Expanded Substation Will Help Meet Future Growth in Greater Victoria Area

BC Hydro

May 18, 2016

BC Hydro has completed a major $47 million expansion of the George Tripp substation to help meet the growing needs of the Greater Victoria area for a reliable supply of power.

“The demand for electricity in Victoria will increase by about two per cent per year over the next 10 years and this important investment at George Tripp will help us meet that demand,” said Bill Bennett, Minister of Energy and Mines. “We are making investments like this all over Vancouver Island. In fact, BC Hydro will spend about $2 billion over the next decade on the island to upgrade existing assets and build new infrastructure to support the growing population and economy. These capital projects will create 9,300 person-years of employment.”

Construction on the George Tripp project began in 2013. Project work involved adding a new step-up transformer and switchgear breaker equipment, and installing a new 230 kilovolt underground transmission cable that connects to nearby Horsey substation.

“Between the upgrades at George Tripp substation and the ones nearing completion at Horsey substation, this represents a $95 million investment to upgrade Victoria’s two major substations,” said Greg Reimer, Executive Vice President, Transmission, Distribution & Customer Service, BC Hydro. “Most of our infrastructure in the area was built decades ago and is in need of reinvestment so that we can continue providing reliable power to our customers when they need it.”

About 75 jobs were created over two and a half years of construction between the George Tripp and Horsey projects. Nanaimo-based F&M Installations provided cable installation for the new underground transmission cable.

“Stable and reliable electrical supply is an essential component of our economy that we often take for granted,” said Bruce Carter, CEO of the Greater Victoria Chamber of Commerce. “This improvement at George Tripp and the array of related projects are critical building blocks for our modern community and our modern economy.”

BC Hydro is in the midst of a major capital plan that is investing, on average, $2.4 billion a year, over the next ten years in the system. Examples of capital projects on Vancouver Island currently under way or nearing completion include:

John Hart generating station replacement project in Campbell River (about $1 billion);
South Wellington substation project in Nanaimo ($29 million);
Buckley Bay substation project in the Comox Valley ($28 million); and
Campbell River substation project ($25 million).

Facts:
The George Tripp substation was originally built in the 1950s and serves 26,000 customers.
The Horsey substation on Nanaimo St. in Victoria serves 74,000 customers.
Construction on the $48 million upgrade at Horsey substation began in 2013 and is scheduled to be completed later this year.
Over the past five years, BC Hydro has invested more than $125 million to upgrade or build new electrical infrastructure throughout the Greater Victoria area.
Over the next 10 years, BC Hydro capital projects on Vancouver Island are expected to generate a total combined GDP of $930 million.
There are about 400 Vancouver Island companies that are currently helping BC Hydro with capital project work across the province.

 

Related Articles


Latest Articles


Changing Scene

  • SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    August 1, 2025 SurgePure Corporation is proud to announce its new partnership with Advance Electrical Agency, who will represent the company across Saskatchewan, Manitoba, and Western Ontario. Led by principals Darren Churchwell and Bob Fiesel , the Advance team is part of a well-established agency known for representing some of the most respected manufacturers in… Read More…

  • Munden Partners with Valid Manufacturing in Atlantic Canada

    Munden Partners with Valid Manufacturing in Atlantic Canada

    August 1, 2025 Munden Enterprises has announced that they are back in the custom enclosure business through a new partnership with Valid Manufacturing Ltd. Expect Canadian-made, engineered solutions for industrial, utility, transportation, wastewater, renewables, and beyond. Whether you need a bare enclosure or a fully assembled panel, Munden is here to help. Reach out to… Read More…

  • JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    August 1, 2025 NOARK Electric is pleased to announce a new partnership with Cambridge, Ontario based manufacturing representitive, JEHS. This strategic collaboration will expand NOARK’s reach and customer support across Ontario and beyond, bringing reliable and innovative electrical solutions to a wider audience. With over 50 years of combined sales experience, JEHS brings a strong… Read More…

  • BC Hydro Making it Easier and More Affordable to Connect New Homes

    BC Hydro Making it Easier and More Affordable to Connect New Homes

    July 24, 2025 BC Hydro is supporting the construction of new housing developments in growing communities by advancing changes to streamline upgrades and reducing the cost of new customer connections to BC Hydro’s electricity grid. “As communities across B.C. grow, so does the need for essential housing. We are committed to ensuring we’re ready to… Read More…