Keeping the roof open: Retrofit of Rogers Centre’s retractable roof

Rogers Centre

The Rogers Centre’s roof and its systems had been meticulously maintained from the outset; however certain parts and components had been discontinued over the years, making the original technology outdated and difficult to maintain. As time went on, opening and closing the roof became more challenging. “I always equate it to this: Not many people are still driving a car they had 20 years ago,” said Dave McCormick, Engineering Manager, Rogers Centre.

The roof, which consists of three moving panels and one fixed piece, is 282 feet high at its center and covers 8 acres. Two of the panels slide under the fixed panel, then the final panel rotates around the stadium and into place until the four panels resemble a stack of plates. When opening or closing the roof, it has to be capable of quickly, reliably, and precisely moving 11,000 tons of steel in winds up to 40 miles per hour blowing from varying directions.

“As much as fans love seeing the sky, in this stats-heavy game, baseball fans also believe the Blue Jays do better when the roof is open which has made the roof an integral part of the game and the fan experience,” said Mark Niesner, Director of Operations and Organizational Development, New Electric, the general contractor for the Rogers Centre’s roof-related renovations.

To continue meeting the expectations of fans and promoters, the roof’s infrastructure required significant upgrades, including a new OT (Operations Technology) network and control system, which help management determine when to close the roof and provide them the ability to once again do so reliably. “Basically, what this project was about was getting this structure and the operating system back to a state where it can sustain for the next 15 to 20 years,” explained McCormick.

Successful replacement of the aging stadium roof OT network and controls system was completed through a number of organizations working in partnership. New Electric, acting as prime and electrical contractor, provided project management, electrical solutions and mechanical support. Rockwell Automation and Cisco provided product and technical expertise. Gerrie Electric provided product and assisted in testing and design. JMP Engineering provided the knowledge, experience and execution of the design installation and commissioned the entire control system.

Rogers Centre selected the team due to their combined proven expertise in successfully delivering critical projects. It was also important to Rogers that the partners had the ability to locally service and support the system during and over the life of the roof. For over 10 years, New Electric has managed Rogers Centre’s requirements, for everything from the roof and its power and control systems to its concession stands and ATMs, lights and the Blue Jays’ locker rooms. As a result, New Electric really understands Rogers Centre, its culture and unique requirements.

“Looking ahead, Rogers Centre committed to leading edge, proven technology to meet today’s standards,” said Steve Szamocki, Executive Vice President of Sales and Marketing, JMP Engineering. “Twenty-five years ago, this technology was leading edge but increasingly, these legacy systems had become a challenge to support effectively and efficiently.”

“Rockwell Automation is excited to have our PowerFlex® variable frequency drive solutions and ControlLogix® PLC’s be a cornerstone of this highly visible and critical roof modernization project,” said Mike Laszkiewicz, Vice President & General Manager, Power Control Business, Rockwell Automation. “Rogers Centre will now be able to achieve greater efficiency and reliability by integrating the roof system with the network and our control system, a vision that Rockwell Automation calls the Connected Enterprise.”

Completion of this retrofit required approximately two years, $10 million and close to 30 people simultaneously working full-time on the renovation. Thanks to the upgrades, the roof once again performs optimally, easily and with absolute reliability. To help Rogers Centre keep fans dry, New Electric also installed a rooftop weather station that tracks weather systems to predict when the rain or cold front will arrive.

While the opening and closing still requires a full crew to operate safety, the control system now only needs one person to monitor the process. The entire process can be completed with a 46% speed improvement as compared to the legacy control system. Also, of significant value to Rogers Centre, the enhanced functionality of the modern control system and its supporting OT network provides fault tolerance, self-diagnostics, and reporting previously not available, allowing the operator an easy and quick way to trouble-shoot and rectify any issues, should they arise.

“As general contractors, we can take on far more than the electrical and had the resources to accommodate Rogers Centre’s incredibly full event schedule,” said Niesner. “We don’t come in to just hook up wires – we’re here to help Rogers Centre give the fans a fantastic experience.”

New Electric

Related Articles


Latest Articles

  • ESA Provides an Update on its New Self-Serve Licensing Platform

    ESA Provides an Update on its New Self-Serve Licensing Platform

    March 27, 2026 In October 2025 Electrical Safety Authority (ESA) officially launched its new self-serve licensing platform, a modern system designed to transform how Master Electricians (MEs) and Licensed Electrical Contractors (LECs) manage their licensing needs. The platform replaces paper-based processes and provides a centralized, web-based experience for renewing and applying for licences, paying fees Read More…

  • BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    March 27, 2026 Starting April 1, 2026, our battery rebate offer is changing. The offer will include: Applications submitted before April 1, 2026, will be reviewed under the current rebate amounts. New requirement for working with contractors Beginning June 1, 2026, solar and battery installations must be completed by a Home Performance Contractor Network (HPCN) member to Read More…

  • CSA Report: Online Sales of Unapproved Consumer Electrical Products in Canada

    CSA Report: Online Sales of Unapproved Consumer Electrical Products in Canada

    March 27, 2026 Canadian electrical regulators have identified that the online sales of unapproved consumer electrical products are of a serious concern, and with the growing number of online marketplaces globally there is likely a higher volume of unapproved, or non-compliant, consumer electrical products available for purchase to Canadian consumers. In 2025, Canadian Standards Association Read More…

  • Tackling Unsafe Electrical Products Sold Online: Key Outcomes from the National Workshop Agreement 

    Tackling Unsafe Electrical Products Sold Online: Key Outcomes from the National Workshop Agreement 

    March 27, 2026 By Electro-Federation Canada The rapid growth of e-commerce has transformed how Canadians purchase electrical products, but it has also introduced new safety risks. EFC members have been raising concerns for several years about the increasing availability of unsafe and unapproved electrical products sold online, often without clear evidence of certification or compliance with Canadian requirements. To Read More…


Changing Scene

  • Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    March 27, 2026 — Skills Ontario welcomes the 2026 Ontario Budget: A Plan to Protect Ontario, released today by the Ontario Government and Minister of Finance Peter Bethlenfalvy, and applauds the continued commitment to investing in skilled trades, technologies, and workforce development. Skills Ontario was pleased to see the government maintain and strengthen its support Read More…

  • Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    April 27, 2026 Toronto Hydro is launching a trailblazing customer pilot project designed to help local builders electrify multiplex housing without complex service upgrades. Through Toronto Hydro’s Multiplex PowerPlay, up to six multiplex projects can qualify to receive funding toward a smart energy load management system. Smart load management systems continuously monitor total building energy Read More…

  • Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    March 25, 2026 Gescan, a Sonepar Company, is proud to highlight its continued commitment to supporting communities across Saskatchewan through their meaningful alliance with George Gordon Developments Ltd. (GGDL). With a strong focus on community development, workforce participation and inclusive growth, Gescan is working closely with GGDL to create training, employment and business opportunities for Saskatchewan residents. These efforts are particularly focused on supporting individuals Read More…

  • Electric Avenue Launches Incentive Program for EV Charging Installers

    Electric Avenue Launches Incentive Program for EV Charging Installers

    March 23, 2026 Halifax-based EV charging solutions provider Electric Avenue has announced the official launch of its new Contractor Incentive Program, a first-of-its-kind initiative in the EV charging industry, built exclusively for contractors who have completed the company’s Installer Certification course. The program rewards certified installers for every verified and networked installation they complete, offering cash Read More…