechnic Joseph A. Remai Saskatoon Campus Proceeding to Request for Proposals

    New Skilled Trades and Technology Building for the New Saskatchewan Polytechnic Joseph A. Remai Saskatoon Campus Proceeding to Request for Proposals

    March 28, 2025 Three teams are advancing to the next stage of procurement for the new Skilled Trades and Technology building for the Saskatchewan Polytechnic, Joseph A. Remai Saskatoon Campus. Upon procurement completion, the successful proponent will be awarded the design and construction of the new Trades building under a Design-Build agreement.  “This project is… Read More…

  • New Brunswick Legislation Introduced to Support Interprovincial Labour Mobility

    New Brunswick Legislation Introduced to Support Interprovincial Labour Mobility

    March 28, 2025 The New Brunswick government has introduced legislative amendments to improve labour mobility and reduce interprovincial barriers. “With potential tariff-related disruptions and an uncertain economic climate, workers and businesses need the ability to adapt quickly to quickly changing circumstances,” said Jean-Claude D’Amours, acting minister of post-secondary education, training and labour. “A flexible and… Read More…

  • New Brunswick Electric Vehicle Incentive Will End July 1

    New Brunswick Electric Vehicle Incentive Will End July 1

    March 28, 2025 The New Brunswick provincial government will end its Electric Vehicle Incentive Program on July 1. “This rebate program made it possible for many New Brunswickers to buy an electric vehicle during their introduction to the market, and is helping reduce greenhouse gas emissions,” said Finance and Treasury Board Minister René Legacy, who… Read More…