The Future is Now: Opportunities for Canada’s Maturing Wind Farms

Wind Farms

 

August 11, 2017

In Canada, we have 6,364 commercial scale wind turbines in operation today.

Until recently, keeping track of this number has been a matter of simply adding new installations to the number from the year before. However, now the equation has changed to include subtracting some active turbines from the total. That’s right, a few wind farms have come to the end of their lifecycle and have been decommissioned, taking some hard working machines offline.

This is through no fault of their own; the turbines simply reached the end of their predicted lifecycle. In fact the ones I’m thinking of were operational beyond their expected 20 years of service. The Cowley Ridge wind farm in Alberta has received a lot of attention in the wind business as a pioneering Canadian decommissioning experience. Built in 1993 this facility operated 57 wind turbines for about three years past their planned lifespan. This impressive accomplishment gives operators and manufacturers of newer machines increased expectations of what can be accomplished in the future.

Decommissioning refers to when a wind farm’s power production is ceased and the above ground equipment is dismantled and land restored.

Repowering refers to replacing or upgrading aging equipment with more advanced and efficient technology. This can mean fewer, but more powerful turbines that can produce equivalent or greater levels of electricity.

Most early wind farm developers planned for decommissioning at the end of the lifecycle. However, this is starting to change. If you research information from other countries that have older fleets you start to notice a trend.

Wind farm owners are increasingly opting to repower.

This is because the free fuel they’ve been using (the wind) is still there, as is the investment in roads, buildings, cabling, etc. There are also substantial sweat equity investments into building a competent team to run the operation and community engagement efforts to ensure landowners and neighbours are being supported.

In Canada, the option to upgrade and continue producing power hasn’t been widely implemented yet because there are very few turbines that have passed their expected lifetime. But as the number of turbines reaching the end of their lifecycle continues to increase (400 wind turbines by 2030) so too will the opportunity and incentive to repower these facilities.

In order to stimulate discussion on this topic, CanWEA has developed a primer entitled, “Decommissioning or Repowering a Wind Farm” in collaboration with the industry. I encourage you to explore this resource for Canada’s maturing wind turbine fleet. It certainly is an exciting development in Canada’s renewable energy future.

http://canwea.ca/blog/2017/08/03/future-now-opportunities-canadas-maturing-wind-farms/

Related Articles


Latest Articles


Changing Scene

  • SATCO Celebrates 60 Years of Excellence in Lighting, NUVO Marks 20 Years of Design Innovation

    SATCO Celebrates 60 Years of Excellence in Lighting, NUVO Marks 20 Years of Design Innovation

    April 10, 2026 SATCO proudly announces the celebration of its 60th anniversary, marking six decades of sustained growth, innovation, and service excellence. Concurrently, NUVO, a prominent lighting brand under the SATCO umbrella, celebrates its 20th anniversary, highlighting two decades of cutting-edge design and creative solutions for residential and commercial spaces. Founded in 1966, SATCO has Read More…

  • D.A.D. Sales Welcomes New Team Members

    D.A.D. Sales Welcomes New Team Members

    April 10, 2026 D.A.D. Sales announced the addition of Bradey Cameron as an Application Specialist on the D.A.D. Sales Solutions team, Katherine Dickson as an Account Manager on the D.A.D. Sales team, supporting Northern Alberta, and Wendy Dyble as an Account Manager / Inside Sales on the D.A.D. Customer Service Team. “Bradey brings a strong Read More…

  • Liteline Introduce New Regional Sales Manager for GTA

    Liteline Introduce New Regional Sales Manager for GTA

    April 10, 2026 Liteline announced on LinkedIn that Peter McCumber has joined their team as Regional Sales Manager for the GTA. “We are excited to welcome Peter as Liteline’s Regional Sales Manager-GTA! Peter brings more than two decades of experience in the electrical manufacturing and wholesale industry, where he has established himself as a dynamic Read More…

  • Dixon Relocates Mississauga Branch to Better Serve Customers

    Dixon Relocates Mississauga Branch to Better Serve Customers

    April 10, 2026 Dixon proudly announces the relocation of its Mississauga branch to 6197 Kennedy Road, enhancing accessibility and customer convenience. Strategically positioned along a busy corridor with excellent access to Highways 401, 410 and 403, the new 14,000-square-foot facility offers improved convenience for customers and partners. The branch features a modern storefront, an enhanced Read More…